Fullerton College Bond Fund Projects Update Fullerton College Athletics Project Scope Overview Schedule Parking.

Similar presentations


Presentation on theme: "Fullerton College Bond Fund Projects Update Fullerton College Athletics Project Scope Overview Schedule Parking."— Presentation transcript:

1 Fullerton College Bond Fund Projects Update Fullerton College Athletics Project Scope Overview Schedule Parking

2 N. BERKELEY AVE. N. LEMON ST. E. CHAPMAN AVE. Fullerton College Athletics Project

3 N. BERKELEY AVE. N. LEMON ST. E. CHAPMAN AVE. Phase 1 Olympic Pool 50 meter pool replaces old 25 meter pool 1 meter and 3 meter spring boards Pool pump house building Fire pump building Serves as additional fire protection to campus Tennis Courts Refurbished New Fire Lane FIRE LANE Fullerton College Athletics Project

4 N. BERKELEY AVE. N. LEMON ST. E. CHAPMAN AVE. Phase 2A Artificial Turf Fields Football, soccer and track and field per NCAA standards 1,500 seat home bleacher & pressbox 500 seat visitors bleacher Six 100 ft. light poles with directional reflectors 76.6 footcandles for games (30 footcandles for simple use) 0.6 footcandles at 100 ft east (1.5 footcandles on vertical) 0.16 footcandles at 150 ft east ( 0.5 footcandles on vertical) Fieldhouse 20,000 sf / 2 stories Locker rooms/Training Field support services 3 Classrooms 10 Offices 6 workstations Roof plaza assembly space (1,800 sf) 60 new parking stalls Fullerton College Athletics Project Level 2 Level 1 Light Pole Reflectors

5 Phase 2C Dance Studio New lighting and A/C Refinished floors and paint Corridors New lighting, floors, and paint Restrooms Storage Phase 2B South Gym New lighting and A/C Refinished floors, paint Refurbished basketball equipment Womens Locker Room New lighting and ventilation Refurbished and new showers New Dedicated team rooms New bathrooms Coaches locker rooms Officials changing rooms Equipment storage Fullerton College Athletics Project

6 Phase 2D North Gym New power retractable bleachers w/ assistive listening Refinished floors New lighting and A/C Mezzanines Renovated for multi-purpose use New lights, A/C & paint (16) Offices & (2) Meeting Spaces New Storage Mens locker room New lighting and ventilation New lockers Refurbished and new showers New Dedicated team rooms New bathrooms Phase 2E Outdoor Sports Court New Sand volleyball pit New Basketball half-court Refurbished strength lab Expanded Training Facilities New circuit lab Fullerton College Athletics Project

7 N. BERKELEY AVE. N. LEMON ST. E. CHAPMAN AVE. Additional Work Playing Field Bleachers/Pressbox Jump Events Signage Throwing Field Doors Security Access hardware Value engineering Dance Studio Floor repair Ballet bars South Gym Bleachers Fullerton College Athletics Project

8 Original Schedule Pool – 8 Months Start Date December 21, 2007 Substantial Completion August 22, 2008 Current Schedule Pool – 16 Months Start Date December 27, 2007 Substantial Completion April 30, 2009 Original Schedule PE/Field House – 13 Months Start Date January 25, 2008 Substantial Completion March 9, 2009 Current Schedule PE/Field House – 21 Months Start Date September 2, 2008 Substantial Completion May 18, 2010 Schedule Fullerton College Athletics Project Phase 1 Phase 2

9 Fullerton College Athletics Project Parking Number of parking spaces at the beginning of our program – 3,314 Number of parking spaces at the present time – 3,554 or gain of 240 spaces Number of parking spaces expected after our last approved project (Technology Complex) – 3,774 or gain of 460 spaces


Download ppt "Fullerton College Bond Fund Projects Update Fullerton College Athletics Project Scope Overview Schedule Parking."