Calice Tile-HCal and Tail-catcher/Muon Tracker

Similar presentations


Presentation on theme: "Calice Tile-HCal and Tail-catcher/Muon Tracker"— Presentation transcript:

1 Calice Tile-HCal and Tail-catcher/Muon Tracker
Vishnu V. Zutshi Northern Illinois University

2 Proposed Test Beam Setup
Joint development of test beam prototype simulation software within MOKKA framework lead by DESY/NIU 5/22/2019 V. Zutshi, DESY PRC Meeting, May04

3 Overall Responsibilities
Mechanics DESY,ITEP Tile-Fiber System ITEP Si-PM MEPhI, ITEP Cassette assembly LED DESY, Prague FEE LAL, MEPhI, JINR DAQ UK Groups APD Option Prague, DESY Slow Control DESY, LPI Software + Simulation DESY, NIU Tail-catcher Coordination DESY, ITEP 5/22/2019 V. Zutshi, DESY PRC Meeting, May04

4 Tile-Cal Schedule Jun04 Jul04 Aug04 Sep04 Oct04 Nov04 Dec04 Jan05
Tiles SiPM Tile+SiPM Cassette LED Stack FEE Chip DAQ Commissioning Mold produced Full production First 500 good Full prod. + selection Second batch of 5000 Tests start 1st 5K ready 2nd 5K  Mech. proto. Assembly of 1st with tiles Full set (mech.) Assembly with tiles continues  Design ready Prototype ready Production continues  Absorber structure ready Scanner 1st submission delivery final submission Delivery  Prototype board in hand Full production (5 boards) ready 1st cassette w/ FEE & DAQ 1st half of hcal ready Jun04 Jul04 Aug04 Sep04 Oct04 Nov04 Dec04 Jan05 5/22/2019 V. Zutshi, DESY PRC Meeting, May04

5 Tile-Fiber-SiPM Testing
5/22/2019 V. Zutshi, DESY PRC Meeting, May04

6 Front End Chip Being developed at LAL, Orsay 5/22/2019
100nF 10pF Variable Gain Charge Preamplifier Variable Shaper CR-RC² 10kΩ 5pF 1pF in 2.5pF 100f 100MΩ 1.6pF 3.2pF 100kΩ 500fF 8-bit DAC 1-5V ASIC Being developed at LAL, Orsay 5/22/2019 V. Zutshi, DESY PRC Meeting, May04

7 Tile-HCal Cost Estimates
Item K Euro Tile-Fiber System 35 Photo-detectors 70 Cassettes 50 Absorber + Table 60 HV System 20 LED System 30 Front-End Electronics 40 DAQ Total 375 5/22/2019 V. Zutshi, DESY PRC Meeting, May04

8 V. Zutshi, DESY PRC Meeting, May04
Contributions Investments: Germany  ~350K Russia  40K for prod. infrastructure and 10K for electronics production (JINR/BMBF) USA  20K for Si-PM photo detectors Czech Republic  25K for APD option 35-40 FTE + travel funds from all collaborating institutions ~35 FTE + travel funds from all collaborating institutions 5/22/2019 V. Zutshi, DESY PRC Meeting, May04

9 Tail-Catcher/Muon Tracker (TCMT)
Optimization of strip width Optimization of strip thickness 5/22/2019 V. Zutshi, DESY PRC Meeting, May04

10 V. Zutshi, DESY PRC Meeting, May04
Extruded Strips >10 p.e./mip 5/22/2019 V. Zutshi, DESY PRC Meeting, May04

11 V. Zutshi, DESY PRC Meeting, May04
TCMT Cassette Layout Separate covers Mirrored end connector Si-PM Co-axial cables 5/22/2019 V. Zutshi, DESY PRC Meeting, May04

12 TCMT Schedule Scintillator Strips SiPM Cassette LED Stack Cart
Commissioning Pre-prod prod For 1st cass. Full sample done for 1st cass. arrive for 8 cassettes arrive Mech. Proto. ready 1st cassette ready 8 cassettes ready Full set done Design ready prototype ready Production cont.  Design ready Absorber structure ready Design ready With some motion 1st cassette w/ FEE & DAQ 8 cassettes of TCMT readout Jun04 Jul04 Aug04 Sep04 Oct04 Nov04 Dec04 Jan05 5/22/2019 V. Zutshi, DESY PRC Meeting, May04

13 V. Zutshi, DESY PRC Meeting, May04
TCMT Cost Estimates Item K Euro Strip-Fiber System 5 Cassettes 8 Module (design+assembly) 15 (FNAL) Cart (design+assembly) LED System 7 Total 50 5/22/2019 V. Zutshi, DESY PRC Meeting, May04

14 V. Zutshi, DESY PRC Meeting, May04
Status and Plans Tile-HCal prototype has entered its construction phase. Unique in its ability to explore the whole range of readout options from the purely digital to the fully analog Inclusion of a tail-catcher/muon tracker for studying shower tails, leakage and muon identification/reconstruction in the PFlow paradigm will allow the full realization Calice test beam program. Program has nurtured and benefited from its truly international character. This trend is expected to intensify…. The next step is the exposure of the prototype to a hadron test beam to not only gain operational experience but even more importantly test, influence and validate the hadronic shower simulations leading to further development of PFlow algorithms. Need to take test beam together with the ECal in the period if conceptual detector design choices are to be made in time for the proposed 2015 start of the LC. 5/22/2019 V. Zutshi, DESY PRC Meeting, May04

15 V. Zutshi, DESY PRC Meeting, May04
Backup 5/22/2019 V. Zutshi, DESY PRC Meeting, May04

16 V. Zutshi, DESY PRC Meeting, May04
Lateral Size 5/22/2019 V. Zutshi, DESY PRC Meeting, May04

17 V. Zutshi, DESY PRC Meeting, May04
5/22/2019 V. Zutshi, DESY PRC Meeting, May04

18 V. Zutshi, DESY PRC Meeting, May04
5/22/2019 V. Zutshi, DESY PRC Meeting, May04