G. PassalevaFirenze - September 8, 2004 Production Readiness Review Firenze MWPC Production Site G. Passaleva.

Slides:



Advertisements
Similar presentations
Davide Piccolo INFN Napoli Muon Annul Review Cern 15 September 2003 Chamber Production QA/QC MUON ANNUAL REVIEW On RESISTIVE PLATE CHMABERS CERN, 15 September.
Advertisements

Muon EDR: Chamber design M2/3 R1/2 16/04/20031T.Schneider/LHCb Muon EDR 1.General description - AW read out -Cathode pad read out -HV supply 2.Details.
Module production at Heidelberg Responsibilities: assembly and test of 60 F- modules (5 m) September 28: Series module # 12 finished  20% reached Full.
Status of the ATLAS MM project
Status Update on Mechanical Prototype in Rome November 6,
Luminosity Monitor MWPCs, commissioning. A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg,
Construction material – All the material has been ordered with some spare (10%) Material Procurement Faraday cage – Final FEE board dimensions available.
Davide Piccolo - INFN NapoliSIENA maggio 2004 Production and Quality control of RPCs for the CMS muon barrel system Davide Piccolo – INFN Napoli.
Walls crates cables gas chambers electronics CERN adb.
QA/QC working group Working group ATLAS NSW - QA/QC working group - J. GIRAUD (20/02/2014)1.
Production Readiness Review of Frascati MWPC Production Site December 4 th, 2003 – P. Campana.
June 8-th 2004W.Baldini1 Ferrara production center Ferrara production center Production Readiness Review OverviewOfOperations P R R.
LHCb MUON MPWC STATUS OF TOOLING, SITES, PRODUCTION AND MATERIAL PROCUREMENT.
G. Martellotti CERN 22/04/20021 Tooling / Test Stations for MWPC (Meeting LNF, Roma1/Pz ) Production rate : 408 chambers (Fe + LNF) :192 R4 M1.
ISR Work Progress Report Muon Week April 10 th 2003 A. Benvenuti INFN Bologna.
TGC Big wheel Sector assembly plan Tatsuo Kawamoto ATLAS workshop 2005.
B. IlleWACH /11/20021 WELCOME to WACH I am happy to introduce this ‘Workshop Analysis Calorimetry H4’ dedicated to M0’ data analysis and the.
Ferrara 8 june 2004M.Savrié1 Production Readiness Review Ferrara MWPC Production Site.
Status of CERN M1R2 production LHCb Muon meeting sept.061Thomas Schneider -Beginning of 2006 two visits to Erbicol because of several reasons: -Material.
Status Report of activities in LNF Soldering procedure 1.Status of soldering machine 2.Measurement of wire position Chamber prototypes 1.Construction of.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
T.Schneider/LHCb Muon EDR
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
The Bigbite second GEM tracker. SBS GEM Trackers Front Tracker Geometry x6 18 modules In Italy  50 cm x 40 cm Modules are assembled to form larger chambers.
Status of production at LNF E. Dane, C. Forti, D. Pinci, A. Sarti – LHCb Muon CERN 25-may-04 Monday 24-may: closed chamber 30. Will close 2 more this week.
MWPC sandwich panels C.Forti INFN-LNF / LHCb-MUON EDR CERN 16 th April sandwich panels typologies of cathodes the mould the production procedure.
M. Gilchriese Sectors, Rings, Frame Assembly and Installation July 18.
Shandong University TGC Site Review Review team General impression Material presented Possible improvements Action items Conclusions.
Chamber construction Construction Tools Production sites Assembly Sequence (“travelers”) Manpower P. Campana LNF – LHCb Muon EDR Cern April 16 th, 2003.
G. Carboni – Muon Meeting – April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to
16/04/20031PNPI / LHCb Muon EDR Wire Pad Chambers PNPI design for regions R4 in Stations M2,M3,M4  4 gas gaps of 5mm±70µm;  Active area: 1224x252.8 mm².
1 DT critical items status: HVBoards Control and Trigger Boards Assembly in Torino fgasparini june 2004.
11/05/2000Wire Chamber Working Group Visit to Fermilab Participants: –Giulio Auriemma, Thomas Schneider, Burkhard Schmidt General Remarks: –Visit was organized.
LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,...
Baby MIND coil modules assembly the aluminium folded strip solution 1 Alexey, Philippe, Gabriella, Helder, Herman Baby Mind Magnet CERN June.
G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.
Panel production status Panels needed according to official plan Oct-05 A rate of 250/month is mandatory to match the chamber production schedule.
09/07/20021Muon Meeting Status of MWPC activities at CERN and PNPI Outline: Module 0 status and plans –M3R1 (CERN) –M3R2 (CERN) –M3R4 (PNPI) Tooling status.
9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress.
CMS Experiment at the LHC, CERN Date Recorded: :21 CET Run/Event: / Candidate Collision Event Report from Belgium Michael Tytgat.
Material procurement Panels 1300 produced (over 5700 planned) – Stop of the production in August (still at 50% of FR4 sheets delivered by ELTOS) – Restarted.
4-Jan-16S.Movchan Straw manufacturing and QC1 Straw tracker manufacturing procedure Dubna: assembly halls procedure conclusion Presented by S.Movchan.
Production Readiness Review at PNPI Chamber assembling: Main production and quality control steps 30 January 2004 – G.Alkhazov 1.Input components control.
G. Carboni - Muon Meeting – Draft Agenda Muon Meeting 6 April 2004 Introduction (15 min) Total 15 min MWPC prodution Material supplies,
Muon Meeting April 2004JsG Status of Chambers Production at CERN Jean-Sebastien Graulich o Open Questions from the PRR O-ring Aging, Aging tests, Storage.
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
DOE/NSF Review of U.S. ATLAS May 21-23, 2003 CSC Mechanics and Electronics Paul O’Connor Tom Muller BNL May 22, 2003.
Radioactive source and cosmic-ray test for the MWPC Davide Pinci on behalf of the Frascati-Roma1 MWPC group.
QA/QC in MM SM1 Mod 0 Production at INFN QA/QC MM SM1 Mod 0 - G. Maccarrone 19-Jan
Status of Anti project. F. Raffaelli,A. Checchetti,C. Capoccia. INFN CERN, July 14 th, Status of the Anti construction test and schedule. -Status.
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
TRD Workshop RomaniaClemens Adler Heidelberg ROC Status Material procurement, Chamber Status TRD workshop Cheile Grandistei, Romania,
CMS Upgrade Workshop, FNAL, Nov 19-21, O.Prokofiev CMS Upgrade Workshop Updated ME4/2 chamber construction costs and prototype Status and plans.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
10/7/2003Thomas Schneider1 Status report of CERN/PNPI Tooling support for PNPI M2R2 Prototype Plans towards the PRR.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
Status of production at LNF E.Dane’ and C. Forti – Meeting with LHCb referees Firenze 14-mar-05 Christmas 3 ch/week Ch. 43.
9/12/2003Ivan Hruska1 First box prototype –Box design in July ‘03 –Box produced during August ’03 Tested last week in few fingers Small changes necessary.
26-Feb-16S.Movchan Straw manufacturing and QC1 Dubna NA62 straw tracker assembly area (milestone) halls plans conclusion Presented by S.Movchan.
CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Update ME4/2 Chambers and Tooling A construction of new ME4/2 prototype at CERN Factory tooling,
11/02/2005M. Alfonsi - LNF1 DETECTOR CONSTRUCTION M. Alfonsi - LNF.
Trigger efficicency on double tracks Trigger efficiency on isolated tracks Final results of the Trigger Test on the 25ns beam Bx NUMBER Fraction of Triggers.
Production and installation plan Construction sharing Production plan Installation sequence Material procurement P. Campana LNF – LHCb Muon EDR Cern April.
Activity report from LNF Panels Soldering tests Production site and tooling status WPC miscellanea (+7 cm layout, cathode costs, aging tests)
Workshop summary Outline  Workshop’s aims  Highlights from the presentations (my selection!)  Costing Exercise – What we learnt  Summary - Roadmap.
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
News about the WA104 Programme C. Montanari – INFN and CERN technical working group meeting, September 16,
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
G. Carboni for the Muon Group
PNPI – M3R4 – Panels 70% - HV bars 100% - FR4 frames 100%
Presentation transcript:

G. PassalevaFirenze - September 8, 2004 Production Readiness Review Firenze MWPC Production Site G. Passaleva

Firenze - September 8, 2004 Agenda 10:00 Introduction:G. Passaleva30’ 10:30 Panel preparation and clean room operationsM. Lenti30’ 11:00 Results on the first chambersM. Lenzi30’ 11:30 Panel preparation and general chamber acceptance criteriaG. Carboni30’ 12:00 Discussion1h lunch 14:00 Visit of the production center1h30’ 15:30 Referees private meeting

G. PassalevaFirenze - September 8, 2004 Goals of the PRR The PRR has to verify/assess: Readiness of the tooling and of the production site Quality controls and assurance tests Material procurement and its flow Manpower availability Production ( and installation ) schedule

G. PassalevaFirenze - September 8, 2004 Production program in Firenze We have to produce: 148 M5R4 70 M1R4

G. PassalevaFirenze - September 8, 2004 Status of the production site Just a bit of history: In November 2002 it was decided to abandon the RPC technology and shortly after we proposed to set up in Florence a MWPC production site In April 2003 the proposal was approved by the INFN and by the Collaboration In may 2003 we got the first funding and we started placing the first orders The bulk of the orders for the main production tools was placed in july 2003 In fall 2003 we got the first equipments but due to the transfer of the Physics Department and INFN to the new Polo Scientifico we could get the first working tools only in February (in this period we contributed providing all the electrical layouts for HV bars and cathodes) We got the first 4 M5R4 panels at the beginning of may Production and testing tools were finalised by the end of June 2004 The first M5R4 chamber was closed the 12th of july 2004, exactly one year after the order for the wiring frame was placed !

G. PassalevaFirenze - September 8, 2004 Status of the production site Today we have: All the tools working 3 chambers completed and tested (2 one in Florence); two of them are almost acceptable…(see Michela’s talk) Infrastructure almost complete. Still missing: Solder fumes evacuation system (available but not yet installed) Radioactive source test Storage setup for assembled chambers Database for chamber assembly and test data storage

G. PassalevaFirenze - September 8, 2004 Infrastructure Wiring machine in the clean room Consolle of the wiring machine View of the open area and the “grey room” Yunshan in the “grey room” picking up panels for measurements

G. PassalevaFirenze - September 8, 2004 Panel gluing 1.Panels are checked for planarity… 2.…cleaned under the hut with isopropilic alcohol… 3.…glued on the gluing machine with automatic glue dispensing… 4.…measured again after gluing…

G. PassalevaFirenze - September 8, 2004 wiring machine Laser soldering bridge Glue dispensing bridge and wire tensioning torque motor

G. PassalevaFirenze - September 8, 2004 Assembly tables Panels wired glued soldered and cleaned are… 1.…measured with WTM… 2.…and with WDM, 3.tested for HV. 4.On the same table we glue side bars Final chamber assembly table (thanks to ROME 2 for the realization of the tools) 3

G. PassalevaFirenze - September 8, 2004 Quality controls: WTM, WDM,HV test WDM cameras WTM hammer laser spot and photodiode HV connections

G. PassalevaFirenze - September 8, 2004 EDR recommendations A small ‘pre-production’ series should be constructed and tested for each chamber type –the goal was to build and test 3-4 M5R4 chambers and to test them in LNF with the radioactive source: we succeeded in building 3; 2 were tested in LNF and 1 in Firenze with a prototype test setup. At least one of these pre-production chambers of each type should have undergone a successful ageing test –actually we have never tested our prototypes for ageing. We plan to test one of our chambers in a test beam in October

G. PassalevaFirenze - September 8, 2004 EDR recommendations A wire replacement procedure should be defined and tested for each chamber type. –we exercised the procedure several times on our chambers with success As the gap size is probably the most critical parameter for pulse height uniformity, an effort should be made to produce panels of best possible flatness. –we check all the panels for planarity with a precision rod and we discard the (few) ones out of specifications

G. PassalevaFirenze - September 8, 2004 EDR recommendations The precision of the wiring should be checked on all pre-production chambers –we do it for all the wired planes Gluing should be handled with the utmost attention, with well tested, constant procedures, in particular under <50% humidity –the humidity control is very effective and the gluing procedures are already automatic and controlled by PC apart for the closing bars and the side bars.

G. PassalevaFirenze - September 8, 2004 EDR recommendations A well-defined testing procedure during production should be established with the pre-series, including some final two weeks of operation at nominal voltage with final gas mixture and flow. –HV test on each wired plane is routinely done; we then perform an HV test of the closed chamber. Storage shelves have been ordered and we will place there the chambers for long term HV test On the basis of the experience gained with the pre-production series, the production schedule should be re-evaluated – we still have to experience the actual mass production, but we are quite confident in the proposed production schedule even though the possibiliy to have Saturday or even weekend shifts is being seriuosly considered

G. PassalevaFirenze - September 8, 2004 Operations performed in our production site (see Massimo’s talk for details) In the labs: –Cleaning of panels and HV bars –Gluing HV bars –Measurement of panels after gluing –Soldering connectors and ground contacts In the clean room: –Wiring soldering and wire gluing –Wire cutting and panel cleaning –WTM,WDM,HV tests –Chamber assembly In the open area: –Gas leak test –HV and gas conditioning and test –Radioactive source test

G. PassalevaFirenze - September 8, 2004 Material procurement All the chamber pieces are shipped to us through LNF CERN provides wire and glue We buy ourselves soldering wire, cleaning and gluing consumables, some extra glue etc. We have now in hands material for about 40 chambers For the moment we don’t see problems in material availability

G. PassalevaFirenze - September 8, 2004 People Staff physicists –Giovanni Passaleva –Giacomo Graziani –Massimo Lenti –Michela Lenzi –Michele Veltri Staff technicians –Fernando Maletta –Gabriella Gheri (part-time) –Giuseppe Giarrizzo (part-time) –Roberto Ciaranfi (electronics team) –Marco Ottanelli (electronics team) –Marco Montecchi (electronics team) Non staff –Yunshan Li (IHEP Beijing)

G. PassalevaFirenze - September 8, 2004 Production schedule FIRENZE Start date 01-set-04 end prod date 100M5R401-ott-05 48M5R402-apr-06 70M1R412-ott (195 equivalent chambers) Assuming an average production rate of 2 ch/week

G. PassalevaFirenze - September 8, 2004 Conclusions Up to know we managed to build and test 3 chambers The chambers have shown several problems and we tried to correct the assembling procedures accordingly As you will see in the talk of Michela, on or more quality control criteria are not fulfilled but the situation is (hopefully !!!) improving The accurate test of these chambers is an invaluable source of information to correct and/or tune the production steps

G. PassalevaFirenze - September 8, 2004 Conclusions We already started but we still need a training period. Our goal is to reach the nominal production rate by the end of September Production of two panel/day is feasible but with no margin: –Time contingency is gone: we are considering Saturday/weekend shifts –Possible failure in the tooling –We are ordering spare parts for the most critical items –Maintenance of the tooling –Time to switch from one chamber type to another Recovery could be possible only having some more man power: we will try to have two more people most probably by the end of the year Two years production is a very big effort especially for a small group like we are: we are aware of all the risks and we are trying hard to by on schedule

G. PassalevaFirenze - September 8, 2004