Project Evaluation and Control

Similar presentations


Presentation on theme: "Project Evaluation and Control"— Presentation transcript:

1 Project Evaluation and Control
Chapter 13 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

2 The Project Control Cycle
Setting a Goal Taking Action and Recycling the Process Measuring Progress Comparing Actual with Planned Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

3 The Project S-Curve Elapsed Time (in weeks) 10 5 45 40 35 30 25 20 15
50 60 Cumulative Cost ($ in thousands) Cumulative Budgeted Cost Cumulative Actual Cost $10,000 Negative Var Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

4 Milestone Analysis Milestones are events or stages of the project that represent a significant accomplishment. Milestones show completion of important steps signal the team and suppliers can motivate the team offer reevaluation points help coordinate schedules identify key review gates delineate work packages Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

5 Tracking Gantt Chart Project status is updated by linking task completion to the schedule baseline Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

6 Earned Value Management
Project S-Curves Cost Performance Schedule Cost Performance Schedule Earned Value Schedule Cost Performance Tracking Control Charts Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

7 Earned Value Terms Planned value (PV) Earned value (EV)
Actual cost of work performed (AC) Schedule performance index (SPI) Cost performance index (CPI) Budgeted cost at completion (BAC) Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

8 Steps in Earned Value Management
Clearly define each activity including its resource needs and budget Create usage schedules for activities and resources Develop a time-phased budget (PV) Total the actual costs of doing each task (AC) Calculate both the budget variance (CV) and schedule variance (SV) Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

9 Earned Value Milestones
PV EV AC Slip Overspend Schedule Performed Actual Budget Cost Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

10 Earned Value Example Value 8=80%(10) Activity Jan Feb Mar April Plan
Staffing 8 7 15 100 Blueprint 4 6 10 80 Prototype 2 60 Design 3 33 1 Mon Plan 17 38 30 Cmltv 21 Mon Act 11 13 Cmltv Act 19 27 40 Earned Value 30= Planned Value 38= Cumulative 40= Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

11 Earned Value Example Schedule Variances
Planned Value (PV) = 38 = Earned Value (EV) = 30 = Schedule Performance Index = .79 = 30/38 = EV/PV Estimated Time to Completion = (1/.79)x4=5 Cost Variances Actual Cost of Work Performed (AC) = 40 = Cost Performance Index = .75 = 30/40 = EV/AC Estimated Cost to Completion = = (1/.75)x38 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

12 Completion Values in EVM
Accurate and up-to-date information is critical in the use of EVM 0/100 Rule 50/50 Rule Percentage Complete Rule Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

13 Human Factors in Project Evaluation & Control
Optimistic progress reports Level of detail Process evaluation Non-technical performance measurement Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

14 Critical Success Factors in the Project Implementation Profile
Project mission Top management support Project plans & schedules Client consultation Personnel Technical tasks Client acceptance Monitoring & feedback Communication channels Troubleshooting Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

15 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall