Update on new alignment kit update 20/3/12 1. 2 Complete table based on a standard table (2400 x 1200 x 150) and a half table (2400 x 600 x 150).

Similar presentations


Presentation on theme: "Update on new alignment kit update 20/3/12 1. 2 Complete table based on a standard table (2400 x 1200 x 150) and a half table (2400 x 600 x 150)."— Presentation transcript:

1 Update on new alignment kit update 20/3/12 1

2 2 Complete table based on a standard table (2400 x 1200 x 150) and a half table (2400 x 600 x 150).

3 Two granite tables to go to two different establishments. 3 RAL’s table.....2400 x 1100 x 150 + Holes for stages Liverpool table...2400 x 600 x 150

4 Add picture of items in R56 4

5 Granite Status Granite (+2 sets of legs) delivered to RAL on the 19 th... yesterday! The smaller piece delivered to Liverpool yesterday too. Installation in the R12 clean rooms expected Thursday 29 th (first day heavy gang is free and I am at RAL) To set up the granite level will take about half a day. It will then take a further 2 weeks (my weeks) to reinstate the frame, interlocks and cabling so April 19 th we should be back where we were but on a granite table 5

6 6 Top view of placement jig Y adjustment X and Theta adjustment

7 Drawings/production Real drawings are now in exsistnace (rather than a model) We have had round 1 where Ian and I have commented on some features. We are now waiting for a second iteration. We are concentrating on the ‘bridge ‘ structure first and the associated walls. The cantilever we will tackle second. The plan is to construct 4 bridge structures but all the wall positions. There will be no prototypes just the 4 items that we will alter as appropreate. No fancy finishes for these ‘prototype’ items Waiting for the Ok to buy the bought in items such as dowels and bearings 7

8 Timescale to aim for activityEnd dateTime to complete Note to self.. Last round of drawings23rd MarchOrder up commercial items granite installed29 th March Refit frames safety cables5 th April2 weeks Restart software development Sp stavelet to populate, also several pipes to pressure test. Unspecified start time but schedule says end March 2 weeks Install vacuum system3rd May1 week Install fume extraction10 th May1 weekNeed to buy suitable pipes etc Install storage17 th May1 weekCheck drawings and get items ordered Expected delivery of manufactured items Mid May1 month from start Fit and make work ???? Adhesive tests to perform2 weeks 8