Building for Learning Project Photo Progress Report 4 November 2009 – December 2009 Project commencement 21 st September 2009.

Similar presentations


Presentation on theme: "Building for Learning Project Photo Progress Report 4 November 2009 – December 2009 Project commencement 21 st September 2009."— Presentation transcript:

1 Building for Learning Project Photo Progress Report 4 November 2009 – December 2009 Project commencement 21 st September 2009

2 AWCC Chairperson Kerryn Dwyer-Parish with Graeme Connelly undertaking site inspections Kerryn braved the situation – high heels and all

3 The 65mm of rain made for 4 internal swimming pools but the task is completed

4 And no photographic record is complete without some rabbit ears

5 November Internal Refurbishments continue

6 Internal Refurbishments Administration Area

7 New ceilings, plaster, office and painting

8 Key workers without who the job could not be done.

9 December new on-site substation for power required.

10 December – carpet, ceilings and windows in modernised Administration area

11 December – steel, bond deck arrives for 1 st Floor

12 December – underground cable boring and concrete footings for stairways and elevator

13 December – Company Directors tour with Graeme Connelly – girls were happy, boys were serious. L-R. Chairperson Kerryn Dwyer-Parish, Director Jan Wyatt-Brown, Director Alison Mitchell, Corporate Services Manager Pauline Butler, Builder Graeme Connelly, Director Rod Jones, Director David Ryan.

14 December – bracing underneath bond deck and steel ready for concrete floor above

15 Final preparations and then concrete pour starting 6am, 22 nd December – 150 tonne concrete

16 22 nd December – 11 truck loads of concrete


Download ppt "Building for Learning Project Photo Progress Report 4 November 2009 – December 2009 Project commencement 21 st September 2009."