HPS Budget and Schedule Marco Oriunno, June 18, 2014.

Slides:



Advertisements
Similar presentations
Preparing for the CD-2 Review Elton Smith Hall D Collaboration Meeting October 12-14, 2006.
Advertisements

Beamline Overview Collaboration Meeting 16 June 2014 Ken Moffeit 1:30pm - 3:00pmBeamline overview (15’+5’)Ken Moffeit Status of the beamline construction.
Fermilab E906 Schedule Paul E. Reimer 20 June 2008.
EPAC June 2003 The EPAC June 2003 Questions 1. Clarify the Motivation for the Proposal. 2. How to ensure the e+ polarimeter works right away? 3. What is.
David Schultz Accelerator Nov. 12, ‘08 SLAC National Accelerator Laboratory 1 Accelerator Readiness ARR scheduled for Dec.
1 Roger Erickson 1 Coordination with Accelerator Systems NEH Accelerator Readiness Review Coordination with Accelerator Systems.
E166 Collaboration J.C. Sheppard SLAC, October, 2003 E166 Background Test Simulations: Overview-what do we need J. C. Sheppard.
E. Michael Saleski PPS and April 20, 2006 LCLS Personnel Protection System and Beam Containment System E. Michael Saleski.
1CUL.PPT Last Revised: 10 June 2005 The Role of the Communications Unit Leader Developed as part of the National Emergency Services Curriculum Project.
An Overview of the Heavy Photon Search Project John Jaros HPS Collaboration Meeting Jefferson Lab May 26, 2011.
HPS Budget and Schedule Marco Oriunno, June 4-6, 2013 HPS Collaboration Meeting, JLAB.
PAIR SPECTROMETER DEVELOPMENT IN HALL D PAWEL AMBROZEWICZ NC A&T OUTLINE : PS Goals PS Goals PrimEx Experience PrimEx Experience Design Details Design.
Server Virtualization: Navy Network Operations Centers
1 Getting Ready for the Climb HPS Project Overview HPS Collaboration Meeting at SLAC John Jaros September 10, 2012 John Jaros HPS Collaboration Meeting.
HPS EC Report John Jaros HPS Collaboration Meeting at JLAB June 18, 2014.
HPS Test Run Setup Takashi Maruyama SLAC Heavy Photon Search Collaboration Meeting Thomas Jefferson National Accelerator Facility, May 26-27,
Bubble Chamber Experimental Readiness Review September.
Machine Advisory Committee Review APS Upgrade Installation Plan and Schedule John Noonan November 15, 2006.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
Project manager report paul drumm CM16 October 2006.
Muon Campus Projects Jerry Annala Jan 23, µ AIP Scope Recycler RF system to provide needed bunch structure to future Muon Experiments Recycler RF.
WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/ SBS DOE Review.
Draft HPS Run Plan March 30, Next Steps Beamline Setup Trigger Commissioning Beam Stability Studies SVT Commissioning Data Taking Checking the.
Project Overview How to get here…. Half Way to the Test Run October 18, 2012HPS Project Overview2 …starting from here? John Jaros HPS Collaboration Meeting.
September 18, 2007H. J. Krebs1 SiD Collaboration One Piece End Door Design Concept plus Forward Equipment Interfaces H. James Krebs SLAC September 18,
HPS Beamline: Background Rates, Sensitivity to Field Uncertainties M. Ungaro1HPS Collaboration Meeting, JLAB, May Concrete Wall thickness Study.
Hovanes Egiyan Jefferson Lab. Main Hall B Beamline Components Beam Tuning Procedure HV System in Hall B Temperature Sensors Summary 10/19/ Hovanes.
1 Zoe Van Hoover 1 User Safety: Commissioning and Early Experiments NEH ARR User Safety: LCLS NEH Commissioning and Early Experiments.
Technical Support Activities in PH-ADO-PO
Jefferson Lab Update R. D. McKeown Jefferson Lab HPS Meeting June 16, 2014.
Jefferson Lab 12 GeV Upgrade Accelerator Readiness Review Phase 3 Roger Erickson SLAC National Accelerator Laboratory ARR Team Chairman August 26-28, 2014.
HPS T EST R UN C ONTINGENCY P LAN S. Stepanyan JLAB.
BIA’s Director Review, September Accelerator Improvements FY11-16 Fulvia Pilat.
Latifa Elouadrhiri Jefferson Lab Hall B 12 GeV Upgrade Drift Chamber Review Jefferson Lab March 6- 8, 2007 CLAS12 Drift Chambers Simulation and Event Reconstruction.
Transversity Readiness and Timeline Xiaodong Jiang, March 17th, This document specifies the overall readiness for Hall A experiments E06-010/E
DoE Review June 6, 2000 Cost Estimate  New Cost Estimate u Manpower Costs (Op. SWF) u Equipment Costs (Eq. M&S) u Contingency  Conclusions Mike Tuts.
RSVP AGS Upgrade Projects MECO RSVP Preliminary Baseline Review Brookhaven National Lab April 6-8, 2005 D. Phillips.
MOLLER Collaboration Meeting May 2014 Hall A Update Thia Keppel 1.
Budget Status and FY03 Requests Elton Smith Hall D Collaboration Meeting Sep 12-14, 2002.
RSVP AGS Upgrade Projects MECO RSVP Preliminary Baseline Review Brookhaven National Lab April 6-8, 2005 D. Phillips.
1 Integration and Milestones Elton Smith Hall D Detector Review October 20-22, 2004.
Hall A Installation Review John J. LeRose 2/25/2009.
HPS Summary Costs, Manpower, Schedule John Jaros Searching for a New Gauge Boson at JLab Jefferson Laboratory September 20, 2010.
HPS Experiment Overview John Jaros HPS Collaboration Meeting at JLAB October 26, 2015.
Experiment Readiness Review P. Rossi – Hall C Coll. Meeting Jan 21, 2016.
Run Coordinator Report February 5 to 8 Stepan Stepanyan JLAB 1.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
For discussion… Adachi. Horizontal effort Horizontal effort: one example – All of the proposed barrel PID detector use quartz bar radiator – Possible.
Time to resolve Design Issues 1. Disclamer Due to the engineering meeting last week I have not had time to coordinate this material with Tim or the L3.
Long-Baseline Neutrino Facility LBNF News and brief overview of Beamline plans for the next few months Vaia Papadimitriou Beamline Technical Board Meeting.
HPS EC Report John Jaros HPS Collaboration Meeting at JLAB May 5, 2017.
Experiment Readiness Review
Jefferson Lab Overview
TC activities.
News and brief overview of Beamline plans for the next few months
Overview of CLAS12 Calibration
Preparations for a Lehman Review
Injector Performance Requirements Conventional Facilities Update
Beam Background and the SVT Protection Collimator
HPS EC Report John Jaros
HPS EC Report John Jaros
C75 LLRF Cost and Schedule
Preparation of the CLAS12 First Experiment Status and Time-Line
Recoil e- detection in Radiative tridents
Extract from today’s talk given to DCB
TSF Upgrade Project Overview Resources Plans and Timetable
S. Stepanyan (JLAB) HPS collaboration meeting May 3 – 5, 2017 JLAB
Experimental Program and Endstations System (WBS ) J
HPS EC Report John Jaros
Presentation transcript:

HPS Budget and Schedule Marco Oriunno, June 18, 2014

2 Schedule and Manpower

3 HPS Master Planning V810 Alcove ready: 5/30/2014 On Schedule SVT Ready to Ship: 9/25/ weeks delay ECAL Assembled: 9/22/ weeks delay Slow Control ready: 9/30 4 weeks delay Installation & Commissioning: From September to November 2014

4 Installation and Commissioning ECAL Ready for the Beam 10/20/2014 SVT Installed < 11/14/2014 SVT Ready for the Beam < 11/18/2014 Engineering Runs > 12/19/2014 Complete Beamline 9/15/2014

5 Manpower (Scientific) PMBeamlineSVTSVT DAQECALTDAQ Slow Control SoftwareI&CFTE M. BattaglieriINFN A. CelentanoINFN Stuart FeganINFN A.D'AngeloINFN0.21 A.RizzoINFN L.ColaneriINFN G.SimiINFN N.RandazzoINFN M.DeNapoliINFN R.DevitaINFN M.CarpinelliINFN V.SipalaINFN M.OsipenkoINFN S.AielloINFN E.LeonoraINFN D.CalvoINFN A.FilippiINFN C.VenturaINFN Raphael DupreIPNO Gabriel CharlesIPNO Stepan StepanianJLAB Arne FreybergJLAB0.05 Hovanes HegiyanJLAB Serguei BoyarinovJLAB0.25 Maurizio UngaroJLAB 0.10 FX GirodJLAB 0.40 Yuri GernsteinRutgers 0.21 Tim NelsonSLAC Per HanssonSLAC Sho UemuraSLAC Matt GrahamSLAC 0.50 Jeremy McCormickSLAC 0.20 Norman GrafSLAC 0.50 John JarosSLAC Homer NealSLAC 0.08 Takashi MaruyamaSLAC Ken MoffeitSLAC 1.00 Clive FieldSLAC 0.17 Vitaliy FadeyevUCSC Forest McKinneyUCSC0.18 Omar MorenoUCSC Kyle McCarthy UNH Maurik HoltropUNH Annie SimonyanYerevan0.50 Nerses GevorgyanYerevan0.50 Holly Szumila-VanceW&M Total FTE by Subsytem

6 New Manpower (Engineering) Mechanical EngineeringPMBeamlineSVTSVT DAQECALTDAQSlow ControlSoftwareI&CTotal Marco Oriunno SLAC Shawn Osier SLAC0.71 Matt McCulloch SLAC Bob Connelly SLAC0.15 Reggie Rogers SLAC0.15 MD JLAB0.46 ME JLAB0.09 ME Accelerator JLAB JLAB0.10 MT Accelerator JLAB JLAB0.70 P. RosierIPNO E. RindelIPNO F. PratolongoINFN0.13 G. MiniINFN0.13 MT Hall-BJLAB0.06 Electrical Engineering Ryan HerbstSLAC Ben ReeseSLAC0.85 Dave NelsonSLAC0.15 ET SLACSLAC0.30 Ben Raydo (EE)JLAB 0.50 EE Hall-B JLABJLAB ET Hall-B JLABJLAB CS JLAB 0.25 EE Accelerator JLABJLAB 0.23 Emmanuel Rauly IPNO Total FTE by Subsytem Baseline Manpower, 4.78 FTE

7 Budget

8 Beamline Supplemental Funding M&S/LaborActualBudgetedDifference Beamline Elements$51.7k / $137.6k$189.4k$134.6k- $54.8 Alcove Installation$62.9k / $76.0k$138.9k$84.5k - $54.4 Magnet$33.3k / $7.5k$40.8k$26.6k- $14.2k TOTAL$147.9k / $221.1k$369.1k$245.7k- $123.4k The missing $125k were requested and agreed by DOEon 4/25, as part of the contingency held by DOE.

9 JLAB Budget (May 2014) $393k $271k

1.Some delays required an increased Engineering Manpower efforts in order to maintain our ability to install HPS this fall at JLAB. 2.Discussion started with DOE on 6/ SVT Supplemental Funding Funds Required to Complete Project Projected Costs $ Balance thru May 31, 2014 $ Net Funds Required $ Funds Requested Total Contingency Available $ 384.1

11 SLAC Budget (May 2014) $143k $1.17M

12 TOTAL (SLAC+JLAB) Budget (May 2014) $510k $1.44M

13 Readiness Review

14 Readiness Review, Charge 1.Are the HPS specific equipment, documentation and procedures to run the experiment in place and adequate? This includes demonstrated readiness for full rate capability and expedient analysis of the data. 2.Are the formal documentation requirements and reporting (run coordinator  shift leaders) procedures for running the experiment adequate, appropriate and complete (COO, ESAD, RSAD, ERG, OSP’s, general equipment operation manuals, etc.)? 3.Has the entire beamline, target, detector configuration been defined (including ownership, maintenance and control during beam operations)? Is all the necessary equipment installed and operable? If not, what are the completion/commissioning schedule and procedures? 4.Has transmission of the primary beam and generated secondaries been evaluated for unexpected beam restrictions (e.g. too small of a beam pipe acting as a secondary target), background sources (e.g. large number of produced photons hitting the beam line) or paths (e.g. primary and/or secondary steering from a magnet fringe field)? 5.Are the radiation levels expected to be generated in the hall acceptable? Is any local shielding required to minimize the effects of radiation in the hall equipment? 6.Are the local shielding and the machine protection system required to minimize the effects of radiation in the HPS detector in place? 7.Have all the jobs that need to be done to mount the experiment/s been identified and defined adequately? 8.Have conflicts with the 12 GeV Upgrade in Hall B been examined and resolved? 9.Are the responsibilities for carrying out each job identified, and are the manpower and other resources necessary to complete them on time in place?

15 Installation and Commissioning Schedule at JLAB, Summary Tasks

16 Hall B beamline Installation, 7/15 through 9/15

17 ECAL Installation and Commissioning, 9/8 through 9/22

18 Receive SVT at JLAB, 10/7 through 10/28

19 Beamline Commissioning, 10/10 through 11/10

20 SVT Installation and Commissioning, 11/13 through 11/18

21 SVT Installation Run Position: 85” Move 15” upstream

22 Complete HPS Checkout – Electron Beam commissioning and Running, 11/24 through 12/19

23 HPS in the Alcove

24 Potential sonflicts with the 12 GeV Upgrade in Hall B

25 Manpower (Preliminary) Mechanical EngineeringI&C Marco Oriunno SLAC0.12 SVT Shawn Osier SLAC Matt McCulloch SLAC Bob Connelly SLAC Reggie Rogers SLAC MD JLAB ME JLAB ME Accelerator JLAB JLAB MT Accelerator JLAB JLAB P. RosierIPNO0.02 ECAL E. RindelIPNO0.02 ECAL Emmanuel Rauly IPNO0.02 F. PratolongoINFN G. MiniINFN MT Hall-BJLAB Electrical Engineering Ryan HerbstSLAC0.13 SVT Ben ReeseSLAC Dave NelsonSLAC ET SLACSLAC Ben Raydo (EE)JLAB EE Hall-B JLABJLAB 0.04 TDAQ, Slow Control ET Hall-B JLABJLAB 0.04 TDAQ, Slow Control CS JLAB EE Accelerator JLABJLAB Total FTE by Subsytem 0.38 I&C M. BattaglieriINFN 0.02 ECAL A. CelentanoINFN Stuart FeganINFN A.D'AngeloINFN A.RizzoINFN L.ColaneriINFN G.SimiINFN N.RandazzoINFN M.DeNapoliINFN R.DevitaINFN M.CarpinelliINFN V.SipalaINFN M.OsipenkoINFN S.AielloINFN E.LeonoraINFN D.CalvoINFN A.FilippiINFN C.VenturaINFN Raphael DupreIPNO 0.02 ECAL Gabriel CharlesIPNO Michel GarconCEA Stepan StepanianJLAB 0.10 ECAL Arne FreybergJLAB Hovanes HegiyanJLAB 0.02 Slow Control Serguei BoyarinovJLAB Maurizio UngaroJLAB FX GirodJLAB Yuri GernsteinRutgers Tim NelsonSLAC 0.05 SVT Per HanssonSLAC 0.05 SVT Sho UemuraSLAC 0.02 SVT Matt GrahamSLAC Jeremy McCormickSLAC Norman GrafSLAC John JarosSLAC Homer NealSLAC Takashi MaruyamaSLAC 0.05 SVT, Beamline Ken MoffeitSLAC Clive FieldSLAC Vitaliy FadeyevUCSC Forest McKinneyUCSC Omar MorenoUCSC 0.02 SVT Kyle McCarthy UNH Maurik HoltropUNH 0.02 Software Annie SimonyanYerevan Nerses GevorgyanYerevan Holly Szumila-VanceW&M Total FTE by Subsytem 0.37

26 Summary 1.Average delay of 4 weeks for SVT and ECAL 2.SVT on the Critical Path 3.Requested in April contingency for Beamline (more labor intensive than expected). Full funded 4.Started last week discussion with DOE to release contingency fro the SVT (delay and design changes require more Labor) 5.Refined Installation and Commissioning Schedule, probably sufficient for the Readiness Review. 6.Need to better estimate the manpower for the Installation and commissioning.