MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Project Update for the Muon Ionization Cooling Experiment (RAL) Mark Palmer Fermilab December 15, 2014.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
MICE Superconducting Solenoids: Status and Update RAL: T W Bradshaw M Courthold J Rochford M Hills D Baynham Oxford: J Cobb W Lau S Yang MICE.
1 paul drumm; ; FAC-PR MICE Project Status Funding Agency Committee 19 th September 2005.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
1 APRP Meeting MICE UK work packages Costs and schedules Organisation and monitoring Schedule summaries Cost summaries Andy Nichols, STFC, 15/8/11.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
CMPB Alain Blondel 14 April STATUS OF MICE.
MuCool RF Status MICE Collaboration Meeting June 7-10, 2006, Fermilab A. Moretti June 9, 2006.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
MICE - UK Project Progress Roy Preece 30 th April 2013.
MICE Project Board MPB Alain Blondel 1 MICE Project board 3 MICE Status Responses to MPB2 recommandations.
K. Long, 2 December 2014 Spokesman’s update 1. Contents: Update Step IV – Installation and commissioning – Preparations for data taking Shift tool; CHEESE.
Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
U.S. MICE Schedule, Cost, & Risks Peter H. Garbincius Mark Palmer, Alan Bross, Rich Krull Fermilab Presented at RAL – November 13, 2013.
Status of the Muon Ionization Cooling Experiment (MICE) Yagmur Torun Illinois Institute of Technology April 1, 2013.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
Executive Board Meeting Roy Preece 23rd May 2014
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
1 MICE MPB/RLSR Integration of Step IV Readiness of the major subsystems Installation sequence and schedule considerations Logistics, staffing and local.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Next Collaboration meeting will be Jun at IIT and the 19th at Fermilab right before the.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Spectrometer solenoid 2. Magnetic shielding 3. Next Collaboration meeting.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
MICE VC 10-Oct-2013 Alain Blondel 1 MICE NEWS VC 162 LOTS OF THINGS HAPPENED! have arrived at RAL: -- EMR (see report today) -- AFC2 see pictures -- SS2.
RLSR 16/4/2015 UK Financial Plan & Risks. Content Finances – Cost to Completion Risks – Top level to completion – R9 working space – Summary 2 RLSR 24/11/2014.
MICE CM35 Status and Goals Alain Blondel 1 WELCOME TO MICE CM35! – Status and Goals - Many thanks to Chris Rogers, Debbie Loader and Rose Hayes for taking.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
MICE VC Alain Blondel 1 MICE NEWS MICE VC 161 Agenda Overall schedule Magnetic field mitigation review Status of things.
Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MPB 31 October 2012 and FAC 15 November monitor how well we are doing in assembling step IV ! -- should deliver a ‘realsitic schedule scenario’
Paul Drumm, cm10, 27 Oct 2004 MICE Project Report Paul Drumm Collaboration Meeting 10 Rutherford Appleton Laboratory October 2004.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
MICE FAC open session Alain Blondel 1   MICE The International Muon Ionization Cooling Experiment.
US Project Plan for MICE Mark Palmer Peter Garbincius, Alan Bross, Rich Krull Fermilab November 24, 2014.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
MICE VC Alain Blondel 1 1. MOM is now Victoria 2. Linda Coney is new MICE Online Group coordinator (rep Jean-Sebastien) May we held.
Muon Ionization Cooling Experiment Update 1Alan Bross AEM October 14, 2013.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
MICE CM30 Goals of the Meeting Alain Blondel 1 MICE CM30 – Goals and Status.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
MICE – UK Plan Roy Preece STFC RAL DOE Review of MAP Brookhaven National Laboratory 13 th August 2014.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
RLSR 16/4/2015 UK Financial Plan & Risks. Content Finances – FY 2014/15 – Cost to Completion Risks – Top level to completion – R9 working space – Summary.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Next Collaboration meeting will be at Cosener’s14-16 February meeting at Coseners House.
MICE Demonstration of Ionisation Cooling Colin Whyte University of Strathclyde On behalf of the MICE collaboration 1RF Review 9th-10th Sept. 2015, Abingdon.
Standalone Commissioning Plan in MICE Hall K Ronald, University of Strathclyde For the MICE RF team 1MICE RF Review 9th Sept 2016.
The MAP 3-Year Plan Mark Palmer Fermilab September 26, 2014.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
K. Long, 28 June, 2016 Introduction to MICE — and the role of the Hydrogen Delivery System.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
MICE RLSR – 13Nov2013 Alain Blondel 1 MICE Project Board 14 November 2013 Alain Blondel.
Schedule and Milestones Colin Whyte STFC RAL Resource Loaded Schedule Review 5 th April 2016.
US Project Plan for MICE Peter H. Garbincius, Mark Palmer, Alan Bross, Rich Krull Fermilab April 16, 2015.
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
Muon Ionisation Cooling Experiment Overview
Status of the MICE Construction Project
UK Financial Plan & Risks
MICE CM31 Schedule summary
MICE Project in the US: Completion of Efforts
Presentation transcript:

MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids

2 Contents 1.Agenda of Meeting 2.Organisation 3.MICE general status by MICE-UK Work Package 4.Spectrometer solenoid status 5.Conclusion MICE OsC Meeting, RAL, 24 April 2014

3 Agenda of meeting o MICE Oversight Committee meeting agenda −11:45: MICE Status and Spectrometer Solenoids (P. Soler) −12:10: Status of Focus Coils (R. Preece) −12:30: Lunch −13:00: Tour of R9 (Focus Coil and Spectrometer Solenoid) −13:30: Spend in FY13/14 and Project Risks (R. Preece) −14:10: Schedule and financial forecast for future years (A. Grant) MICE OsC Meeting, RAL, 24 April 2014

4 New MICE Organisation o Personnel: −Spokesperson: Prof Ken Long (Imperial College) −Collaboration Board Chair: Prof Alain Blondel (U. Geneva) −MICE Project Manager: Mr. Roy Preece (STFC) −MICE Project Engineer: Mr Andy Nichols (STFC) −MICE UK Capital Project Associate: Mr Alan Grant (STFC) −Accelerator Integration Scientist: Dr J. Pasternak (Imperial) −Experimental Integration Scientist: Dr P. Hanlet (IIT) −US MAP Director: Dr M. Palmer (FNAL) −MICE US Construction Project Manager: Dr A. Bross (FNAL) −MICE UK Principal Investigator: Dr Paul Soler (U. Glasgow) MICE OsC Meeting, RAL, 24 April 2014

5 General Status o Work Package 1: Project Management −MICE International Project Office (MIPO): construction of project

6 General Status MICE OsC Meeting, RAL, 24 April 2014 West Wall Mezzanine (for Step IV) Rack room 2 o Work Package 2: Mechanical Integration −MICE Hall Manager: John Govans

7 General Status MICE OsC Meeting, RAL, 24 April 2014 Decay Solenoid power supply Step IV control racks o Work Package 3: Electrical Integration −Focus coil quench detection system and control −Rack room 2: control racks, 30 kVA UPS −Decay solenoid power supply and quench detection

8 General Status MICE OsC Meeting, RAL, 24 April 2014 Insertion hydrogen turret and absorber into FC 1 o Work Package 4: Absorber-Focus Coil Module −AFC integration: hydrogen turret + absorber in FC 1 −Focus Coil status: see Roy Preece’s talk

9 General Status MICE OsC Meeting, RAL, 24 April 2014 Insertion hydrogen turrent and absorber into FC 1 o Work Package 5: Hydrogen delivery system −Most activity on integration of AFC −LH2 delivery system simplified due to PRY solution −HAZOP review: diagnostic system, expansion tank, vacuum relief valve, control system, nitrogen purge gas −Second LH2 absorber: ready to ship (KEK/Osaka)

10 General Status MICE OsC Meeting, RAL, 24 April 2014 o Work Package 6: RF Power −Delivery 2 MW power at 201 MHz at Daresbury (last OsC) −TIARA milestone met: installation RF amplifiers at MICE RF loads installed under mezzanine

11 General Status MICE OsC Meeting, RAL, 24 April 2014 Final stage amplifier with triode valve o Work Package 6: RF Power −Delivery 2 MW power at 201 MHz at Daresbury (last OsC) −TIARA milestone met: delivery of >500 kW power from TH116 amplifier at MICE

12 General Status MICE OsC Meeting, RAL, 24 April 2014 o Work Package 6: RF Power −Cavity tests at the MTA stand at Fermilab −RF workshop at Fermilab on 2 June 2014 with UK team (K. Ronald, T. Stanley) Tuner arms

13 General Status MICE OsC Meeting, RAL, 24 April 2014 o Work Package 7: Vacuum −The design of the vacuum system for Step IV is complete and has been mocked up in the MICE Hall. −A complete services inventory for the vacuum system has been compiled and is being used by the services design engineer to make the overall layout.

14 General Status o Work Package 8: Magnetic Field Mitigation −Partial Return Yoke and floor fixing designs completed and sent out tender MICE OsC Meeting, RAL, 24 April 2014 Partial Return Yoke (PRY)

15 General Status MICE OsC Meeting, RAL, 24 April 2014 o Work Package 9: Software and Computing −Computing and controls Work Breakdown Structure −Finite-state-machine implemented in EPICS Spectrometer solenoid control panel Computing WBS

16 General Status MICE OsC Meeting, RAL, 24 April 2014 o Work Package 10: Operations and analysis −MICE Experiment Management Office (MEMO): operations, maintenance and analysis

17 General Status MICE OsC Meeting, RAL, 24 April 2014 o Work Package 10: Operations and analysis −MICE Analysis Structure −Combination of simulation and analysis tools and physics activities

18 Target trajectory S7 beam loss ISIS beam loss Magnet ramps General Status o Work Package 10: Operations and analysis −Target: operated at 0.8 Hz (April 2014) with little beam loss −Pneumatically activated proton absorber MICE OsC Meeting, RAL, 24 April 2014 Proton absorber

19 General Status MICE OsC Meeting, RAL, 24 April 2014 Muon decays in EMR o Work Package 10: Operations and analysis −First MICE physics paper published: D. Adams et al., “Characterisation of muon beams for the Muon Ionization Cooling experiment”, E. Phys.J. C73 (2013) −EMR delivered by U. Geneva – EMR run Oct. 2013

20 General Status MICE OsC Meeting, RAL, 24 April 2014 Criteria for success o Work Package 10: Operations and analysis −Step V vs VI running decision will be motivated by physics criteria and schedule, financial constraints −Expect collaboration decision before end of 2014 after careful evaluation

21 Spectrometer Solenoid SS2 ready for shipping at Wang NMR o Spectrometer solenoid status: −Completion of the assembly, training, 3D magnetic mapping and shipping to RAL of SS2 (October 2013) MICE OsC Meeting, RAL, 24 April 2014 Magnetic field mapping SS2 at Wang NMR

22 Spectrometer Solenoid Training sequence SS1 and SS2 o Spectrometer solenoid status: −SS1 also assembled, trained and mapped at Wang NMR −SS1 is ready to be shipped to RAL (27 April 2014) MICE OsC Meeting, RAL, 24 April 2014 SS1 at Wang NMR during final vacuum vessel assembly

23 Spectrometer-Tracker integration MICE Tracker o Integration of the spectrometer solenoid and scintillating fibre tracker −Trackers have been available for a number of years and commissioned with cosmic rays Individual tracker station MICE OsC Meeting, RAL, 24 April 2014

24 Spectrometer-Tracker integration Tracker 2 just before inserting into bore SS2 Tracker 2 in bore SS2 MICE OsC Meeting, RAL, 24 April 2014 o Integration of the spectrometer solenoid and scintillating fibre tracker −Installation tracker 2 in upstream SS2 completed 31 March 2014 and will be moved to MICE Hall 29 April 2014

25 Spectrometer-Tracker integration Tracker 2 installed and light-guides in place o Integration of the spectrometer solenoid and scintillating fibre tracker −Installation tracker 2 in upstream SS2 completed 31 March 2014 and will be moved to MICE Hall 29 April 2014 Closed SS2 with tracker inserted MICE OsC Meeting, RAL, 24 April 2014

26 Conclusions o MICE is proceeding towards Step IV o Many achievements in last six months: –New organisation with change of spokesperson –Mechanical and electrical integration being achieved –Hydrogen absorber inserted into FC –RF power in MICE Hall milestone achieved –Partial Return Yoke design achieved: out to tender –Target doubled rate and proton absorber completed –EMR delivered and running well –Spectrometer solenoid SS2 integrated with tracker 2 and SS1 completed at Wang NMR, ready for shipping o Focus coil status, schedules and resources to be shown by Roy Preece and Alan Grant in next talks MICE OsC Meeting, RAL, 24 April 2014