Wesley SmithAug. 18, 2010 Trigger Budget Review: Labor & M&S - 1 US CMS FY 2011 Budget Review Trigger Labor & M&S Wesley Smith Aug. 18, 2010 Outline Overview.

Similar presentations


Presentation on theme: "Wesley SmithAug. 18, 2010 Trigger Budget Review: Labor & M&S - 1 US CMS FY 2011 Budget Review Trigger Labor & M&S Wesley Smith Aug. 18, 2010 Outline Overview."— Presentation transcript:

1 Wesley SmithAug. 18, 2010 Trigger Budget Review: Labor & M&S - 1 US CMS FY 2011 Budget Review Trigger Labor & M&S Wesley Smith Aug. 18, 2010 Outline Overview of Activities FY 11 Budget  M&S  Labor Summary

2 Wesley SmithAug. 18, 2010 Trigger Budget Review: Labor & M&S - 2 Overview of US CMS L1Trigger Activities – FY 10 & 11 Operating Regional Calorimeter Trigger Maintenance of Regional Calorimeter Trigger Evolution/Adjustment of Regional Calorimeter Trigger R&D on Calorimeter Trigger Upgrade* Simulation Studies for Calorimeter Trigger Upgrade* Operating CSC Muon Detector Trigger Maintenance of CSC Muon Detector Trigger Evolution/Adjustment of CSC Muon Detector Trigger R&D on CSC Muon Trigger Detector Upgrade* Operating CSC Muon Track-Finder Trigger Maintenance of Endcap Muon Track-Finder Trigger Evolution/Adjustment of CSC Muon Track-Finder Trigger R&D on CSC Muon Trigger Track-Finder Upgrade* Simulation Studies for Endcap Tracker-Muon Trigger Upgrade* * Covered as part of upgrade presentation

3 Wesley SmithAug. 18, 2010 Trigger Budget Review: Labor & M&S - 3 FY 2011 Budget - Labor Details on next slides Engineer Tech Total Labor Total FTE InstituteCostFTECostFTE Florida60,0000.527,0000.587,0001 Rice40,0000.25 40,0000.25 Wisconsin87,0000.540,0000.5127,0001 Grand Total187,0001.2567,0001254,0002.25

4 Wesley SmithAug. 18, 2010 Trigger Budget Review: Labor & M&S - 4 FY 2011 Budget – Labor: Comments The plan for FY11 is to continue the extended data run. We are learning how to operate the trigger system under beam collisions with synchronized interactions and collision data flow in cards, links and backplanes We have to be ready for surprises in all hardware areas, particularly as the luminosity and data-flow increase.  As the luminosity climbs, we can expect the changing occupancy to present a changing hardware situation as well We need the expert engineering team ready to respond to analyze & diagnose aspects of how the hardware behaves. We need to be ready for additional repairs, adjustments or even modifications based on what we learn. Finally, we will have a heavy ion run where the trigger may also behave differently and need more diagnostics/modifications…

5 Wesley SmithAug. 18, 2010 Trigger Budget Review: Labor & M&S - 5 FY 2011 Budget – Labor: Cal, Mu Trig scope RCT (Wisc.) consists of 2000 high speed electronics cards, 340 of them are large form factor (9U VME) cards with thousands of components in 18 custom backplane crates and rest are high-speed link (4 Gbaud) mezzanine cards. Also custom clock distribution & high-power control system. All in USC55, accessible 24X7 RCT is mostly programmed through memory lookup tables (LUTs), but has some firmware mostly in controls, timing. On detector CSC Trigger Electronics consists of 80 Muon Port Cards (MPC) & clock/control cards (CCC) (Rice) which operate in peripheral crates on the disks. These are large high-speed boards (9U VME) with a large FPGA. They are not accessible during beam but can have firmware revisions Off detector CSC Track-finder crate has a custom backplane and 12 operating Sector Processor Cards (SP) (Florida) & Sorter Card (SC) (Rice). These are large high-speed boards (9U VME) with multiple large FPGAs. They are in USC55, accessible 24X7. All of the above systems maintain test systems in B904

6 Wesley SmithAug. 18, 2010 Trigger Budget Review: Labor & M&S - 6 FY 2011 Budget – Labor (cont’d) RCT Eng (50%) – Tom Gorski, Wisconsin (50% on Cal Trig Upgrade): Lead RCT engineer & designer: debugging problems, diagnosing failed boards, analyzing system performance, revise control/timing firmware RCT Tech (50%) – Bob Fobes, Wisconsin (50% on Cal Trig Upgrade): Repair of broken boards, repair/replacement of broken cables, power supplies, spares inventory (1000’s of parts) CSC “on detector” Trig. Eng (25%) – Mike Matveev, Rice (25% on Mu Trig Upgrade, 50% on EMU): MPC,CCC,SC engineer & designer: firmware revisions, debugging problems, diagnosing failed boards, analyzing system performance CSC “off detector” Trig. Eng (25%): Alex Madorsky, U. Florida (25% on Mu Trig Upgrade, 50% on EMU): : Lead SP, TF backplane engineer & designer: firmware revisions, debugging problems, diagnosing failed boards, analyzing system performance

7 Wesley SmithAug. 18, 2010 Trigger Budget Review: Labor & M&S - 7 FY 2011 Budget – Labor (cont’d) CSC “off detector” Trig. Eng. (25%): Lev Uvarov, U. Florida PNPI subcontract (25% on Mu Trig Upgrade, 50% on EMU): SP, TF backplane engineer & designer: firmware expert, debugging problems, diagnosing failed boards, analyzing system performance, expert on interfaces to EMU system. CSC “off detector” Trig. Tech. (50%) -- Arman Ballado, U. Florida. Assist engineer in routine tests and diagnoses, revision of LUT contents and firmware configurations as requested.

8 Wesley SmithAug. 18, 2010 Trigger Budget Review: Labor & M&S - 8 FY 2011 Budget – M&S Florida:  Annual transport. Meyrin ↔ Prevessin & P5 for trigger operations (CERN car+fuel): $10K  CERN pool charges, small parts, refurbishing boards: $6K  Server plus RAID disk pool for trigger commissioning/performance studies: $8K Rice:  No FY11 request because of unspent funds in FY08,09 still available  CERN pool charges, small parts, refurbishing boards: $6K spent against FY08.09 funds Wisconsin:  Replacement Cables, Power Supplies & Components depleted in spares stock: $15K  Annual transport. Meyrin ↔ Prevessin & P5 for trigger operations (CERN car+fuel): $15K M&SInstitution FY 11 Budget Request Counting Room Muon Trig M&SFlorida24,000 Detector Muon Trig M&SRice0 Calorimeter Trig M&SWisconsin30,000 Total 54,000

9 Wesley SmithAug. 18, 2010 Trigger Budget Review: Labor & M&S - 9 US FTE Fraction of Trigger L1:  Above table shows US CMS provides 27% of L1 Trigger Physicists HLT:  Trigger Studies Group MoA pledges total 49.5 FTE  US CMS TSG MoA Pledges total 31.5 FTE  US CMS is 64% of TSG pledged FTE  Note this includes some students Level-1 TriggerPhysicists% Austria70.27 Italy10.04 Poland30.12 Portugal10.04 Spain10.04 UK60.23 US70.27 Total261.00

10 Wesley SmithAug. 18, 2010 Trigger Budget Review: Labor & M&S - 10 Summary and Conclusions Labor:  Have a strong experienced engineering team that represents the US CMS trigger “institutional knowledge”.  This team is essential to keeping the trigger system working  Whatever time this team does not spend on M&O, is spent on upgrades. The fraction has been about 50% each.  The support of this team is split between M&O and Upgrades M&S:  Reaching a steady-state and understood level General Comment:  Expect that all funding will be needed and unexpected events will be covered by contingency


Download ppt "Wesley SmithAug. 18, 2010 Trigger Budget Review: Labor & M&S - 1 US CMS FY 2011 Budget Review Trigger Labor & M&S Wesley Smith Aug. 18, 2010 Outline Overview."