Deliverables, Cost, Manpower, Schedule & Maintenance Su Dong CSC Readout Replacement CDR Oct/8/2012 1.

Slides:



Advertisements
Similar presentations
ALICE © | RRB | 17 April 2013 | Catherine Decosse 24 th meeting of the ALICE Resources Review Board CERN-RRB
Advertisements

DOE/NSF U.S. CMS Operations Program Review Closeout Report Fermi National Accelerator Laboratory March 10, 2015 Anadi Canepa, TRIUMF Anna Goussiou, University.
Project Management Process. Project Complexity means that: a team of people are needed to supply expertise the work needs to be broken into manageable.
The LAr ROD Project and Online Activities Arno Straessner and Alain, Daniel, Annie, Manuel, Imma, Eric, Jean-Pierre,... Journée de réflexion du DPNC Centre.
Project Planning Dr. Jane Dong Electrical and Computer Engineering.
Link Board Upscope Frascati group Napoli group Warsaw group.
PALM-3000 Management Update A. Bouchez Team Meeting #9 10/22/2008.
NGAO Team Meeting Management Peter Wizinowich May 26, 2009.
L. Greiner 1IPHC meeting – September 5-6, 2011 STAR HFT Plans for the next year A short report on review results and plans for TPC – Time Projection.
ISSUES TO CONSIDER IN YOUR PROJECT This is a short presentation from issues discussed in a meeting of MCS3 on Tues 2 nd March 2004.
1 Timescales Construction LCR MICE Beam Monitoring counters + DAQ My understanding Jan 07 Feb 07 Mar 07 Apr 07 May 07 Jun 07 Jul 07 Aug 07 Sep 07 ISIS.
Tevatron BPM Upgrade Project Manager Overview Stephen Wolbers Tev BPM Technology Choice Review December 16, 2003.
WBS 1.7: AFE II Project Cost and Schedule Alan Bross DZero Run IIb AFE II Director’s Review April 13, 2005.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
HPS Budget and Schedule Marco Oriunno, June 4-6, 2013 HPS Collaboration Meeting, JLAB.
WP1.2 – Photon Detectors Stephan Eisenhardt University of Edinburgh  Budget  Milestones  Progress Report  Partners: International Collaborating Groups.
August 2 and 3, 2010 Project Cost, Schedule, Risk and Contingency Jay Elias.
U.S. MICE Schedule, Cost, & Risks Peter H. Garbincius Mark Palmer, Alan Bross, Rich Krull Fermilab Presented at RAL – November 13, 2013.
L. Greiner 1IPHC meeting – May 7, 2012 STAR HFT Plans for the next year A short report on HFT/PXL plans for post May 2012 TPC – Time Projection Chamber.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Wesley SmithAug. 18, 2010 Trigger Budget Review: Labor & M&S - 1 US CMS FY 2011 Budget Review Trigger Labor & M&S Wesley Smith Aug. 18, 2010 Outline Overview.
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
Cost Estimate Marion White (Argonne) SCU 3-Lab Review Meeting December 16, 2014.
Workpackages & deliverables Funding & manpower Uncovered areas Institutions round table Institutes commitments Vit Vorobel, AFP kick-off1.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
M&O status and program for ATLAS LAr calorimeter R Stroynowski (on vacations)
Status and planning of the CMX Wojtek Fedorko for the MSU group TDAQ Week, CERN April , 2012.
Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array FPGA Spectrometer.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)
U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine.
TeV BLM Review 4/19/041 Tevatron BLM Review - Schedule BLM Replacement Prototype schedule: Provide prototype digitizer cards, crate, readout path by ~
1 ME1/1 OTMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project.
1 The Cost & Schedule to Accomplish the Transition Proposed SLAC Controls Upgrade December 1, 2010 Ray Larsen.
1 Global Design Effort: Controls & LLRF Controls & LLRF Working Group: Tuesday Session (29 May 07) John Carwardine Kay Rehlich.
Introduction CSC ROD review 8 October 2012 Andrew J. Lankford University of California, Irvine 1.
Status of ATLAS Resources Presentation to RRB Markus Nordberg ATLAS Resources Coordination CERN-RRB
Global Design Effort: Controls & LLRF Americas Region Team WBS x.2 Global Systems Program Overview for FY08/09.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
Computing Division FY03 Budget and budget outlook for FY04 + CDF International Finance Committee April 4, 2003 Vicky White Head, Computing Division.
U.S. ATLAS Executive Meeting Silicon M&OWBS 3.1 August 3, 2005Toronto, Canada A. Seiden UC Santa Cruz.
Department of Particle Physics & Astrophysics CSC ROD Replacement Conceptual Design Review New ROD Complex (NRC) Overview & Physical Design Michael Huffer,
1 Project Management Software management is distinct and often more difficult from other engineering managements mainly because: – Software product is.
Executive Committee, Toronto August 3, 2005 TRT Barrel WBS 1.2/3.2 Harold Ogren Indiana University.
17 th November 20061M. Battistin CERN LEAF Committee 2/R-030 8h30 – November 17 th 2006 Michele Battistin (TS/CV/DC) TS/CV Detector Cooling On call and.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
1 MICE RLSR Summary of Issues Relating to Question One of Review charge ‘ Given a resource-limited, year-by-year schedule for the project, how reasonable.
August 24, 2011IDAP Kick-off meeting - TileCal ATLAS TileCal Upgrade LHC and ATLAS current status LHC designed for cm -2 s 7+7 TeV Limited to.
Governor’s Office of Emergency Services 1 The Governor’s Office of Emergency Services Application and Benefit Cost Analysis (BCA) Training.
09/05/2006Project Status Report1 Nova DAQ Software Development Project Status Update for 09/05/2006 Gerald Guglielmo (CD/CEPA/OAA)
UK Project Plan (Finance & Risk) Alan Grant STFC DL RLSR 5 th April 2016.
ALICE Trigger Upgrade CTP and LTU Design Review ALICE CTP and LTU Upgrade Design Review CERN 27 th January 2016 Budget, time schedule, resources David.
Summary of IAPP scientific activities into 4 years P. Giannetti INFN of Pisa.
SCT Project Management Issues
U.S. ATLAS TDAQ FY06 M&O Planning
TDAQ Phase-II kick-off CERN background information
TileCal upgrade EVO meeting Demonstrator tesks
Face to Face Meeting – March 2012 Sarah Morgan
10/month is the present production rate 2 FTE + sporadic contributions
Francesco Forti University and INFN, Pisa
Preparations for a Lehman Review
VLA to EVLA Transition Plan
EIC Tracking Meeting, March 26, 2012
TSF Upgrade Project Overview Resources Plans and Timetable
Durham and Orange Transit Plan Funding Needs
Details supporting the increase
05/08/09.
Calice Tile-HCal and Tail-catcher/Muon Tracker
East Hall under construction
Detector Proto-Technical board Sep 30, 2010
Presentation transcript:

Deliverables, Cost, Manpower, Schedule & Maintenance Su Dong CSC Readout Replacement CDR Oct/8/2012 1

Deliverables and Hardware Cost ComponentsSystemSparesUnit cost (K$) Sum cost (K$) COB549,76087,840 CSC RTM (FEX)443,33026,640 SFP RTM (Formatter)121,2003,600 ATCA Shelf (crate+PSU)115,50011,000 TDAQ control server114,0008,000 Miscellaneous cables1,000 Total (include 9% overhead) 138, ,510 2 Production system (FY14): Prototype and test stands (FY13): -2*(COB + RTM) (25 k$) - CERN test stand shelf + server (10K$) - Need to increase 2*(COB+RTM) at SLAC ?

Manpower PersonnelFY12FY13FY14 Mike Huffer Ric Claus Jim Russell SLAC engineer + tech support Raul Murillo Garcia Total (US ATLAS M&O) SLAC RCE core effort supported by R&D funds for COB+RTM hardware and core firmware are not charged to US ATLAS. Only CSC specific implementation manpower are listed in table above. Additional Physicist resources: o Nicoletta Garelli (SLAC project scientist) [SLAC research budget] o Michael Schernau (UCI project scientist) [US ATLAS M&O] o Andy Nelson (UCI postdoc) [UCI research budget] o Anthony DiFranzo (UCI grad student) [UCI research budget] There will be manpower needs for FY15 commissioning with first beam beyond the regular asymptotic operations, but assumed that will be operations M&O after construction, to be addressed later.

Maintenance Both SLAC and UCI are committed to operate the NRC throughout its operational lifetime, foreseen as /LS2. SLAC and UCI will have CERN based experts taking direct responsibilities for hardware maintenance and software updates. SLAC based design team will supply operational support which will benefit from a larger base of expertise that’s necessary for development and support of RCE applications for other projects. 4

Schedule Key dates and milestones of a preliminary schedule: –Oct/8/2012: Conceptual Design Review –Mar/8/2013: Fully functional COB+CMB+RTM preproduction hardware and RCE Gen-II core firmware ready for testing. –Jun/14/2013: Final Design Review. Prototype firmware and software designs are validated on prototype hardware. –Feb/05/2014: Completion of full set of hardware production. –Apr/09/2014: System Readiness Review. Full system DAQ operations demonstrated with data injector input emulation. –Aug/02/2014: Join ATLAS for combined commissioning. Contingencies to mitigate schedule risks: –All tasks are based on fractional time efforts with key personnel available at a larger fraction of their time if needed. –Task to task sequence has some time gaps built-in. –System validation with data injectors largely decoupled from availability of CSC detector & P1 infrastructure until May/

Schedule 6 Task durations are not 100% FTE times, but actual working days needed based on fractional FTE efforts. “RCE core” refers to the larger RCE core R&D team at SLAC. Task resource list is only some names with main responsibility while some common activities such as major tests and reviews will involve almost the entire team.

Backup 7

COB Cost ComponentsMultiplicityUnit Cost ($) Summed cost ($) COB PCB & loading11800 COB motherboard components1700 CMB PCB and loading CMB components Total cost per COB Parts are mostly based on existing purchases COB PCB cost based on a quote of 10 boards CMB PCB cost extrapolated from a 8-board quote of $475/board DTM CMB cost with 1 RCE approximated to be same as 2-RCE DPM Production will most likely be joint with at least small requests from other projects

RTM costs Cost estimates all based on dedicated small volume production 9 ComponentsMultiplicityUnit Cost ($) Summed cost ($) CSC RTM PCB & loading1350 CSC RTM MPO transceivers CSC RTM other components100 Total cost per CSC RTM3330 SFP RTM PCB and loading1350 SFP RTM transceivers SFP RTM other components50 Total cost per SFP RTM1200