Hybrid and Module Status 1. Hybrid Delivery First hybrids over-etched and shrunk due to changes in design and mistakes in manufacturing – Shrinkage for.

Slides:



Advertisements
Similar presentations
23-Aug-2005 VELO Production UCD VELO Module Production at Liverpool T. Bowcock.
Advertisements

Status of Sensor and Hybrid Production LHCb Zurich Week T. Bowcock.
Lyon Gantry Status TEC meeting Dec D. Contardo Module production in Lyon Rigidifier test on R4 Frame tolerance effect on assembly plates Short term.
Stave Vacuum Tool Tim WP4 Face to Face Liverpool, 13/11/14.
Stave Hybrid Status Ashley Greenall 1. Current Status Current build of hybrids (Version 3) distributed to 6(+1) sites: Cambridge, DESY, Freiburg, LBL,
ATLAS Module building at Glasgow
Design Ash finished electric hybrid tracing to connector fields –Changes to allow for HCC-less and HCC running on one hybrid awaiting final confirmation.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
AMS-02 tracker mechanics status of assembly and integration Inner tracker integration completion: - Assembly and cabling - Temperature and magnetic field.
The AMS-02 detector is based on a large acceptance (~0.5 m²sr) and high sensitivity spectrometer composed by a super-conducting magnet (0.8 T), cooled.
G.Barber Mice Tracker Mechanical Progress Imperial Tracker Update Contents:- Components Station Layout Light Guide Map QA Patch Panel Alignment.
QA during Stave Core Assembly Stephanie Qing Yang (Oxford) 25 th Sept 2014 WP4 f2f meeting at RAL.

VELO upgrade electronics – HYBRIDS Tony Smith University of Liverpool.
Tooling and assembly of US stavelet at Berkeley S. Díez Cornell, C. H. Haber, M. Defferrard, R. Witharm Sept 6th, 2012 Berkeley mechanical meeting, 5th-7th.
March 20, 2001M. Garcia-Sciveres - US ATLAS DOE/NSF Review1 M. Garcia-Sciveres LBNL & Module Assembly & Module Assembly WBS Hybrids Hybrids WBS.
ATLAS Tracker Upgrade Stave Collaboration Workshop Oxford 6-9 February 2012 ABC 130 Hybrid.
Status Brussels GANTRY Ê Assembly of R3 modules (36 modules) 4 precision of the modules 4 problems with DataBase (not adapted for single sensor modules)
Update on alignment kit and stave 250 frame M.Gibson (RAL) 1.
TPAC progress Jamie C 29 th July TPAC1.1 Status Submitted 17 th –Some minor DRC errors found at foundry –Corrected/waived Re-Submitted 23 rd July.
1 WP3 Bi-Weekly Meeting Activities at Liverpool 1.Evaluation of Compact DCDC converter Designed to match up to an ABC130 module 2.Status of FIB’d hybrid/module.
Update on new alignment kit update 20/3/ Complete table based on a standard table (2400 x 1200 x 150) and a half table (2400 x 600 x 150).
Malte HildebrandtDC Status Report, Dear MEG Committee,PSI, April 14 th 2009 this is the first report concerning the drift chamber status as.
ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused.
Update on Alignment kit and Stave 250 frame and thoughts for Stave 130 M.Gibson (RAL) 2/5/13 1 Status of the frame for stave 250 Status of infrastructure.
G.Barber: Mice-International Meeting Plans for Sci-Fi Prototyping. Contents:- Mechanical Layout of Sci-Fi Design of the Fibre Optic Connectors.
Stave Module Status Tony Affolder The University of Liverpool On behalf of cast of thousands… ATLAS Upgrade Week November 10,
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
Abe Seiden December 2003 SCT Week S USA SCT Barrel Module Assembly SCT Week CERN December 2003 Presented by Abe Seiden U.C. Santa Cruz.
March OsC Report and Restructuring WP4. OsC Report 4.1 Tapes Bus tape designs have been completed for modules with 130nm ASICs which incorporate options.
And now for something completely different First results from the DC-DC Stavelet Peter & Ashley with Giulio & John.
DOE Rev of Run IIb Sep 24-26, Detector Production WBS James Fast Fermilab.
SCT Week 2 Oct 2002N.P. Hessey NIKHEF1 Status ATLAS SCT 2002 NIKHEF Contributions to ATLAS: Magnets – discussed by Frank Trigger DCS Muon MDT and alignment.
Assembly Procedure ALICE Outer Barrel Stave 14 Module 2 Cold Plates 1 StaveMarco Kraan Paul Kuijer.
Thermo-mechanical petal status Sergio Díez Cornell 23Jan 2015.
BNL Role In ITK 1.Current R&D Roles 2.Proposed Production Role 3.Activities now until TDR (early 2017) 4.Resources and Infrastructure 5.Personnel 1 D.
Chiho Wang Duke University 1 TRT Barrel integration Status / Schedule Chiho Wang.
Hybrid Mechanical/Thermal Design Ray Thompson / Manchester FP420 meeting Torino 11/12 July 06.
Stave Hybrid/Module Status. Modules Stave Module Building 2 Mechanical Chip Gluings Mechanical Wirebonding Electrical Chip Gluings Electrical Wirebondings.
QMUL 2/2/12 1  Current status of new alignment system.  Drawing status update.  Laser alignment.  Module removal from frames for new kit.  Stave(lets.
D. Greenfield CLRC1 UK-V End-cap Engineering 15 July 2003 Debbie Greenfield, RAL.
PASI OsC meeting 12th July 2012
Gluing, measuring and shearing Heated plate curing Is the process feasible? Tests with 130nm hybrids Measure resulting glue thickness Determine the shear.
G.Barber Mice Tracker Mechanical Progress Tracker Mechanical Progress Contents:- Station Space Frame Station Layout Light Guide Map Connectors Patch.
WP3 Meeting 8 th October 2015 Power Boards for TM stave status 30 boards received and tested – targeted for TM modules Testing communication with 1-wire.
PS Module Ron Lipton, Feb A bit of History During much of the conceptual design phase of the outer tracker we had focused on the “long barrel”
WP7&8 Progress Report ITS Plenary meeting, 10 June 2014 LG, PK, VM, JR.
D0 PMG, May 04, 2000 Slide 1 Schedule DØ SMT Status Report.
Module Assembly Jig Status Cambridge and DESY came to Liverpool Nov. 15 th -16 th for training on module assembly – A complete jig set was sent back with.
DOE CD-2/3a Review of the BTeV Project – December 14-16, BTeV Pixel Detector Pixel Module Assembly and Half-Plane Assembly Guilherme Cardoso James.
Origami and PA design 6 February 2012 Christian Irmler (HEPHY Vienna) 1 Common SVD-PXD Meeting.
Progress on Stave assembly tooling Stephanie Yang (Oxford) WP4 meeting at Liverpool University, 13 th November 2014.
PACKAGE FABRICATION TECHNOLOGY Submitted By: Prashant singh.
25th April 2013 C. Irmler (HEPHY), Y. Onuki (IPMU) Ladder Assembly Procedure Belle II – New Collaborators Meeting.
Thoughts about PS module assembly Ulrich Heintz, Meenakshi Narain, Bill Patterson, Eric Spencer, Juan Trenado Brown University, Providence 4/16/2015Heintz,
The STS-module-assembly:
BM&N STS ladders assembly in VLHEP
Berkeley status Aug 10th, 2012.
ATLAS pixel module assembly flow
What is Stave Carrier Frame Required to Do?
Ladder Assembly All tools and jigs produced Glue dispensing works
BSS Prep work at CERN and Acceptance of Parts
Ladder Assembly All tools and jigs produced Glue dispensing works
Gluing jigs for Demonstrator
Equipment for Assembly – UK Experiences
HIC Assembly - Liverpool
Status Brussels GANTRY
Flex Status A.Nomerotski, 4 May 2010.
LPKF Laser Direct Structuring System
Presentation transcript:

Hybrid and Module Status 1

Hybrid Delivery First hybrids over-etched and shrunk due to changes in design and mistakes in manufacturing – Shrinkage for both circuits and alignment holes To use at all have to re-drill holes, hand solder all surface mounts, re-set all wire bonds – Build also not as expected 2 bond-ply between ground and shield layers, 9  m instead of 5  m copper for two layer, 35  m instead of 5  m copper for shield Modifications to design to make manufacturing easier submitted by Nov. 1 st, production are supposed to have started on the Nov. 9 th – Misunderstanding by vendor lead to devices manufacture to start on Dec. 3 But have improved communication path to track progress, confront problems, etc. Build is back to original specifications. New understanding on the method to locate the tooling holes 2

Hybrid Delivery (cont) Thus, the delivery is now delayed relative to AUW schedule – Foresee delivery week before Christmas First pieces back from passive stuffing 2 nd -3 rd week of January – First working re-spun hybrid last January-early February To keep closer to schedule and get experience, we are populating 3 hybrids with over-etched, shrunk circuit now to start program 3

Module Fixturing Status ConceptDrawingManufactureTestingFinalETA Chip TrayNov Vacuum Placement Chuck Nov Hybrid Bonding JigDone Module Assembly Plate Late Nov (Dec)  Module FrameLate Nov (Jan)  Module Bonding Plate Late Nov (Dec)  Module Testing BoxJan Design/manufacture/testing processing well, in the order needed. Progress since AUW in grey arrows. Slightly off schedule due to unanticipated testing of BCC and emergency work in shop for another project 4

Asics ‘Set out’ jig Material :- Acetal (Static Dissipative) Chip Tray 5 Second version made. Chips and pickup tool fit snugly. Vacuum removed ASICs cleanly Trialling multiple pickup trial to ensure ASICs aren’t damaged.

Material:- top Aluminium bottom Acetal Location dowels Face contacts ASICs Vacuum Placement Chuck 6 Second version finished. Fits all jigs and has be levelled on legs. Checking placement accuracy of ASICs after pickup trialling

Hybrid Bonding Jig First version finished – Used successfully to bond first ASICs Will make second version with separate vacuum areas for each hybrid – Easier repair cycles – Will only happen after first few modules finished 7

Dowel holes for Placement chuck (In shop) Height setting pins (In shop) Vacuum holes Dowels stops for Silicon Vacuum port Module Assembly Plate 8 Dowels being finished this week. Next week, we will start smart scope measurements of the placement accuracy achievable for silicon relative to hybrid pins Will need to grind height setting pins to set correct glue level. Will attempt first super-mechanical in early January

With now machine rebate for module at Liverpool Machined “mechanical” blank to continue assembly testing Used for:- Electrical testing Assembly movement Storage Ready to submit today. Will get just before Christmas Module Frame 9

Test Assembly 10 With mechanical sensor, failed electrical hybrids, and mechanical frame, we have shown that everything “fits” together After gluing, we will be able to give precisions of the assembly

Dowel locators Vacuum Module Bonding Plate 11 Dowels in shop. Fits on wirebonder. Will be ready in time for first assembled module

Short Term Plans Using over-etched electrical hybrids, we will die- attach, wire bond and test 3 hybrids with proper jig set – Hopefully the first before Christmas With 1 electrical and 1 mechanical, and “failed” electrical sensor, we will assemble, bond, and test 1 module in first 2 weeks of January Hope to use the other 2 hybrids with FZ2 sensor to make first module for stavelet program following this first piece 12

Overall Time Schedule Finish all jigs needed to assemble and bond module- before Christmas (with minor tweaks afterward) Super-mechanical modules- early January Bond/test “over-etched” electrical hybrids- December-early January Receive new electrical hybrids- before Christmas ?? QA and passive attach-early Jan Assemble/bond/test first “over-etched” electrical module with best method available- Mid-Jan – This is the first test of single-sided module with correct grounding/HV filter, still some concern about noise performance with two hybrids on one sensor Assuming first assembly ok, will make next 4 modules in February –Maybe we should have a working meeting at Liverpool of the future module assembly sites at this point to discuss results Depending on results of first mechanical assemblies and electrical tests, put out jigs sets to industry for other single-sided module build sites in March/April 13