Progress Report 11/10/11
2
Progress Schedule November 2011
Work Completed November: Masonry Walls 100% Complete Parking lot complete Rough In M&E All building floors poured Run water service Tower Foundation started Precast roof plank set Work Scheduled December: Install the concrete topping on the roof Install the roofing Spray on the building insulation Enclose building and heat Erect Tower begin interior build out Start Masonry Screen walls Start exterior brick
3
Progress 11/10/11 Mechanical room Electrical/Work room
4
Progress 11/10/11 Front office area Call Center
5
Progress 11/10/11 Staff parking lot Public parking lot