DoE Review June 6, 2000 Cost Estimate  New Cost Estimate u Manpower Costs (Op. SWF) u Equipment Costs (Eq. M&S) u Contingency  Conclusions Mike Tuts.

Slides:



Advertisements
Similar presentations
Report from MICE project teams Proposed MICE organogram: revised Revised request for resources for financial year 2003/04 Review of iMICE schedules – status.
Advertisements

Executive Session Director’s CD-1 Follow-Up Review of the APUL Project November 2-3, 2009 Dean A. Hoffer.
US CMS DOE/NSF Review: May 8-10, US CMS Cost & Schedule Mark Reichanadter US CMS Project Engineer DOE/NSF Review 8 May 2001.
Effort Management: New Reports July Overview Changes to existing reports Payroll Distribution Confirmation (PDC) reports Payroll Distribution.
DOE/NSF U.S. CMS Operations Program Review Closeout Report Fermi National Accelerator Laboratory March 10, 2015 Anadi Canepa, TRIUMF Anna Goussiou, University.
Chapter 7: Managing Risk
Irwin/McGraw-Hill ©The McGraw-Hill Companies, 2000 Chapter 5 Managing Risk.
Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 1 DOE/NSF Review of the Dark Energy Survey (DES) Project SC 6/7 Cost, Schedule.
LIGO-G M LIGO Laboratory1 Adv. LIGO Installation (INS) Plans, Schedule, Costs, Team Plan, Schedule Costs Team.
FRA’s Earned Value Management System Corrective Action Plan Implementation January12, 2010 Dean Hoffer and Mike Rhoades.
FRA’s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 Dean Hoffer Head, Office of Project Management Oversight.
UCSF HR Billing 1. UCSF HR budget overview  Transformed organizational structure under one AVC comprised of five service centers, an academic specialty.
LSU 07/24/2004Defining Project Tasks1 Defining the Project Tasks Project Management Unit, Lecture 4.
WBS 1.7: AFE II Project Cost and Schedule Alan Bross DZero Run IIb AFE II Director’s Review April 13, 2005.
U.S. ATLAS Physics and Computing Budget and Schedule Review John Huth Harvard University DOE/NSF Review of U.S. ATLAS and CMS Computing Projects Brookhaven.
W. Freeman, D0 PMG 25-Feb-03 1 Run IIb Schedule Status u Schedule Status u Update on near-term equipment expenditures u Budgeting Update u Summary.
Server Virtualization: Navy Network Operations Centers
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
SNuMI 1 Outline Action Items PP2 Progress [Nancy/Elaine] –Org Chart Update –FY07 Budget/Plans Discussion –FY08 Summer Shutdown –Overall cost Reduction.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck NLSL II Deputy Director (Project Management)
Software Project Management (SPM)
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
7/26/2006 Wyatt Merritt 1 DECam Preparations for Critical Decision 2/3a Preparations for CD2 Preparations for CD3a DECam MOUs.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Slide 1 6-Nov-98PHOBOS Review: Cost & Schedule Cost & Schedule S. Steadman, MIT PHOBOS Cost & Schedule Review Technical Advisory Committee BNL November.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
John Peoples for the DES Collaboration BIRP Review August 12, 2004 Tucson1 DES Management  Survey Organization  Survey Deliverables  Proposed funding.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
David Lee, FVTX Review Nov Cost and Schedule WBS 1.0 David M. Lee Los Alamos National Lab Deputy Project Leader.
Project Management Methodology
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Lesson 1: Examining Professional Project Management Topic 1A: Identify Project Management Processes.
Response to TAC8 and Annual Review Recommendations John Haines Head of Target Division April 2, 2014.
Rev of Run IIb, Nov 4-8, 2002, A. Bean 1 Silicon Management  Organization and Management  Schedule  Resources  Conclusions Alice Bean Univ. of Kansas.
D0 PMG 6/15/00 PMG Agenda June 15, 2000  Overview (Tuts) u Detector status u Reportable milestones u Financial status u Summary  Response to DOE review.
Mark McKinnon NSF Mid-Project Review May 11-12, Baseline Project Definition Mark McKinnon Project Manager.
FTA Research Program Requirements Bruce Robinson Office of Research, Demonstration and Innovation April 17, 2007.
MICE CMPB Alain Blondel 1 Highlights on MICE.
DZero Run IIb Rev Nov 05 ‘03 1 Kotcher Agenda (from Rebaselining Review)  Introduction (Kotcher – 10’)  Trigger & DAQ/Online (Wood – 30’) u AFE II/TriP.
Wesley SmithMay 12, 2008 Trigger Budget Review - 1 US CMS Mid-Year Budget Review Trigger Wesley Smith May 12, 2008 Outline Overview of Activities FY 08.
Budget Status and FY03 Requests Elton Smith Hall D Collaboration Meeting Sep 12-14, 2002.
Brenna Flaugher Sept. 24 th Lehman Review1 Run IIB Silicon Upgrade: Cost and Schedule Lehman Review Sept. 24, 2002 Brenna Flaugher Run IIB Silicon Project.
W. Smith, U. Wisconsin, US CMS DOE/NSF Review, September 2004 Trigger Report - 1 CSC Trigger Muon Port Card & Sector Processor in production Mezzanine.
HPS Budget and Schedule Marco Oriunno, June 18, 2014.
1 draft NO A WBS J. Cooper NO A Working Group Meeting June 29,2005 Work is the effort of Ron, Dave, Bill, Suzanne, Harry, not just me.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
Computing Division FY03 Budget and budget outlook for FY04 + CDF International Finance Committee April 4, 2003 Vicky White Head, Computing Division.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
D0 PMG 2/3/00 PMG Agenda Feb 3, 2000  Overview u Project Manager’s Report – Tuts u Fallback options – Weerts  Silicon Support Cylinder Modifications.
V. O’Dell, L0 Workshop 25-Sep Run 2b Layer 0 Workshop u Layer 0 proposal from project Management perspective s History/News s Schedule.
U.S. ATLAS Project Manager’s Review with the Project Advisory Panel March 21-22, BNL Introduction Howard Gordon.
PMP Study Guide Chapter 11: Controlling Work Results.
Finance Roy Preece STFC RAL Oversight Committee Meeting 27 th November 2015.
EVM – Do You Really Know What the Numbers Mean? Booz | Allen |Hamilton Seth Huckabee EVP, PMP, PMI-SP.
Proton Plan PMG 7/27/06 J. Sims 1 Proton Plan Cost and Schedule Report Jeff Sims.
NCSX Strykowsky 1Independent Project Review (IPR) June 8-9, 2004 NCSX Project Review June 8-9, 2004 Cost, Schedule, and Project Controls Ron Strykowsky.
Arnd Meyer (RWTH Aachen) Sep 8, 2003Page 1 Integrated Luminosity Total data sample on tape with complete detector > 200pb -1.
Lukens - 1 Contingency Reduction Review – 27 May 2005 The Run IIb CDF Detector Project Contingency Reduction Discussion Patrick T. Lukens Fermilab 27 May.
Excessive Surplus Balances. NEW RULES ON SURPLUSES Following consultation with and approval from the Schools Forum it was agreed that the level of schools.
WBS 1.05 Commissioning Detector Scope, Cost & Schedule Sven Vahsen University of Hawaii.
Jim Fast Pacific Northwest National Laboratory
WBS 1.03 Readout Systems Scope, Cost and Schedule
Finance Committee Report
Preparations for a Lehman Review
Management Breakout: MREFC Budget Summary Victor L
Mark McKinnon EVLA Project Manager
LINAC OPS Budget Review
Presentation transcript:

DoE Review June 6, 2000 Cost Estimate  New Cost Estimate u Manpower Costs (Op. SWF) u Equipment Costs (Eq. M&S) u Contingency  Conclusions Mike Tuts DOE Review June 6, 2000

DoE Review June 6, 2000 Re-evaluating Cost Estimate  Elements of the cost estimate u Manpower s Technical manpower costs are those assigned to D0 s We estimate contingency of ~50% on our estimates for FY00-01 u Equipment s Accepted the prior year costs (<FY00) in lab books s Concentrated on bottoms up estimate to complete u Contingency s Based on present experience, assigned larger than “normal” contingencies to assure fiscal success

DoE Review June 6, 2000 Manpower  Track actual manpower by effort reporting at WBS level 2 (data available from 1/98) u by type, eg MT, ME, ET, EE u by subsystem  Extract manpower profiles from MS Project u Based on schedule as of end 99 u Have observed that effort reported manpower larger than from schedule u Schedule delays => greatly underestimated in the outyears relative to baseline  Use effort reported manpower to estimate Operating SWF costs

DoE Review June 6, 2000  Effort reported Fermilab FTE by type  Converted to then yr k$ using average salaries (Op SWF)  Change request submitted & approved by Lab 3/20/00 Manpower (Op SWF) Labor (then yr k$) FY97FY98FY99FY00FY01Total Baseline4,2774,2952,9551,064012,541 Reported/Est.--3,9684,5985,640*654*19,087 Present Op SWF4,2773,9684,5988, , ,093 * Estimated + Including contingency

DoE Review June 6, 2000 Equipment (M&S) Cost Estimate  Performed new bottoms-up cost estimate to complete in Feb-March 2000 u Provided by subsystem managers u Clear we would exceed the baseline cost s Recall “uncomfortably” low contingency at last review  Change request to Lab u Include FY99 and before as in lab books s Accept Lab figures for (+$479k) u Review of ETC by John Cooper + 20 reviewers! March 15,16,21 s Reduce cost by $130k, raise contingency by $675k s D0 response to further raise contingency by $200k for management contingency based on recent experience to further assure success  Change request approved by Lab and submitted to DOE u Approved by DOE on 4/24/00

DoE Review June 6, 2000 M&S Cost Estimate  Estimate to complete through April 2000 u provided by Level 3 managers u M&S only, then year k$, incl. $70k contingency u EAC= estimate at completion, ETC = estimate to complete (based on obligations through April) WBSSystemEACETC% obligated 1.1.1Silicon Tracker7, Fiber Tracker7, Central Preshower Forward Preshower Tracking Electronics3, Cal Electronics4, Intercryostat Detector Cosmic Ray Scintillator1, Central Moun Forward Muon Trigger2, Forward Muon Tracking1, Muon Electronics3, Framework1, Lum Monitor L1 Trigger1, L2 Trigger2, L3 Trigger1, Online Solenoid/beam pipe/shield4, TOTAL46,4793,10593

DoE Review June 6, 2000 Cost Variance  Variances from Nov 99 DOE review (then yr k$)  PMP 6/98 baseline for reference (*=FY95 x 1.06) WBSPMP 6/98* 11/994/00Diff 4/00-11/99 Reason ,2497,5337,857324Lower yields, installation ,8207,1407,774634More fiber & waveguide, shop charges Clear waveguide fab ,4263,5293,704175Si & Fiber readout: design cycles, parts TOT16,33818,95120,0981,147 WBSPMP 6/98* 11/994/00Diff 4/00-11/99 Reason 1.116,33818,95120,0981,147See below 1.24,618 4,65739Spares, power supplies 1.39,0409,3589,498140Mechanical supports, Gas syst 1.45,6366, Software licenses 3.15,1684,9754,886-89Savings TOT41,44145,21946,4791,260

DoE Review June 6, 2000  Risk based analysis (Then Yr $) u Initial subsystem & project managers estimate s $528k + $200k (management) u Cooper committee adjusted s +$715k u Project managers adjusted for management contingency s +$200k  Used $71k of this contingency to date Contingency Analysis WBSUnobligated (end April) Est. Conting % of unobligated Issues 1.11, See below Spares, power supplies Mech supports, Gas syst Other Install/safety/… TOT3,1051,64353 WBSUnobligated (end April) Est Cont % of unobligated Issues Readout elec., F & 90 o Flex circuits, waveguides,… Waveguides, connectors Fiber cards

DoE Review June 6, 2000 M&S Cost Change Request  Based on prior obligations, new ETC, contingency analysis, and review (Then Yr $) – as of March 2000  Change request ( ) approved by DOE on 4/24/00 u Did not realize $1.5M of non-DOE funds originally anticipated u Cost increased by $1.5M (-$250k Plant) u Estimate $1.6M of contingency CategoryBaselineMarch 00 Cost Est. Cost increase Contingency EQ. M&S 38,66540,1761,5111,643 EQ. SWF 86818,676-5 G&A7,9588, TEC55,30457,4312,127 Plant5,1684, Non- DOE 3,2871,824-- TOT63,75964,173-- Actual: $282k

DoE Review June 6, 2000 Contingency use  Contingency now held by Lab (Deputy Director) & DOE Project manager  Have implemented change control to request contingency u Total $71k to date u Near future: s Silicon ~$100k –Shop charges, mechanical infrastructure, installation s Muon trigger ~$50k –Additional cards, engineering

DoE Review June 6, 2000 Funding Summary  Based on Lab spreadsheet u In Then Yr k$, and FY95 k$ u Includes all contingency in FY2001 u Includes: all approved changes (M&S, Op SWF, G&A)

DoE Review June 6, 2000 Obligation Profile  Based on input from subsystem managers u No contingency included  Forward funding u $1M Stony Brook -in place u $0.8M Michigan State – in process

DoE Review June 6, 2000 FY00 Funding  Given profile, do we have sufficient obligation authority this FY to move ahead?  Obligated the present (FY00) budget amount $2.8M  Conclude that we may need $0.5-1M in additional forward funding (have prospects)  We can defer some of the obligations (~$300k) NeedsThen Yr (K$) Comments Cost profile May-Sept 2,698From managers profile estimate Contingency??500Guessing based on present rate TOTAL3,198 Obligation AuthorityThen Yr (K$) Comments Lab0All $2.8M now obligated Lab (other)215PO closings, paybacks, MOU closing Forward Funds1,800MSU, Stony Brook Non-DOE385May not get all this FY TOTAL2,400

DoE Review June 6, 2000 Conclusions  Costs and contingency recently reviewed  Change to TEC implemented through DOE change control  Contingency use monitored & controlled more closely  Will need additional forward funding this FY (~$500k-$1M)  We believe that the funding (with contingency) is adequate to complete the project