1 TSF Upgrade Project Overview Resources Plans and Timetable
Hardware + Tests : Scott Kolya VHDL + Tests: Marc Kelly Bristol – Manchester - RAL Nicolo de Groot 11th April 2003 Final Design Review

2 From … To …

3 History September 2001: First proposal to PPRP. Based on daugthercards. Estimated costs £200k. Decision postponed. December 2001: Approval for prototype funding (£27k). Up to 60k for production. 2002: Trigger Upgraded postponed by one year, use this to make a cheaper board, no daughtercards, only 5 FPGAs. December 2002: New Proposal to PPRP

4 Funding Full production costs, estimated at £75k are approved by the PPRP, after we have demonstrated a working prototype An amount of £23k has been released to order components with a long lead time (FPGAs)

5 Current Status: Prototype
3 Chips, complete functionality needed for testing Boundary Scan OK Currently under test at SLAC (see Scott’s and Marc’s presentation)

6 UK Manpower Physicists / Management Roger Barlow, Manchester
Nicolo de Groot, RAL Technical effort Jamie Boyd, Postdoc, Bristol, 100% Dave Mercer, Engineer, Manchester, 50% Scott Kolya, Postdoc, Manchester, 50% Marc Kelly, Bristol, 100% These are time integrated averages.

7 Schedule Item Target Date Prototype completes electrical tests
Prototype System function tests (UK) Jan + Mar + Apr 2003 Full firmware for Fast Control/DAQ/Op Control Full firmware for Input Formatter Full firmware for Engines Apr 2003 System Test (SLAC) Apr + 1st Week May 2003 Parallel System Test at SLAC (with prototypes) June 2003 Final design complete Full System Test at SLAC Preseries tested at SLAC Early Sept 2003 Final delivery Oct 2003

8 Test Timetable The schedule represents our most optimistic timetable. It is dictated by the need to have a full system test before the end of the run (July) using a pre-series. In order to be able to do so we will instrument 6 of our prototype boards for the system tests. The test schedule will look like this: Last week April: completion engine firmware, completion test VHDL First week May: system tests at SLAC End of this week: start assembly of 6 test boards: 2 weeks End of May: boards to SLAC for full system test June: testing This assumes the prototype boards will be usable for the full system test. (so far, so good)

9 Production Timetable End June: final design, start production
End August: pre series ready Early September: test at SLAC September: production October: delivery Currently beam back on September 5th. Can we speed things up ?

10 Summary Complete redesign of TDF completed.
Prototype is there, testing. Confident that we can deliver. Some worries about the schedule. Maybe on time but under budget