SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:

Slides:



Advertisements
Similar presentations
Endcap assembly update C Buttar UK-SCT-MB RAL 2 nd Sept 04.
Advertisements

Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
27 September 2005A.Ciocio - ID Week1 SCT Service Installation Overview Status of Type IV Cable Installation Type II/III Cable Installation Plan for the.
SCT Power Supply Installation Schedule Jan Bohm, Prague AS, 4 th November 2005 The SCT Power Supply System will be installed in 22 LV&HV racks situated.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
18th March Richard Hawkings Humidity control in the ATLAS ID Richard Hawkings (CERN) JCOV meeting 18/3/04  Overview of humidity and associated gas.
Atlas SemiConductor Tracker Andrée Robichaud-Véronneau.
LAr ROD Status Arno Straessner and Alain, Daniel, Annie, Manuel, Imma, Laurent, Eric, Jean-Pierre, Gilbert,... ATLAS Geneva DPNC January 12 th, 2005.
Problems with UPS racks last week... During the DSS tests on the weekend Jun 1-2 all racks connected to „interruptable“ UPS were cut by DSS at some point.
Walls crates cables gas chambers electronics CERN adb.
31 January 2006A.Ciocio - SCTSG1 Type IV cables and PP3 Installation Type IV installation Connector in situ work Status of PP3 Testing.
29 November 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status of Type IV installation Connector in situ work Status of PP3 Testing.
Yu. Guz 18/12/20061 HCAL commissioning: status and plans Yu. Guz, IHEP, Protvino Outline 1. current status of HCAL a)CW+PM b)signal cables c)LED monitoring.
Preparation of SPD Cabling Calo comissioning meeting – 19th July 2006 – CERN I.Status of cables II.Cable reels III.Labelling IV.Cabling inside a VFE box.
Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005.
14 February 2006A.Ciocio - ID Week1 SCT Services Procurement & Installation Type IV PP3 Type II-III and PP1 Fibres Heaters DCS Testing MTF Workpackage.
TMDB delay and production plan Augusto. TMDB Prototype Status The prototype boards almost fully assembled should be delivered this week ( May 5 th ) First.
25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.
ID week - 26 September 2006 A. Ciocio1 SCT Services Installation SCT Cables Web page
RICH WG M.Lenti. Outlook Mirror Support Vidyo meeting on June 12, 20, 27 and on July 4 and 11 RICH WG meeting on august 27  Vessel status (see Ferdi’s.
Pippa Wells25 October Procurement and manpower for service installation Services readiness dates Planning for type ii/iii Fibre installation dates.
Activities Status and Plan for the week D. Giugni / INFN Milano D. Giugni Monday Meeting
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia DAQ, DCS, Power Supply and Cables Review CERN, March Electrical PP1 Basic features Electrical.
8 June 2006A.Ciocio - SCTSG1 SCT Services Installation Type IV PP3 Type II-III and PP1 Testing & Installation Plan Workpackage
CMX Production Status Presented to the L1Calo Meeting on Monday 22-Sept-2014 by Dan Edmunds for the CMX Group.
Pixel Heaters Refurbishment A.Bitadze.
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
SSD Status Report July SSD Status Report accessible from STAR group documents Pictures Updated documentation.
Abe Seiden December 2003 SCT Week S USA SCT Barrel Module Assembly SCT Week CERN December 2003 Presented by Abe Seiden U.C. Santa Cruz.
ATLAS SCT End-Cap C Integration 1.Introduction: to the SCT within ATLAS 2.End-Cap C Reception at CERN 3.Final Assembly 4.Integration with the TRT 5.Combined.
R. Fantechi. TDAQ commissioning Status report on Infrastructure at the experiment PC farm Run control Network …
18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page
Leonardo Rossi – ATLAS plenary- Stockholm 10/07/061 Inner Detector: highlights and concerns  A lot of progress on SCT & TRT integration.  Pixel production.
Straw Working Group Status assembly at CERN Plans 10/2/14Straw WG.
CHANTI update F. Ambrosino, T. Capussela, D. Di Filippo, P. Massarotti, M. Mirra, M. Napolitano, L. Roscilli, G. Saracino.
14 December 2005A.Ciocio - SCTSG1 Services and Patchpanels Installation Type IV installation Connector in situ work Status of PP3 Type II/III Testing.
E.Guschin (INR,Moscow) 17 July 2007 CALO commissioning group meeting CERN Status of PS/SPD LED system.
ATLAS Endcap Signal Feedthrough Project Status Report Pin carrier Procurement Summary Feedthrough Production QA/QC Shipment to CERN Reception Tests at.
Chiho Wang Duke University 1 TRT Barrel integration Status / Schedule Chiho Wang.
November 04 Jason Tarrant CCLRC1 SCT EC Interconnects l Progress of SCT EC Interconnects »Services (Required for Disc Insertion 2004 / Integration 2005)
7 March 2006A.Ciocio - SCTSG1 SCT Services and Patch Panels Type IV PP3 Type II-III and PP1 Fibres Heaters DCS Testing Workpackage
Status of and Installation Plan for DC Gas Control System and Target Work Scheduling Meeting 4 August 2006 PSI W. Molzon, Feng Xiao.
9 May 2006A.Ciocio - SCTSG1 SCT Services Installation Type IV PP3 Type II-III and PP1 Fibre Cables DCS Testing & Installation Plan Workpackage
13 September 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Delivery Installation Connector work Testing Summary.
Pending mechanics issues for electronics/services (updated 18/08/05 by Ana) Fixation/shielding for 2 LV PS (no fingers):  - Clermont worked out a proposal.
1/5 ECAL/HCAL Front-end status Calorimeter Meeting Frédéric Machefert Wednesday February 9 th, 2011.
M. Gilchriese Pixel Update October 3, M. Gilchriese 2 Outline Barrel status and repair strategy Revised ATLAS installation schedule Finishing pixel.
25 October 2005A. Ciocio - SCTSG1 Type II/III Cables and PP1 Status & Plan.
R. Boyd 1 February  Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
Atlas Muon Spectrometer: installation and commissioning L. Pontecorvo INFN Roma.
Status of Muon Activities W.Baldini, N. Bondar, O.Maev, B. Schmidt LS1 Meeting Dec. 20-rd 2013.
8 June 2006A.Ciocio - SCTSG1 Status of Type IV Cables Cables production –resumed in February after 3 months stop –See ID week February ‘06 Delivery of.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
André Augustinus Infrastructure  Turbines  Radmon  Thermocouple readout  Netgear redundancy  Other cavern items  Cooling CRs  Other CR and surface.
31 January 2006A.Ciocio - SCTSG1 Type ii-iii and PP1 Production Timescale for installation Plan PP1and Testing.
Status of the ATLAS ID Evaporative cooling system JCOV 25 Nov P. Bonneau TS/CV/Detector Cooling CONTENTS Overall statusOverall status Cooling plant.
9/12/2003Ivan Hruska1 First box prototype –Box design in July ‘03 –Box produced during August ’03 Tested last week in few fingers Small changes necessary.
Status of the DCS Richard Brenner (Uppsala University) " Structure of the DCS " Cabling of DCS sensors " Interlock " Status and near future plans.
Executive Committee, Toronto August 3, 2005 TRT Barrel WBS 1.2/3.2 Harold Ogren Indiana University.
August 04 Jason Tarrant CCLRC1 SCE EC Design & Manufacture l Progress of SCT EC »Support Structure (Required for Disc Assembly 2004) »Services (Required.
March 12 th 2013 Muon LS1 operation meeting1 Muon LS1 Status Outline Recap of last week P1 weekly schedule Muon related activities Open issues and discussions.
Proposed integration of cryo BLMs in LHC during LS1 V.Parma, CERN, TE-MSC With contributions/input from: M.Sapinski (BE-BI) Th.Renaglia (EN-MME) N.Bourcey.
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
News about the WA104 Programme C. Montanari – INFN and CERN technical working group meeting, September 16,
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
PIXEL CAEN Installation Status
LS1 Committee January 24th, 2014
Nearly the end of a long story...
Presentation transcript:

SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page: Workpackage: EDMS:  Specifications of SCT power cables, type II, III and IV  SCT Power Cables Layout

SCTSG - 17 October 2006 A. Ciocio2 Type II/III cables status 4088 cables: installation and testing completed ! 2112 barrel cables & 1976 Endcap cables 3594 cables (including all the 2112 Barrel) installed between March-July 494 (EC sector 11&15) installed in September % of the type III cables fixed on cable trays and positioned in PP3 (by TC) One recent faulty cable replaced (last week) Additional inspection, final verification and repair of damaged wires  ongoing Re-position (and insulation) of EC bundles and clamp on the flange  ongoing Test of the whole chain from Cryostat to Power Supply  ongoing Test of connectivity with Peter Phillips  November

SCTSG - 17 October 2006 A. Ciocio3 PP3 Rework Completed Because of insulation problem (see previous reports) ALL PP3 subracks of 30 units were: –disassembled –cleaned –glued properly –plastic layers (0.25 mm polyethylene terephthalate) inserted between all sides of PP3 units Disconnection of all cables was completed at the end of August (by the SCT cabling/testing team) –8000+ cables were hanging by the racks for several days –~4000 PP3 units in B161 Scott Moncrieff and Ashley French were at CERN for 4 weeks in September to do this rework –Many SCT collaborators participated in the re-assembling (THANKS!) –The last couple of weeks of September were very intense due to the late arrival of parts from Australia and running out of glue All PP3 subracks back in the pit and all re-installed by October 1 st 70 % of cables are re-connected to PP3

SCTSG - 17 October 2006 A. Ciocio4 PP3 Racks - USA side Sector 7 Type IV cables from Power Supplies racks in USA15 Type II-III cables from Cryostat Sector 9 Through corridors About 70 meters Sector 11

SCTSG - 17 October 2006 A. Ciocio5 PP3 Racks - US side Sector 3 Sector 1 Sector 15 Type II-III cables from Cryostat Type IV cables from Power Supplies racks in US15 Through wall holes About 30 meters

SCTSG - 17 October 2006 A. Ciocio6 Plan for PP3 Racks Rework Cables Reconnection & Testing (as of September 23) Taking into account: Connector in situ work PS installation Time to reconnect Time to test whole chain

SCTSG - 17 October 2006 A. Ciocio7 Type IV Cables Installation US side: –Type IV cables (2044+spares) from PP3 racks in the ATLAS cavern to PS racks in US15 Installed in 2005 (as double harness) Connectors in situ (March 06) 9 PS racks (8 for barrel) installed and cables plugged into PS backplanes (July) All type IV and type III (except for sector 15 EC) were connected to PP3 and test of whole chain done (in August) but then disconnected for PP3 rework USA side: –Type IV from PP3 to USA15 installation completed (end of July) –All type IV were connected to PP3 (17 racks in UX15) but then disconnected for PP3 rework –extra spare cables just added in several racks (USA side) All cables tested before and after installation

SCTSG - 17 October 2006 A. Ciocio8 Type IV Cables – cont’d Connector in situ (CPE) –All connectors (2100+) in US15 completed in March –“saga” to resume work in USA15  finally it started on Aug 1 st –8 USA racks with Barrel cables completed last week –The last 3 racks (EC) by End-October

SCTSG - 17 October 2006 A. Ciocio9 Type IV Cables – cont’d PS installation in USA15 (see next talk) –started 4 weeks ago –first plug-in/testing started on Sept 25 Testing –2 test systems are used for testing connector work and 2 test systems for PS/whole chain –1 test system failed 2 weeks ago  repaired after one week –Cables are first tested after connector work (plugged in PP3 – or not) to check connectors (rack by rack) –All cables are tested (whole chain) as they are plugged in row by row during PS connection –Test of whole chain in USA15 75% done now (sector 7, 9, 11) –Test of whole chain was performed on the US side (80 %) in end- July/August (but needs to be redone after PP3 rework) –Test of whole chain (again) in US15 started this week (sector 1, 3, 15) Test of sector 1, 3, 7, 9 will be completed in 2 weeks and partially sector 11 and 15

SCTSG - 17 October 2006 A. Ciocio10 PS racks layout priorities for connector in-situ and plug-in

SCTSG - 17 October 2006 A. Ciocio11 SCT DCS Cables Richard Brenner + Lars Lindquist 128 type II and 40 type IV + 4 canbus Almost all cables between cavern and USA15 are installed Interlock cables in US15 installed Interlock cables between PS racks in USA15 and DCS rack in USA15 installed (4 cables x 11 racks) In the next few days we’ll resolve the rest of the cables to be installed: –Y34-23.X0 : 6+6 type II cables missing for Barrel but they have been routed from the cryostat to Z=0 –Y29-01.X1: 6+6 type II cables missing for Barrel but they have been routed from the cryostat to Z=0 –type IV interlock cables have been routed to Y04-05.S2 in US15, but unfortunately incorrectly –Y35-05.X8 : All type II cables are missing from the rack. The cables were left to the cable tray 2 m below the rack (Sergei told me that they have already started to route them)

SCTSG - 17 October 2006 A. Ciocio12 SCT Readout Cable Installation All 144 SCT Readout Cables installed and tested See (September) ID week report No update

SCTSG - 17 October 2006 A. Ciocio13 Schedule (Power Cables & PP3) Barrel All Connector in situ (USA15) + testingend-October PS crates (USA15)mid-October Test of whole chain (sector 1, 3, 7, 9)end-October sector 11, 15mid-November PP3 & cabling PP3 rework (done) end-September All cables re-plugged into PP3/PSend-October Endcap 3 USA15 PS racks installationNovember 3 US15 PS racks installationJanuary 07 Test of whole chain November and January 07

SCTSG - 17 October 2006 A. Ciocio14 PEOPLE Freiburg, MPI, Japan, Glasgow, Manchester, Lancaster, UCL, Oxford, Cambridge, Geneva…

SCTSG - 17 October 2006 A. Ciocio15 Final Remarks PP3 rework has added extra load to an already dense schedule of activities –The help received in the last few weeks has been crucial to make progress 2 days per week (over the last 3 weeks) of 2 techs (Jean and Gilbert) from Geneva Tony W. + Ellie D. Janet, Stephen H., Richard B. Nobu + Reisaburo Last week 2 techs (Andy and Mike) from Manchester This week 3 techs (Ines, Dieter, Patrick) from Freiburg Next week 2 techs (Joe B. and Richard S.) from Oxford October 30 (for 2 weeks) 3 students from Bergen Need additional technical people (two) from October 30 until mid-November Consequences of PP3 rework and delay of connector in situ work added difficulties to keep up with the schedule –We are falling behind schedule with reconnecting to PP3 and testing of the whole chain (also due to the test system failure) –We are one week behind with connection to PS –USA15 was very crowed and hectic in the last 3 weeks Hoping to catch up in the next 2 weeks and be ready for the final connectivity test with Peter Phillips