Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.

Slides:



Advertisements
Similar presentations
LS1 Status Report – 116 th LHCC Frédérick Bordry 4 th December 2013.
Advertisements

O. Pirotte, A.Perin, TE/CRG, 4 th LHC Splice Review, Page 2 4 th LHC Splice Review, July 22-24, 2013 O. Pirotte (TE-CRG), A. Perin (TE-CRG)
LHC HARDWARE COMMISSIONING REVIEW May 2005 CRYOGENIC VACUUM SYSTEM Paul Cruikshank for AT/VAC.
A. Perin, CERN, TE-CRG, 26 May Review of the cryogenic by-pass for the LHC DS collimators 26 May 2011 Modifications to the DFBs, DSLC and cryogenic.
Leak Testing QC of Cold Vacuum Systems the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133) 1 Paul Cruikshank.
QRL Leak Tests the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133) 1 Paul Cruikshank TE/VSC - QRL Leak Tests.
Vacuum, Surfaces & Coatings Group Technology Department Cleanness of the 3-4 cold beam lines Outline:  History: Status of 2009 cleaning  Foreseen and.
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
Overview of SMACC-QA 1.Recall of SMACC-QA organization 2.Tuning the procedures 3.Main results from the QC teams 4.Auditors findings Ranko Ostojic 23 July.
Status of SMACC-QA 1.Recently resolved issues 2.Update from QC teams 3.Statistics S56 and S67 4.Auditors findings 5.4th Splice Review – 22/24 July Ranko.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
Vision from TE/MSC and the SMACC project Superconducting & Warm Magnets LHC & injectors (20 min) J.Ph. TOCK (TE-MSC-CMI)
Alfa-Omega Team Coordination LS1 Collaboration Seminar, 27 th November 2014 Anna Chrul, IFJ PAN Kraków.
Beam Vacuum Quality Control Outline  VSC consolidation  VSC support  Organization  Status Cédric Garion on behalf of TE-VSC Cédric Garion TE/VSC Beam.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page
M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve.
Technology Department 1 Visit to Hall 180: Presentation of the consolidation process Third LHC Splice Review, November 12, 2012.
7/23/ J.Coupard. 1) Cryogenic risks 2) Cryogenic phases from RT/floating to nominal and additional safety rules A. Sectors warmed-up to RT or considered.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
Fourth LHC Splices Review Quality Assurance Review Review of actions from 3 last reviews NB : 8 non-closed ones from 1 st review 5 non-closed ones from.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, slides  Status of LHC: electrical connections  Description of shunt.
MP3 recommendations from June 2013-Feb 2014 Arjan Verweij on behalf of the MP A. Verweij, LSC meeting 7/2/2014 One of the tasks of the MP3 is.
Fourth LHC Splices Review Quality Assurance Review Introduction Why this 4 th review ? Committee, mandate Questions to the reviewers Overall Quality Assurance.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project … Courtesy ….
8 June 2006A.Ciocio - SCTSG1 Status of Type IV Cables Cables production –resumed in February after 3 months stop –See ID week February ‘06 Delivery of.
A. BallarinoLASA, Milano,18/09/2012 High-Tc Superconducting Link Status of Task 7.5 FP7 Meeting at LASA-Milano A.Ballarino, CERN for the Task 7.5 Collaboration.
Special interventions Status of production and QC Nicolas Bourcey TE-MSC-MDT Fourth LHC Splice Review November 2013.
Work Organisation for Splice Consolidation Francesco Bertinelli 20 minutes presentation, 10 minutes discussion: 12 slides First LHC Splice Review, CERN,
Third LHC Splices Review Production Readiness Review Introduction Why this 3 rd review ? Planning, committee, mandate Evolutions since last review: SMACC.
4 December 2007Sylvain Weisz - LEMIC1 Status of LHC installation.
Injectors & LHC report K. Foraz on behalf of OSS members 01/11/13LSC - EN-MEF-OSS1.
LHC magnet protection diodes status and recommendations for LS1 October 10 th, 2012 F. Savary on behalf of the diode working group (TE-MSC and MPE Groups.
Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix Jan’10)
Quality Assurance Overview Ranko Ostojic 12 Nov 2012.
Injectors & LHC report K. Foraz on behalf of OSS members 01/08/2013LSC - K. Foraz1.
D. Delikaris, TE-CRG, LSC 25th Meeting Page 2 October 18 th, 2013 LS1 Committee (LSC)- 25 th Meeting D. Delikaris, TE-CRG Cryogenics activities.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 30/08/2013LSC - S. Baird, M. Bernardini1.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
A. Perin, TE/CRG, DFBA LSC Page 2 LHC Long Shutdown 1 Committee June 14 th, 2013 A. Perin (TE-CRG) On behalf of the DFBA splices consolidation.
Proposed integration of cryo BLMs in LHC during LS1 V.Parma, CERN, TE-MSC With contributions/input from: M.Sapinski (BE-BI) Th.Renaglia (EN-MME) N.Bourcey.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
MSC Technical Meeting 29 August 2013 Overheated QBBI.A21L6 F. Savary with contributions from N. Dalexandro, H. Prin, C. Scheuerlein, P. Voisin.
LHC Machine Advisory Committee Meeting no.19 QRL status 16 June 2006 G. Riddone, AT-ACR On behalf of the QRL team.
A. Perin TE-CRG, 06 April LMC 08 April 2009 Consolidations related to pressure protection on DFBs and DSLs A. Perin, TE-CRG.
5-year operation experience with the 1.8 K refrigeration units of the LHC cryogenic system G. Ferlin, CERN Technology department Presented at CEC 2015.
LHC Risk Review Installation Progress Francesco Bertinelli – TE/MSC 5 March, 2009 (20 minutes) On behalf of - and with several contributions from – the.
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
L. Tavian, TE/CRG, LSC Page 2 February 21 th, 2014 LS1 Committee (LSC) L. Tavian TE-CRG.
Third LHC Splices Review SMACC Organisation Scope of work (What’s new since Nov 2011) Organization chart update Human resources Budget Unforeseen? Unexpected?
SMACC Eighteenth report [20 min] 07/02/2014
First LHC Splice Review Introduction
SMACC Tenth report [15 min] 13/09/2013
K. Foraz on behalf of OSS members
Update of cryogenic activities
LS1 Committee January 24th, 2014
LHC Dipole Diode Insulation Consolidation Review (I) INTRODUCTION
Reinforcement of the LHC Dipole Diodes Insulation during LS2
MPE main activities planned for LS2
Renovation of the 45-year old PS magnets
SMACC local splice quality control
Functional specification for the consolidated LHC dipole diode insulation system and consolidation strategy C. Scheuerlein on behalf of the LHC dipole.
Consolidation of the dipole diode insulation Technical aspects
K. Foraz on behalf of OSS members
Presentation transcript:

Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project

 Activities since last LSC (28/02/2014)  Arc splices installation By Activities By sectors  SIT  DFBA  Dashboards  Specials  Update on overheated splices  End of project issue  Activities for the next 2 weeks  Conclusions

JPh Tock 4/29  Sector 56 :  Final leak test and reconnection of DFBAK  Sector 67 :  Complete interventions on NC, reclose insulation vacuum  Sector 78  Work on NC,  Reconnection of DFBAO-SHM  Sector 81 (Priority)  Progress on insulation vacuum leak test  Sector 12  Complete last IC (#1)  Progress on closure of ICs  Sector 23  Progress on the installation of electrical insulation  Complete Q diodes consolidation  Complete M line rewelding (but NCs)  Sector 34  Complete installation of electrical insulation  Work on overheated splices  Start consolidation of Q diodes  Sector 45  Complete resoldering of splices  Progress on installation of shunts SMACC Main activities for the last 2 weeks  >98 % done  All shunts are installed   > 95% rewelded   Resoldering completed    DFBAK SHM reconnection on-going [Splices are resoldered], > 98% reclosed, 12/14 vac subsectors leak tested Leaks on K hoses repaired, > ½ is finally LT > 40% done  From last LSC ( ) DFBAK SHM reconnection on-going [Splices are resoldered], Only the last subesector remains to be leak tested Completed   > 90% injected and controlled > 75% reclosed   >95 % of the shunts are installed Interventions completed, ICs to be reclosed then final LT  1 out of 4 repaired, on-going

JPh Tock 5/29 SEQUENCE AND STATUS OK to open Open ICs Install DN200 Open M sleeves ElQC (old splices) Undo / Redo splicesElQC (new splices) Machine Cu > 7.9 sectors ElQC after Cu mach. > 7.9 sectors Install shunts ≈ 7.9 sectors ElQC after shunt ≈ 7.9 sectors Insulate splices ≈ 7 sectors Weld M ≈ 6 sectors Leak test M ≈ 5.5 sectors Close IC > 4.5 sectors Final LT ≈ 3.5 sectors Consolidate Q diodes ≈ 6.5 sectors Cancelled Completed Non-conformities (Before P Test) Non-conformities (After P Test) 1 completed ≈ 3.5 sec-eq Almost completed in 1 st sector (67) Completed

JPh Tock 6/29 SMACC Progress report by activity Courtesy H Prin  Resoldering: Completed for the whole LHC  Some desoldering/resoldering will be necessary because of NC Degradation after Cu machining, non-conformities,…  Competence and minimum capacity will be kept up to the end of the project

JPh Tock 7/29 SMACC Progress report by activity  Cu machining completed in > 7.9 sectors-eq Completed in 3 sectors Only 11 remaining, mostly linked to overheated splices and DFBA SHM reconnection Courtesy MDumas

JPh Tock 8/29 SMACC Progress report by activity  Shunts are installed in ≈ 7.9 sectors-eq 2 weeks ahead of schedule Saturation effect is seen Completed in 3 sectors (67, 81, 12) Only 16 ICs remains in the whole LHC (≈1%) Shunt weekly installation rate (4 weeks sliding average) *Estimate for W11 Courtesy H Prin

JPh Tock 9/29 SMACC Progress report by activity  Insulation box: Installed in > 6.5 sectors equivalent Courtesy H Prin / G Maury On the baseline  > 3 weeks buffer wrt welding  Only 8 ICs left in 6 first sectors (<1 %)  but it was 12 ICs 2 weeks ago  Issue with some tooling components (mixer), should be solved next week  A fall back solution exists (4 weeks sliding average) *Estimate for W8

JPh Tock 10/29 SMACC Progress report by activity  Consolidation of Q Diodes: in ≈ 6.5 sectors equivalent  Detailed schedule worked out  Should not interfere with welding activities  NC of un~/badly coated BB  Already decided to “use as is” if on magnet side  Decision extended to diode side [Diodes WG ] was confirmed at TETM Courtesy L Grand-Clement,

JPh Tock 11/29 SMACC Progress report by activity  M Welding : Done in ≈ 6 sec-eq:  Routinely 60 ICs/week  Work concentrated in 1 sector, starting in 34 (7 th /8)  No major disturbance  Exactly on the baseline presented on  Detailed presentation at next LSC As presented LSC Slightly ahead of revised schedule Courtesy S Atieh

JPh Tock 12/29 SMACC Progress report by activity  M sleeves leak testing : Completed in ≈ 5.5 sec-eq  Following the M lines rewelding, less regular by nature (sectorization)  ≈ 3 weeks behind schedule  Under recovery as for the M welding Courtesy P Cruikshank / L Mourier

JPh Tock 13/29 SMACC Progress report by activity  Reclosure of interconnections : > 4.5 sec equivalent are reclosed  Work mainly in S12 and starting in S23  On the baseline  The 1000 th IC will be closed this afternoon Courtesy A Chrul / A Musso

JPh Tock 14/29 SMACC Progress report by activity  Final leak test: > 750 ICs validated, > 3.5 sec equivalent  3 weeks to have results after repumping  S56: only DFBAK subsector remains  S67: fully validated but subsectors to be revalidated after interventions on NC  S78: 12 subsectors validated  S81: 11 subsectors validated, 3 under test, several interventions  S12: 6 subsectors under test  About 1 week behind schedule, was 3 weeks at last LSC

JPh Tock 15/29 SMACC Sector 67  2 leaks fixed, one not localised, accepted as is On-going:  Reclosure and final leak test of insulationvacuum SMACC Sector 81 Remaining : Less than half of W leak test and DN200 (Back on baseline )

JPh Tock 16/29 SMACC Progress report by sector Main activities are :  Leak test of M lines  Closure of interconnections  6/14 subsectors are under final LT Main activities are :  Welding of M lines  Leak test of M lines  Start reclosure of Ics (Today)

JPh Tock 17/29 SMACC Progress report by sector Main activities are :  Work on overheated splices (More info in next slides)  Q diodes consolidation  Rewelding of M lines Main activities are :  Installation of shunts  Installation of electrical insulation

JPh Tock 18/29 SMACC Dashboards  Shunting is slowing down (Difficult cases: overheated splices, DFBAs,… )  The installation of insulation boxes is ahead of the baseline  Welding and M leak test rates are recovering the baseline schedule in parallel  Reclosure: On baseline, nominal rate achieved  Insulation vacuum leak test : RECOVERING  Disturbances of leak tests (M lines and insulation vacuum) have to be minimised

Completed New

JPh Tock 20/29 SMACC Progress report SIT  SIT  Team is reduced but can be remobilised very quickly  Activities linked to NC, leaks and overheated splices Courtesy N Bourcey, S Le Naour

JPh Tock 21/29 SMACC DFBA Courtesy A Perin, E Vergara 95% of splices are consolidated OK for just in time (New schedule) Many operations are well advanced but not completed 8 DFBAs are completed

JPh Tock 22/29 SMACC Dashboards Baseline:82.7 % (77.4 %) Completed:84.2 % (78.9 %) Delay -3 (-3) days Baseline:76.9 % (72.8 %) Completed:74.9 % (69.0 %) Delay 10 (20) days Ahead of schedule Decreasing delay  Arc splices: Stable but difficult cases ahead  SIT Delay decreases, waiting validation  DFBA: Many activities on-going In the shadow of the arcs Baseline:85.7 % (81.1 %) Completed:67.1 % (57.4 %) Delay 3 (4) months Recovering

JPh Tock 23/29 SMACC Dashboards Progress: Baseline:82.5% (77.5 %) Completed:82.1% (76.6 %) Delay2 (6) days Decreasing ; Δbaseline <≈ Δcompleted

JPh Tock 24/29 SMACC Overheated splices From LSC of Courtesy C Scheuerlein, F Savary Confirmed as is Within the present schedule, possible to repair 4 to 5 splices with new cables [Forecast is max 6]

JPh Tock 25/29 End of project issue Courtesy R Ostojic, M Struik In order to alleviate effect of the end of work atmosphere, presence in the tunnel is increased: * One extra staff (Thx TE-VSC) to second worksite supervisors * Auditors are reinforced and are intensifying audits

JPh Tock 26/29 SMACC Summary on progress Main 13 kA Splices: On schedule  Q Diodes consolidation : Almost all components are at CERN and tested  Overheated splices : to be followed up closely Leak test rate is according to forecast,  slightly more needed Special Interventions:  Delay is decreasinng Almost all planned interventions are completed  Focus on NC DFBA: Activities are back in the shadow of arc splices (except 56-78) SMACC: About 2 days of delay, reducing wrt schedule defined one year ago !! Very slightly more than nominal rate achieved these last 24 weeks !

JPh Tock 27/29  Sector 56 :  Final leak test and reconnection of DFBAK  Sector 67 :  Reclose insulation vacuum and start final leak tests  Sector 78  Work on NC  Reconnection of DFBAO-SHM  Sector 81 (Priority)  Complete insulation vacuum leak test  Sector 12 (Priority)  Reclose last ICs  Progress on insulation vacuum leak test  Sector 23  Complete the installation of electrical insulation  Complete M line rewelding (but NCs)  Progress on M-lines leak testing  Start reclosure of ICs  Sector 34  Work on overheated splices  Complete consolidation of Q diodes  Sector 45  Progress on installation of shunts  Progress on electrical insulation SMACC Main activities for the next 2 weeks

JPh Tock 28/29 Conclusions  Project is almost back on schedule (-2 days)  Mind the last X % effect  Leak testing is reaching the planned rates  DFBA consolidation is progressing very well  Overheated splices : On the critical path  S67 is almost ready for next step (ElQA before cooldown foreseen end of April)  S81 should be ready on time for pressure test ( )

JPh Tock 29/29 Advancement is > 80 % …. But

JPh Tock 31/29