Earned Value SOS section 3.7 1 541Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much.

Similar presentations


Presentation on theme: "Earned Value SOS section 3.7 1 541Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much."— Presentation transcript:

1 Earned Value SOS section 3.7 1 541Sp8Jan24ev3

2 Earned Value Analysis One approach to measuring progress in a software project is to calculate how much has been accomplished. This is called earned value analysis. It is basically the percentage of the estimated time that has been completed. Additional measures can be calculated. Although this is based on estimated effort, it could be based on any quantity that can be estimated and is related to progress. 2 541Sp8Jan24ev3

3 Basic Measures - 1 Budgeted Cost of Work (BCW): the estimated effort for each work task. Budgeted Cost of Work Scheduled (BCWS): the sum of the estimated effort for each work task that was scheduled to be completed by the specified time. Budget at Completion (BAC): the total of the BCWS and thus the estimate of the total effort for the project 3 541Sp8Jan24ev3

4 Basic Measures - 2 Planned Value (PV): the percentage of the total estimated effort that is assigned to a particular work task. PV = BCW/BAC Budgeted Cost of Work Performed (BCWP): the sum of the estimated efforts for the work tasks that have been completed by the specified time. Actual Cost of Work Performed (ACWP): the sum of the actual efforts for the work tasks that have been completed 4 541Sp8Jan24ev3

5 Progress Measures Earned Value(EV)= BCWP/BAC the sum of the PV’s for all completed work tasks Schedule Performance Index (SPI) = BCWP/BCWS Schedule Variance (SV) = BCWP – BCWS Cost Performance Index (CPI) = BCWP/ACWP Cost Variance (CV) = BCWP – ACWP 5 541Sp8Jan24ev3

6 Example – as of 4/1/08 taskEst effort Actual effort Est Comp Date Actual Date Comp 175601/25/082/1/08 225402/15/08 3120805/15/08 440504/15/084/1/08 560507/1/08 680709/01/08

7 For next Tuesday – 1 or 2 people u Use the data from slide 6. Assume that the rest of the tasks finish 1 month late. u Calculate EV, SPI, SV, CPI, and CV at half month intervals from Jan 1 through the finish of the project. u Plot the values as line graphs. Turn in hard copy of the spreadsheet and the graphs. u 25 points 7 541Sp8Jan24ev3

8 Tuesday, Jan 29 – post mortem u Read two articles –Anreas Birk,”Postmortem: Never Leave a Project without It” –June Vernier “In-House Software Development: What Project Management Practices Lead to Success” –Making Meaning for each – upload together on Monday 8 541Sp8Jan24ev3