Earned Value Measures Planned Value (PV) Earned Value (EV)

Similar presentations


Presentation on theme: "Earned Value Measures Planned Value (PV) Earned Value (EV)"— Presentation transcript:

1 Earned Value Measures Planned Value (PV) Earned Value (EV)
Baseline cost of work scheduled BCWS Earned Value (EV) Baseline cost of work completed BCWP Actual Value (AC) Actual cost of work completed ACWP

2 BCWS BCWP ACWP Baseline cost of work scheduled
Baseline cost of work performed ACWP Actual cost of work performed

3 EAC BAC VAC Estimate at Completion Budget at Completion
Variance at Completion

4 SV CV Scheduled Variance BCWP-BCWS How much done vs how much planned
SV is positive = Ahead of schedule CV Cost Variance BCWP-ACWP Baseline cost vs Actual cost CV is positive = Under budget

5 SPI CPI Scheduled Performance Index BCWP/BCWS
SPI< 1 = Project behind schedule CPI Cost Performance Index BCWP/ACWP CPI> 1 = Project is under budget

6 TCPI To Complete Performance Index
Ratio of Remaining work vs Remaining budget TCPI> 1 = Over budget TCPI< 1 = Under budget

7 Earned value > Planned Value = More work done than we planned

8 Earned value > Actual Cost = Baseline cost higher than actual, we are under budget