D0 PMG 4/19/01 Completed Reportable Milestones MilestoneBaselineActualVar. H Half-Wedge Fabrication 20% Complete 10/15/99 0 w 3 Chip Ladder Fabrication.

Slides:



Advertisements
Similar presentations
DoE Review June 6-7, 2000 Current Detector Configuration June 6, 2000  Solenoid, Central Preshower installed in central bore  A-layer MDTs installed.
Advertisements

1 Status of the CMS Pixel project Lorenzo Uplegger RD07 Florence 28 June 2007.
Status of Eric Kajfasz CPPM/Fermilab GDR-Susy, Lyon - 26 novembre 2001.
All DØ Meeting December 1, 2000 Uncle DØ Needs you!!! Commissioning Status & Plans Jae Yu All DØ Meeting Dec. 1, 2000 What have we been doing? What is.
Detector Systems Update MICO Feb 25, MICE Detector Systems  CKOV u CKOV installation planned during March shutdown u Cable issues resolved. Geneva.
PXL Electronics Status update for HFT TC meeting on May 11, 2010 at LBNL 1HFT TC 05/11/ LG.
13 January All Experimenters’ MeetingAlan L. Stone - Louisiana Tech University1 Data Taking Statistics Week of 2003 January 6-12 We had to sacrifice.
David L. Winter for the PHENIX Collaboration PHENIX Silicon Detector Upgrades RHIC & AGS Annual Users' Meeting Workshop 3 RHIC Future: New Physics Through.
1 November 18, 2014 DOE SC-OPA Review of 12 GeV ENC vs. preamp load FSSR2 by FNAL Single chip on a PCB Load from capacitors SVT module testing.
M. Gilchriese ATLAS Upgrade Introduction January 2008.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
1 Re-gas compressors to 2.20 Mpa - Me New oil mist adsorbers in compressors at 20k hrs – Me Comp1 11K hrs, Comp2 11K, Comp3 20K, Comp4 18K Service cold.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
Figure 1: ICD Single Channel Block Diagram Schematic PMT High Voltage Supply (see Figure 4 & 4a) LED Pulser PMT Calibration (see Figure 6) ICD Scintillator.
Collaboration Mtg Cotober 11, 2000 Installation Status Opening Remarks Overview, logistics Recent events, status Outlook, concerns Conclusions Jon Kotcher.
NIU Trigger Workshop CTT Commissioning Trigger Workshop October 22, 1999 WBS & Presented by Fred Borcherding for the D0 Electronics Group.
D0 PMG 12/2/99 Fiber Tracker Status  Carbon fiber work u All support cylinders done u Some work remains on band/support pieces + work for Silicon Detector.
10-25 years of DØ FranceE. Kajfasz1 -France RunII RunIITracking Hard/Soft-ware with.
Tracker Summary Alan Bross MICE CM October 10, 2007.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
22 June 2000 D  NIU Workshop S. Doulas From Detector to Ntuples: Muons Steven Doulas Northeastern University Boston, MA D0 Muon Upgrade Group.
This presentation will probably involve audience discussion, which will create action items. Use PowerPoint to keep track of these action items during.
17 February All Experimenters’ MeetingAlan L. Stone - Louisiana Tech University1 Data Taking Statistics Week of 2003 February Dedicated some.
D0 Collab Mtg Feb 7, 2001 D0 Detector: Status for Run 2 Wistful reminiscences Near term: Roll in, detector status, next few weeks Latest from Beams Division.
Mikhail Kubantsev - Kansas State University 1 Assembly of a Large Area Microstrip Silicon Tracker Some Experience of Construction of D0 SMT H- disk Silicon.
2 Silicon pixel part Done and to be written Written! Under way To be done Introduction 1.Hybrid Pixel Assembly Concept 2.Silicon sensor 1.First thinned.
PMG, Aug 03, 2000 Slide 1 Schedule In preparation Done Started Done Started Half done.
HFT DOE Review July 17-18, 2012 The Silicon Strip Detector WBS 1.4 Jim Thomas Lawrence Berkeley National Laboratory SSD.
7 Feb 2005T. Yasuda, Fermilab D0 Status Report 2/7/2005 Taka Yasuda Fermilab.
Fermilab PMG Jan 20, 2000 Reconsideration of the Installation at D0  Overview  Major constraints  Basics of old, new schemes  Some details on each.
Forward Muon Installation and Commissioning Dmitri Denisov Fermilab Director’s review 7/12/1999 Plan Forward muon detectors Mini-drift tubes installation.
L0 Technical Readiness Review-Electronics Installation Linda Bagby L0 Electronics Installation  System Electronics Overview u Low Voltage s Filter.
D0 Status: 01/14-01/28 u Integrated luminosity s delivered luminosity –week of 01/ pb-1 –week of 01/ pb-1 –luminosity to tape: 40% s major.
All Experimenters MeetingDmitri Denisov Week of July 7 to July 15 Summary  Delivered luminosity and operating efficiency u Delivered: 1.4pb -1 u Recorded:
FNAL PMG Feb 5, DØ RunIIb Trigger Upgrade WBS 1.2 Paul Padley, Rice University for the DØ Trigger Upgrade Group.
Director’s Review Feb 3-4, Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.
M. Brooks DC Meeting, 15-Sep-00 MuTr Mechanics Status SOUTH ARM: Chambers fabrication complete Stations 2+3 installed Station 1 test-installed will be.
D0 PMG 6/15/00 PMG Agenda June 15, 2000  Overview (Tuts) u Detector status u Reportable milestones u Financial status u Summary  Response to DOE review.
US CMS DOE/NSF Review, May Cal. Trig. 4 Gbaud Copper Link Cards & Serial Link Test Card - U. Wisconsin Compact Mezzanine Cards for each Receiver.
D0 Status: 04/01-04/08 u Week integrated luminosity –1.7pb -1 delivered –1.5pb -1 utilized (88%) –1.1pb -1 global runs u Data collection s global data.
Proposed full upgrade of the L1CTT/DFE for Run2b Meenakshi Narain Boston University Outline: Proposal Reviewers comments and responses Schedule Cost.
FNAL All Experimenters Meeting January 7, Leslie Groer Columbia UniversityDØ Status 1 DØ Status and Progress Dec 17, 2001 – Jan 7, 2002  Reasonably.
February 24, DØ’s VLPC Detectors: The Fiber Tracker and Preshowers Greg Davis University of Rochester.
D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K.
Nirmalya Parua March 25-29, 2002 The RunII D0 Calorimeter Electronics Upgrade & Its Performance Nirmalya Parua State University of New York Stony Brook.
DoE Review June 6-7, 2000 Installation and Commissioning of the D0 Detector Overview since last review Organization Current status Installation sequence,
Plans to Test HBD Prototype in Run 6 Craig Woody BNL DC Meeting March 8, 2006.
1 KU MRI What is the MRI? What is KU doing? Firmware/testboards Optical hybrids Sensors.
D0 PMG February 15, 2001 PMG Agenda February 15, 2001  Overview (Weerts) u Detector status u Reportable milestones u Summary  Operations Organization.
D0 PMG 2/3/00 PMG Agenda Feb 3, 2000  Overview u Project Manager’s Report – Tuts u Fallback options – Weerts  Silicon Support Cylinder Modifications.
2000 IEEE NSS Lyon,France Oct Hervé Lebbolo LPNHE ParisDØ Calorimeter Electronics Upgrade DØ Calorimeter Electronics Upgrade for Tevatron Run II.
04 Feb 03 Shutdown Activities Cryostat warm-up –Dilute contaminates Use purer helium on cooldown –Thermal stress test for cassettes –Move cassette from.
Director’s Review Dec 1999 DO Timeline Old Version J F M A M J J A S O N D J F M D Install silicon front-end ICD FPS Lum (L0) CFT install/hookup.
Collaboration Mtg April 14, 2000 DO Timeline J F M A M J J A S O N D J F M D Install silicon front-end ICD FPS Lum (L0) CFT install/hookup 1/2.
DON LYNCH OCTOBER 28, October 28, 2014 sPHENIX Detector Integration & Assembly Concept.
July 20, 2007Anita Topkar, BARC PSD Production: Present Status Dr Anita Topkar BARC.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
 94 LVPS Packages mounted 4’-25’ from the front-end electronics.  4 modules per package. u +5V& -5V “Digital”, +5V & -5V “Analog” 18 A 1A 18A 18Amps.
The ICD Project Alan L. Stone Louisiana Tech University All D0 Meeting - 7 September 2001.
Nikhef Scientific Meeting 2000Onne Peters D0 Muon Spectrometer December 14-15, Amsterdam Onne Peters Nikhef Jamboree 2000.
Arnd Meyer (RWTH Aachen) Sep 8, 2003Page 1 Integrated Luminosity Total data sample on tape with complete detector > 200pb -1.
Status of the CDF II silicon tracking system
MDT and analog FEE mass production:
DØ Upgrade Run II Introduction Physics Goals Tevatron Upgrade
New Calorimeter Trigger Receiver Card (U. Wisconsin)
L H C A T L A S International Collaboration on the LHC Project
RPC FEE The discriminator boards TDC boards Cost schedule.
Calice Tile-HCal and Tail-catcher/Muon Tracker
Calorimeter Upgrade The Tevatron and Dzero Upgrades
LIP and the CMS Trigger Upgrade On behalf of the LIP CMS Group
Presentation transcript:

D0 PMG 4/19/01 Completed Reportable Milestones MilestoneBaselineActualVar. H Half-Wedge Fabrication 20% Complete 10/15/99 0 w 3 Chip Ladder Fabrication 80% Complete 10/20/9910/26/990.6 w Arrival Of C-Layer MDT Modules At FNAL 10/22/9911/3/991.7 w 9 Chip Ladder Fabrication 20% Complete 11/3/9911/4/990.2 w M3-Fiber Tracker Ribbon Fabrication 50% Complete 11/12/9911/5/ w First Readout Crate Installed & Working 12/2/9911/16/99-2 w SCA Testing Complete12/15/9911/23/ w MDT ADB Fabrication Complete 12/2/99 0 w SLICs Received11/10/9912/10/994 w

D0 PMG 4/19/01 Completed Reportable Milestones (cont’d.) MilestoneBaselineActualVar. F Wedge Assemblies 20% Complete 1/19/001/24/000.4 w 6 Chip Ladder Fabrication 20% Complete 1/3/001/31/003.9 w MDC Fabrication Complete 12/13/991/31/005 w M2-Muon Electronics Preproduction Installation Complete 12/13/991/31/005 w M2-Fiber Tracker Assembly Begun 12/6/992/1/006.2 w M3-Establish Single Crate Internal Data Movement 1/6/002/17/006 w Shaper Hybrid 50% Complete 5/9/002/22/00-11 w All Pixel Octants Assembled 4/4/002/23/ w M3-1st Forward Preshower Detector Complete 1/12/002/24/006.2 w

D0 PMG 4/19/01 Completed Reportable Milestones (cont’d.) MilestoneBaselineActualVar. M3-Fiber Tracker Cylinders 8, 7, 6, and 5 Complete 1/28/003/2/005 w H Half-Wedge Fabrication 80% Complete 2/23/003/29/005 w M2-All Muon Forward Tracker MDT Modules At Fermilab 3/10/003/30/002.8 w (FPS) Module Fabrication and Testing Complete 12/10/994/1/0014 w M3-2nd Forward Preshower Detector Complete 3/8/004/3/003.6 w

D0 PMG 4/19/01 Completed Reportable Milestones (cont’d.) MilestoneBaselineActualVar. Steady DAQ Running3/31/003/17/00-2w M3-ICD Tile Modules/Boxes Ready 1/18/004/19/0013.2w FEB, CB Production Complete1/3/004/10/0014w M2-ICD Modules Arrive at Fermilab 1/25/004/24/ w M3-InterCryostat Detectors Installed 2/1/005/5/ w M3-Level Ø-South Installed2/9/005/8/ w M3-Fiber Tracker Ribbon Fabrication Complete 3/6/005/10/009.5 w M3-Fiber Tracker Ribbon Mounting Complete 4/20/005/13/003.3 w M2-Fiber Tracker Assembly Complete 5/4/005/26/003.3w M2-Calorimeter Preamp System Test Complete 3/31/007/13/0014.4w 6 Chip Ladder Fabrication 80% Complete 3/14/007/12/0016.8w

D0 PMG 4/19/01 Completed Reportable Milestones (cont’d.) MilestoneBaselineActualVar. Waveguide Production 50% Complete 1/29/007/24/0024.6w 10 Digital Boards Available3/22/007/28/0018w F Wedge Assemblies 80% Complete 4/26/007/31/0013.2w 9 Chip Ladder Fabrication 80% Complete 3/27/007/31/0017.4w M2-Muon End Toroids Installed on Platform 11/15/008/4/ w Ten 8-chip Analog Boards Available 4/19/008/8/0015.4w M3-VLPC Cryo System Operational 6/12/008/18/009.6w B-Layer Octants Assembled4/18/008/24/0018w All MDT Octants Assembled7/14/008/24/005.8w M3-VLPC Cassette Assembly 50% Complete 4/12/009/13/0021.5w M2-First Silicon Tracker Barrel/Disk Module Complete 1/24/009/14/0033w Low Mass Cables Available For Silicon North NA9/4/00NA SFE,SRC Fabrication Complete 2/3/009/21/0032.5w

D0 PMG 4/19/01 Completed Reportable Milestones (cont’d.) MilestoneBaselineActualVar. South H-Disks Ready To Move to DAB 7/3/0010/13/0014.4w MRC, MFC Production Complete 3/27/0010/18/0028.8w Preproduction MTCxx, MTFB, and MTCM Complete 1/24/0010/19/0038w South Half-Cylinder Complete and Ready to Move to DAB 8/1/0010/25/0012.2w M1-Begin Shield Wall Removal/Ready to Roll-in 11/22/0011/7/00-2.2w M3-Waveguide Production Complete 6/5/0011/7/0022w M3-Muon Level 1 Trigger Preproduction Testing Complete 4/18/0011/8/0028.6w M3-All Silicon Tracker Barrels/Disks Complete 8/25/0011/22/0012.6w (Calorimeter) Daughterboard Vendor Production Complete 6/16/0012/7/0024w

D0 PMG 4/19/01 Completed Reportable Milestones (cont’d.) MilestoneBaselineActualVar. North Half-Cylinder Complete and Ready to Move to DAB 9/18/0012/12/0012w M1-Central Silicon Complete9/18/0012/12/0012w Muon Forward Tracker B- Layer Planes Installed 6/15/0012/22/0026.2w All MDT Planes Installed8/4/0012/22/0019.2w All Muon Forward Trigger Detector Planes Installed 8/25/001/12/0118.6w M3-Calorimeter CC,ECN Preamp Installation Complete 3/31/001/15/0139.4w Multichip Modules Received2/23/001/27/0146.6w MBTs Received3/16/001/31/0144w M2-Silicon Tracker Installed in Solenoid / Fiber Tracker 9/25/002/12/0119w

D0 PMG 4/19/01 Completed Reportable Milestones (cont’d.) MilestoneBaselineActualVar. M1-Detector Rolled-in and Hooked Up 2/2/012/27/013.4w M3-VLPC Cassette Assembly Complete 8/22/003/20/0128.6w (Cal) Timing System Installed8/18/004/2/0130.8w BLS Motherboard Assembly Complete 8/7/004/16/0134.6w M2-Calorimeter BLS Assembly Complete 9/26/004/16/0127.6w

D0 PMG 4/19/01 Remaining Reportable Milestones MilestoneBaselineCurrentVar.SlackSince 2/15 Comments M3- Cal Readout Available to L2 2/11/005/15/0163.6w-- (ICD) Drawers Ready12/14/995/30/0172.2w14.4w50% here; test stand problems; manpower CFA Commissioning Complete 7/10/006/29/0149.3w19.3wContinues Production MTCxx, MTFB, and MTCM Complete 6/27/006/29/0150.8w10.4wMTCM-done MTCxx-16 of 48 assembled; rest by 6/29/01 MTFBs- MTM- done MTC05- done MTC of 28 assembled; rest mid- May M3-L3 Operational (One Full Chain) 6/1/007/5/0155w-- Global Installation Complete 7/12/007/17/0151w-- L2 Cal Installation Complete 8/21/007/17/0145.4w--Depends on alphas L2 Muon Installation Complete 7/26/007/17/0149w--Depends on alphas Mixer Boards Ready6/22/007/25/0154.8w13wLittle contingency left between this and AFE8 boards Alpha Cards Received5/15/007/31/0161w--For 12 alphas L2 CTT Installation Complete 8/9/008/14/0151w--Needs 12 alphas

D0 PMG 4/19/01 Remaining Reportable Milestones (cont’d.) MilestoneBaselineCurrentVar.SlackSince 2/15 Comments PDT Commissioning Complete 6/9/008/30/0161.8w27wContinues; gas flowing M3-Trigger Level 2 Commissioned 9/21/009/26/0151w--