1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.

Slides:



Advertisements
Similar presentations
K. Long, 18 April, 2015 Beam-line status — red sky at night?
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
MICE Hall – South Mezzanine Jason Tarrant - STFC l Contents »Device checks with current South Mezzanine »South Mezzanine change summary »Conclusion.
1 MICE Video Conference Installations to date Future installation work Plans for May shutdown MICO organisation Use of Technical Board.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
MOM Summary 11/01/10 Due to the Inclement Weather it has perhaps been quieter than usual Water - Tank has been holding water fine. Some ice has been forming.
A. Bross Imperial College – 9/04 Status of VLPC Cryo-Cooler Cryostat Design Russ Rucinski (Alan Bross) Fermilab.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009.
MICE: Hall Infrastructure Chris Nelson CEng CM16 8 th Oct 2006.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
MICO 1 st February 2010 Terry Hart (MOM). MICO 1 st February June 2015 Decay Solenoid DS will not be ready for Machine Physics. Matt Hills spent.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 11 th May 2009.
Status of VLPC Cryo-Cooler Cryostat Design Russ Rucinski (Alan Bross) Fermilab.
1 MICE Radiation Shutter Description Present status Plans, schedule and remaining work MICE CM26, 24-27th March, 2010.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 12, 2010.
MOM - M.ApollonioMICO meeting - RAL - 17/3/20081 NEXT steps + proposed aims Today - START Cherenkov INSTALLATION (?) Tuesday 25 MARCH - MICO Meeting (?
M. apollonioAccel. R&D/Physics and IADR - RAL - 19/3/ Magnets Dry Run ISIS Scheduling Meeting Latest news on Target Ready to run ? Summary of: Magnets.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
MOM Report. Shield Wall – Gone Before During After 2.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO May 5, 2009.
MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO April 6, 2009.
Commissioning needs: K.Long. Routine: LN2 bottle: –Needs to be sited in MICE Hall or outside vault so that routine checks of contents can be made.
1 Implications Of Infrastructure Build The Infrastructure Project is bigger than anyone thought, but now it’s understood The cost was underestimated, but.
Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.
1 MICE Magnets Contents: Background Refurbishment Testing Installation & survey Current status Upstream beamline Open issues & concerns MICE Beamline Review,
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
1 Hall & Beamline Installation Richard Apsimon, Andy Nichols, Willie Spensley MICE Collaboration Meeting, th Feb 2008.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
Infrastructure Update As at 11 th March 2009 Remaining four plates now fitted to North shield wall North & South walls and all galleries are considered.
1 MICE PM Report Phase One installations to date Problems with target & decay solenoid and rolling platforms Phase One remaining items Progress with Phase.
1 MICE PSAG PM report Brief overview Re-planning the project Solenoids, decay and spectrometer Open issues and worries Andy Nichols, STFC, PSAG, 5/5/10.
MOM Report Galina Vankova RAL, MICE Video Conference.
Project manager report paul drumm CM16 October 2006.
K. Long, 10 October 2015 Project Manager’s report Status/progress since CM18 Looking forward Organisation Conclusions.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
1 MICE CMPB Contents: Progress to date Project management things Plans for the May shutdown Steps towards Phase Two Problems and open issues summary Andy.
Status of installed target Preparation of “demonstrator” target Chris Booth Sheffield 25 th January 2008.
Electrical & Control Power Supplies Trevor Hartnett.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, DL, 4 th -7 th June 2008.
Target Status Target installed in ISIS “Demonstrator” target in R78 Chris Booth Sheffield 7 th February 2008.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
PSI Contact PSI visit arranged for Feb 9th –Assessment of activity/contamination Possible remedial action –Seek additional equipment for solenoid Power.
DIFFUSER HARDWARE REPORT V. Blackmore J. Cobb, M. Dawson, J. Tacon, M. Tacon.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
Decay Solenoid – what do we have to do to make it work?
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
Target Commissioning Target installed in ISIS “Demonstrator” target in R78 Initial commissioning plans Chris Booth Sheffield 11 th February 2008.
G.Barber Mice Tracker Integration Harbin Jan Mice Tracker Integration Installation requirements & Procedure.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
Update: Puck and Gun Magnet March 1, Magnetized Gun 2 K 2 CsSb Preparation Chamber HV Chamber.
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
Magnetized Beam LDRD: Design Tasks February 19, 2016.
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
1 MICE CM25 Engineering Session Summary Contents: Infrastructure Diffuser Coupling Coils Radiation Shutter AFC module EMR Andy Nichols, STFC, 4-7 th November.
MICE Target Report Video Conference 29/11/07
MICE Operations Scenario Run 1
MICE PM Report Progress with the Infrastructure A few problems
Presentation transcript:

1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns Weekly MICO meeting, 7 th February 2008 Andy Nichols, RAL

2 Upstream, target, BPM Online target has been installed, tested to 500 continuous actuations, currently raised out of ISIS beam awaiting off-line target to start, due at RAL today – meeting on Friday with ISIS to discuss operating conditions – see talk by Chris B Q1,2,3, D1 all connected to water & power & interlocks Actual BPMs are not installed, untested scintillating tile devices were installed, but cannot discriminate between ISIS background and MICE beam Some stainless steel filler plates required for aperture in synchrotron – four weeks to manufacture, install next short shutdown

3 Decay Solenoid Progress now dependent on problems with Linde plant  Defective compressor rotors gone back to Linde, due in two weeks  Re-commissioning will resume then Work continues on piping & cabling form gas panel to solenoid – no real problems, but access to DSA will be needed to erect scaffolding – it is a worry that none of this work is defined properly on drawings Then we have to reconnect transfer line to solenoid, again access to DSA essential – short shutdown in March?

4 DSA, D2, Q4,5,6,cKOV stand D2 is connected to power & temporary water Q4,5,6 are connected to power and polarity check OK Water is not connected before DSA access barred – flanges not ready. But now we have the flanges but no ‘O’ rings! For the future, need to cover requirements like this on assembly drawings – that way at least we have a list of parts The cKOV stand arrived in time, but was 150mm too low despite being reviewed. New packing pieces now made – simple installation job, but…… Need access to DSA of course…  Need to follow up with ISIS – there might be a case to go in, as the radiation survey showed no difference from previous ones. Need to understand risks with non-solid shielding around solenoid

5 Q7, 8, 9 Q7 – essentially complete, needs klixons fitted, then water/power test in R6 Q8 – known as the oddball – being stripped down, new tubing required, then test as above Q9 – only manifolding refurbishment outstanding (but mostly done) Girder boxes, etc – Q8 support needs new holes tapped, stiffening plates making (Steve York at DL), Mirror plates are horizontally joined, new holes need drilling One month’s work remaining, so:  Magnets mounted by 8 th March Water & power connections will be done then, by then we had better make sure that we have all the bits

6 Open issues & concerns We have been held up by relatively mundane, but vital things, such as the water flanges Each MICE subsystem must have reasonably representative installation drawings and specification that capture all details of pipe/cable runs, flanges, fittings, seals and fasteners If nothing else, this is a requirement of the CDM regulations We have to plan for this in phase two