14.10.2008 CLIC Workshop, CERN 1 CLIC/ILC Collaboration Report: Marc Ross (Fermilab); for Nick Walker, Akira Yamamoto Project Managers International Linear.

Slides:



Advertisements
Similar presentations
CERN TS Department / Civil Engineering Group 8 February 2008 Civil Engineering Layouts & Tunnel Cross Section 1 CLIC/ILC Collaboration Meeting 8 Feb 2008.
Advertisements

Nick Walker KEK-DESY meeting 7 th March 2005.
LCC status Lyn Evans 1April 18, 2015PAC Orsay. ILC in Linear Collider Collaboration 2 ICFA Chair: J Mnich Program Adv. Committee PAC – Chair: N. Holtkamp.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
Global Design Effort - CFS TILC09 and GDE AAP Review Meeting - Tsukuba, Japan 1 GDE ACCELERATOR ADVISORY PANEL REVIEW CONVENTIONAL FACILITIES.
Global Design Effort 1 Conventional Facilities and Siting Overview A. Enomoto, J-L. Baldy, V. Kuchler GDE.
HEPAP and P5 Report DIET Federation Roundtable JSPS, Washington, DC; April 29, 2015 Andrew J. Lankford HEPAP Chair University of California, Irvine.
Global Design Effort BDS KOM Opening remarks/comments from EDR Project Management SLAC Marc Ross / Nick Walker.
Global Design Effort - CFS CLIC 09 Workshop - WG 5 Technical Systems 1 CLIC 09 WORKSHOP Working Group 5 - Technical Systems ILC REBASELINE ILC.
ILC CFS / CLIC CES Studies for the Interaction Region : - An action was given at the Geneva Linear Collider Meeting for CFS to develop a more in-depth.
Global Design Effort - CFS ILC Global Systems Meeting 1 ILC GLOBAL SYSTEMS MEETING CONVENTIONAL FACILITIES AND SITING GROUP Status and Overview.
Global Design Effort - CFS ILC CFS and Global Systems Meeting 1 ILC CFS AND GLOBAL SYSTEMS MEETING CONVENTIONAL FACILITIES AND SITING GROUP GENERAL.
CES Status J.Osborne 6 November 2009 Status Report from Civil Engineering and Services Working Group J.Osborne GS/SEM for CES Working Group.
1. Civil Engineering works for Linear Colliders* : -Brief introduction on the overall machine layout (just for CLIC at this stage) -Experimental Area.
Nick Walker, Brian Foster LAL, Orsay WP2: Coordination with the GDE.
Global Group 4 – Conventional Facilities and Siting V. Kuchler1 of 17 Fermilab R&D Meeting Fermilab R&D Meeting Vic Kuchler Conventional Facilities.
1 st October Linear Collider workshop The CLIC/ILC common work plan progress J. Clarke and L. Rinolfi.
Global Design Effort Beam Delivery System => EDR LCWS07 June 2, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi Yamamoto.
J.P.Delahaye:16/11/2008LCWS08 Chicago 1 CLIC-ILC Collaboration Following constructive visit of CERN (Nov 07)
WWSWWS Next steps for Detectors by F. Richard LAL/Orsay TILC08 TILC08 Joint ACFA Physics and Detector Workshop and GDE meeting on ILC, 3-6 March 2008,
Global Design Effort - CFS TILC09 and GDE AAP Review Meeting - Tsukuba, Japan 1 GDE ACCELERATOR ADVISORY PANEL REVIEW CONVENTIONAL FACILITIES.
1 CLIC / ILC Collaboration for CES issues JOHN OSBORNE – CES 8 April 2009.
Workshop Goals Marc Ross LC May, 2013 Accelerator Plenary.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
ATF-II Review by GDE Marc Ross, (SLAC) For GDE Project Managers: Nick Walker and Akira Yamamoto 24 January, th ATF2 Collaboration Meeting.
1 Global Design Effort TILC08 - WG1 Summary WG-1: Cost Reduction Studies J. Carwardine, T. Shidara, N. Walker (For WG-1 participants)
TILC08 - WG1 Summary Global Design Effort 1 TILC08 仙台 GDE 会議 WG-1 活動報告 GDE 活動報告会 3月11日10:00- 3号館7階会議室 設楽
Agenda : CLIC Civil Engineering and Services (CES) WG.
27 Nov 07 VM Workshop Global Design Effort 1 ILC – Superconducting Linear Collider Marc Ross, Project Manager GDE Fermilab.
Global Design Effort - CFS ILC Accelerator Design and Integration Meeting 1 ILC AD&I MEETING CONVENTIONAL FACILITIES AND SITING GROUP UPDATE V.
Summary R.-D. Heuer, Univ. Hamburg/DESY/CERN CERN, Nov 20, 2008 LCWS 2008 University of Illinois at Chicago Outlook Physics Accelerator and Detector General.
Recent news from CLIC C&S WG and CLIC-ILC WG on General Issues Ph. Lebrun CLIC Project Meeting 1 June 2011.
CLIC main activities and goals for 2018 Design and Implementation studies: CDR status: not optimized except at 3 TeV and not adjusted for Higgs discovery,
CLIC Workshop, CERN Marc Ross, ILC Global Design Effort 1 Content: Reason ILC - PM were there – introductory plenary Tolerances and ‘CTF4’.
The fourth Baseline Technical Review (BTR) - Conventional Facilities and Siting March 2012 All changes made to the CFS 2007 Reference Design during.
BDS Andrei Seryi, Deepa Angal-Kalinin, Emmannual Tsesmelis, Rogelio Tomas, Andrea Latina, Daniel Schulte Detectors Civil engineering.
Activities and news Last meeting: 2015 CERN budget allocations as expected, now distributed on accounts Annual report done, and MTP (Medium Term Plan)
Global Design Effort - CFS GDE Plenary Session 1 LCWS10 GDE Plenary Session SB 2009 ILC CONVENTIONAL FACILITIES AND SITING GROUP A. Enomoto, V.
WWSWWS Report of the World Wide Study J. Brau June 4, 2008 Dubna ILCSC Meeting.
Global Design Effort - CFS Damping Ring Baseline Technical Review 1 DAMPING RING BASELINE TECHNICAL REVIEW CONVENTIONAL FACILITIES AND SITING.
CFS / Global – 04 Aug, 2010 PM Report: SB2009: –ADI meeting 23.07: Parameter tables with low energy / low power operation –BA Workshop Planning CFS participation.
November 05, 2008CFS-GBL meeting 1 PM report Nov 5, 2008: 0) ILC08 plenaries 1) Summary of Pac review 2) Report on ttc and barc (india) 3) Summary of positron.
Global Design Effort - CFS ILC Global Systems Meeting 1 ILC GLOBAL SYSTEMS MEETING CONVENTIONAL FACILITIES AND SITING GROUP STATUS REPORT V. Kuchler,
CLIC Machine-Detector Interface Working Group (MDI) Emmanuel Tsesmelis CERN TS/LEA CLIC-ACE of 3 September 2008.
ILC D RAFT P ROJECT S CHEDULE K LYCLUSTER 500GeV K Foraz & M Gastal ILC Mechanical & Electrical Review and CFS Baseline Technical Review Many thanks to.
Global Design Effort CLIC-ILC BDS & MDI work Materials for discussion Daniel Schulte, Rogelio Tomas and Emmanuel Tsesmelis for CLIC team Andrei Seryi for.
Global Design Effort - CFS DESY Accelerator Design and Integration Meeting 1 ACCELERATOR INTEGRATION AND DESIGN MEETING CONVENTIONAL FACILITIES.
1 Future Circular Collider Study Preparatory Collaboration Board Meeting September 2014 R-D Heuer Global Future Circular Collider (FCC) Study Goals and.
Introdcution to Workpackage/Activity Reflection D. Schulte.
Tor Raubenheimer KEK Mtg Goals KEK January 19 th, 2006.
Detector Cooperation with CLIC PAC Pohang meeting November 3, 2009 F. Richard LAL/Orsay 11/03/20091.
CLIC project 2012 The Conceptual Design Report for CLIC completed – presented in SPC, ECFA and numerous meetings and conferences, also providing basis.
Summary: Site Discussion Jonathan Dorfan SLAC Plenary Session, June 6, 2008.
Global Design Effort - CFS ILC CFS and Global Systems Meeting 1 ILC CFS AND GLOBAL SYSTEMS MEETING CONVENTIONAL FACILITIES AND SITING GROUP CFS.
Fred Asiri1 Conventional Facilities and Siting Global Group (CFS) SLAC Update Conventional Facilities and Siting Global Group (CFS) SLAC Update December.
The ILC Outlook Barry Barish HEP 2005 Joint ECFA-EPS Lisbon, Portugal 23-July-05.
CFS / Global – 09 June, 2010 PM Report: SB2009: –4 two-day workshops form the core of ‘TOP LEVEL CHANGE CONTROL’ –  as advised by AAP, PAC and etc –Written.
Main Linac Technology (MLT) Meeting To be held through WebEx July 13, 2007.
J.P.DelahayeTILC08: 06/ 03/ 081 CLIC-ILC Collaboration? Following visit of CERN (Nov 07)
July 11, 2008M Ross for PM - ILC GDE - ILCDR08 closeout 1 GDE Program for the ILC Technical Design Phase Marc Ross for: Akira Yamamoto, Nick Walker GDE.
Mandate Priorities Other tasks Membership Forthcoming reports to CTC
Review of the International Linear Collider (ILC) Electrical and Mechanical System Design to be held at CERN on 21 March, 2012 The purpose of the Review.
Conventional Facilities and Siting Global Group (ARCFS)
LCWS11 AWG9 PARALLEL SESSION SUMMARY
CLIC / ILC Collaboration for CFS works
Beam Delivery Systems and the Machine-Detector Interface Terms of Reference for the CLIC-ILC Collaboration Working Group B. Parker (BNL), D. Schulte.
ILC GLOBAL SYSTEMS MEETING
CLIC-ILC BDS & MDI work.
Conventional Facilities and Siting Global Group (CFS) SLAC Update December 10, 2007 Acknowledgment: Jerry Aarons, Clay Corvin, and Esther Kweon Fred Asiri.
CLIC/ILC Collaboration Meeting: Objectives & Organization
Presentation transcript:

CLIC Workshop, CERN 1 CLIC/ILC Collaboration Report: Marc Ross (Fermilab); for Nick Walker, Akira Yamamoto Project Managers International Linear Collider – Global Design Effort

CLIC Workshop, CERN Marc Ross, ILC Global Design Effort 2 CLIC – ILC Collaboration Strategy What can ILC bring to CLIC? –Use the same cost basis. – develop a credible comparison –(ILC will help in the costing of CLIC) And CLIC to ILC: –CERN & CLIC-collaboration experts to work with ILC team on common design issues The credibility of each project within our community will be facilitated through communication

J.P.DelahayeTILC08: 06/ 03/ 08 Marc Ross, ILC3 Conclusion CLIC/ILC collaboration on subjects with strong synergy Win –Win for both studies and for HEP Ambitious but realistic and practical approach –starting on limited number of subjects –conveners to define plan of (limited) actions Most efficient use of limited resources Provide credibility to Linear Collider Community by: –mutual understanding of status, advantages, issues of both tech. –responsible preparation of the future comparison of possible options for HEP with agreed pro&cons and criteria Collaborative Competition and / or Competitive Collaboration First Report to the community – TILC08 March 2008

CLIC Workshop, CERN Marc Ross, ILC Global Design Effort 4 CLIC – ILC Collaboration Chronology November 2007 – Barish / Aymar meet and agree on basis First plenary meeting: February 8, 2008 –Working Group Definition and convener assignment (typically 2+2 conveners/group) Second plenary meeting: May 13, 2008 –Working Group Mandates – what should be accomplished prior to the fall project meetings (CLIC 08 / ILC 08 workshops) Third plenary meeting – teleconference: September 19, 2008 –Progress reports from each group Collaboration website: – Study/CLIC_ILC_Collab_Mtg/Index.htm (Thank you Sonia) Study/CLIC_ILC_Collab_Mtg/Index.htm

CLIC Workshop, CERN Marc Ross, ILC Global Design Effort 5 Five (initial) Working Groups: Civil Engineering and Conventional Facilities (CFS) Beam Delivery and Machine Detector Interface Detector and Physics Cost and Schedule Beam Dynamics Each is ‘mapped’ into a CLIC08 Working Group – –Each CLIC08 WG will have collaboration reporting in their agenda –(CFS and Cost and Schedule will meet in the ‘Technical Issues, Integration & Cost’ Working Group)

CLIC Workshop, CERN Marc Ross, ILC Global Design Effort 6 Two new Working Groups planned: Damping Rings Positron Generation Overlap criteria readily met (“ subjects with strong synergy ”) Conveners to be named soon (work already started)

CLIC Workshop, CERN Marc Ross, ILC Global Design Effort 7 ILC08 Chicago, November 16-20, 2008 Presentation of Collaboration WG activities to GDE Convener instructions: “It is important that we maintain a visible component in the working groups to address those identified issues of common interest between the CLIC and ILC collaborations. Specifically the ILC08 WG (where appropriate) should include in their schedule some block to discuss the collaborative work. It is expected that a brief progress report on CLIC-ILC collaboration activities will form part of the close-out summary. “The ILC-CLIC collaboration is currently focused on four working groups (five including Physics and Detectors) which have identified points of contact. As conveners of the ILC08 WGs, please make sure the relevant people are included in the planning discussions for this part of the programme.”

CLIC Workshop, CERN Marc Ross, ILC Global Design Effort 8 Review of Mandates (CFS): both groups will work together on areas of mutual interest for both projects, including : Civil Engineering Studies –Optimisation of Tunnel and Shaft diameters, distance between shafts (linked to safety) –Overall layout of the machine and interaction region infrastructure –Shallow site v Deep Tunnel Option –Tunnel –Single Tunnel v Double – Safety issues such as emergency egress –Environmental issues Other Infrastructure –Cooling Water ? –Power Distribution –Air Handling –Transport Issues – Radiation simulations / shielding ?

CLIC Workshop, CERN Marc Ross, ILC Global Design Effort 9 Review of Mandates (BDS): provides a forum where those technically responsible –for the beam delivery systems and –for the issues at the interface between the machines and experiments from the ILC and CLIC projects can meet and discuss issues of mutual interest. The subjects treated cover everything of common importance to the machines and experiments and includes, –(but not limited to), –machine performance for the experiments, –design and integration of the beam delivery system and –corresponding interaction regions and experimental areas, –experimental beampipes and the vacuum, radiation shielding and monitoring, –collimation system, –beam instrumentation, –luminosity and background measurement and monitoring, –mechanical supports and stabilisation, –design of the near-beam forward detectors, –data exchange and common safety issues.

CLIC Workshop, CERN Marc Ross, ILC Global Design Effort 10

CLIC Workshop, CERN Marc Ross, ILC Global Design Effort 11 Review of Mandates: (Cost and Schedule)

CLIC Workshop, CERN Marc Ross, ILC Global Design Effort 12 Review of Mandates: (Beam Dynamics) The working group should foster the exploitation of synergy between the ILC and CLIC beam physics studies. It should promote common meetings, standards, codes and studies.

CLIC Workshop, CERN Marc Ross, ILC Global Design Effort 13 Collaboration issues Note the nature of the collaboration: –What does each team bring? –What does each expect? –ILC to CLIC: Use the same cost basis. (ILC could even help in the costing of CLIC.) –CLIC to ILC: CERN expertise helpful in design studies Work a practical balance into the mandates