1 US Cost & Schedule Summary W. R. Edwards US Project Manager CD-2/3a Review January 8, 2008 BNL.

Slides:



Advertisements
Similar presentations
Prototype of the Daya Bay Neutrino Detector Wang Zhimin IHEP, Daya Bay.
Advertisements

3 Oct Cost and Schedule Update Craig Ogilvie, Iowa State University Analysis of system risks Update schedule  Critical path.
Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 1 DOE/NSF Review of the Dark Energy Survey (DES) Project SC 6/7 Cost, Schedule.
GLAST LAT ProjectLAT Face to Face, July 17-18, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center
1 Daya Bay Muon system Installation Workshop, IHEP, July 14, Updated RPC Gas System Installation Plan Changguo Lu Princeton University.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
OFFICE OF SCIENCE Review of Critical Decision 2 for the Large Liquid Argon Detector for Neutron Physics (MicroBooNE) at Fermi National Accelerator Laboratory.
1 Daya Bay Muon system Installation Workshop, Daya Bay, March 22, Daya Bay RPC Gas System Installation Plan Changguo Lu Princeton University.
Overview of the Schedule and Budget for the ARCS Instrument Doug Abernathy ARCS Hardware Project Manager ARCS Construction Project Review DOE Germantown.
RF Cavity / Coupling Coil Module
DOE Site Visit: Daya Bay7/18/20111 Daya Bay Steve Kettell BNL 1)Status 2)BNL roles.
Common PDR Problems ACES Presentation T. Gregory Guzik March 6, 2003.
NEDM Construction Project Cost & Schedule Philosophy Vince Cianciolo, ORNL Physics Division Internal Cost & Schedule Review 02/11/2005.
NuMI NuMI Overview NBI 2002 S. Childress (FNAL) 14 March ‘02 NuMI / MINOS Overview.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier Director for Conventional Facilities CD-2 Planning May 8, 2007.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck NLSL II Deputy Director (Project Management)
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Slide 1 6-Nov-98PHOBOS Review: Cost & Schedule Cost & Schedule S. Steadman, MIT PHOBOS Cost & Schedule Review Technical Advisory Committee BNL November.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Cryo AIP Muon Campus AIP Review Arkadiy Klebaner January 23, 2012.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
Cheng-Ju S. Lin Lawrence Berkeley National Lab (On Behalf of the Daya Bay Collaboration) 17 July 2010 Status of the Daya Bay Neutrino Oscillation Experiment.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 1 Project Management W. J. Foyt Project Scope Timeline Cost Estimate.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
The Daya Bay Experiment to Measure  13 Herbert Steiner UC Berkeley & LBNL On behalf of the Daya Bay Collaboration Presented at the Erice School/Workshop.
PHENO 2010 Christopher White, IIT 1 The Daya Bay Reactor Antineutrino Experiment Christopher White 1.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
M. Bonesini - MICE Inst Meeting M. Bonesini INFN Milano TOF installation plans.
,,,,, The Daya Bay Reactor Neutrino Experiment Liangjian Wen On behalf of the Daya Bay Collaboration Institute of High Energy Physics Daya Bay Detectors.
KOPIO Catcher System RSVP Baseline Review Brookhaven National Laboratory April 20, 2005 Noboru Sasao / Tadashi Nomura (Kyoto U.)
TOF Preliminary Design and Safety Review Project Management Controls R. L. Brown.
David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.
The Daya Bay Reactor Neutrino Experiment R. D. McKeown Caltech On Behalf of the Daya Bay Collaboration CIPANP 2009.
Tevatron BPM Upgrade Stephen Wolbers CD Accelerator Coordination Meeting August 3, 2004.
LHC CMS Upgrade Project CD-1 Alternative Selection and Cost Range Steve Webster Federal Project Director August 26, 2013 CD-1 Executive Session.
DoE Review January 1998 Online System WBS 1.5  One-page review  Accomplishments  System description  Progress  Status  Goals Outline Stu Fuess.
D. M. Lee, LANL 1 07/10/07 Forward Vertex Detector Cost and Schedule.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
AGS RSVP Weekly Meeting P. Pile 24 Mar 2005 AGS RSVP Weekly Meeting 24 Mar 2005 Useful Links: RSVP Project : C-AD.
Daya Bay Reactor Neutrino Experiment On behalf of the DayaBay collaboration Virginia Polytechnic Institute and State University Joseph ykHor YuenKeung,
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
KOPIO Catcher System RSVP Preliminary Baseline Review Brookhaven National Laboratory April 6, 2005 Tadashi Nomura (Kyoto U.)
1 Daya Bay Project Design Review Status Ralph L. Brown US Chief Engineer January 9, 2008.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
1 Muon Veto System and Expected Backgrounds at Dayabay Hongshan (Kevin) Zhang, BNL DayaBay Collaboration DNP08, Oakland.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier NSLS-II Conventional Facilities Schedule Review December 13, 2006.
Proposed LCLS-II SCU Schedule Soren Prestemon (LBNL) SCU 3-Lab Review Meeting December 16, 2014.
Collaborating for Quality Quality Assurance (QA) & Quality Control (QC) in the Accelerator Project (ACCSYS) Matthew Conlon ACCSYS QA/QC
DOE Review of LARP – Feb 17-18, 2014 DOE Critical Decision Process Ruben Carcagno February 17,
LARP Review, June 10, 2013Magnet Cost and Schedule – M. Kaducak 1 IR Quadrupole Cost and Schedule Marc Kaducak LARP Review June 10, 2013.
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
LARP Review, June 10, 2013Cost and Schedule Overview – M. Kaducak 1 Cost and Schedule Overview Marc Kaducak LARP Review June 10, 2013.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Schedule Steve Sawch Asst. Director, Construction Management CF Advisory Committee Review of the.
Long-Baseline Neutrino Facility LBNF News and brief overview of Beamline plans for the next few months Vaia Papadimitriou Beamline Technical Board Meeting.
ELENA installation progress F. Butin / ELENA collaboration.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
WBS 1-7 System Assembly & Installation John Voirin August 10-11, 2011.
Resource Loaded Schedule and Budget Profile
Jim Fast Pacific Northwest National Laboratory
LIU Wire Scanner Milestones June 2017
News and brief overview of Beamline plans for the next few months
Electron Beam Systems ETC and Methodology
X-Ray Endstations Update
Conventional Facilities
X-Ray Endstation Systems (XES) 2006 Schedule
Presentation transcript:

1 US Cost & Schedule Summary W. R. Edwards US Project Manager CD-2/3a Review January 8, 2008 BNL

2 Outline  US Baseline Cost Overview  Contingency Analysis  Comparison of CD-1 vs CD-2 Costs  DOE & Project Funding Profiles  Construction Schedule & Major Milestone Overview  Critical path analysis  Long-Lead Items for CD-3a  Summary

3 WBS & Experiment Scope  1.1 Antineutrino Detector (AD)  1.2 Muon System  1.3 Calibration and Monitoring Systems  1.4 Electronics & Online  1.5 Offline Hardware & Software  1.6 Conventional Construction and Equipment  1.7 Installation and Test  1.8 System Integration  1.9 Photomultiplier Systems  New WBS item  1.10 Project Management

4 Notes:  TPC is in At Year (AY) US $ - escalated at 3% per year in the Resource Loaded Schedule  Cost Books are in Base Year FY08 US $ - unescalated  Be aware of this subtle difference when reviewing all the numbers.  It amounts to a difference of less than $300K for the total Project  I will attempt to point this variation out throughout my talk(s)

5 US Cost - TPC Note: TPC is in AY US $ - Escalated

6 Contingency Analysis Note: All numbers in AY US $ - Escalated

7 Contingency Analysis

8 Comparison of CD-1 vs CD-2 Costs Note: These values are in FY07 & FY08 US $ - unescalated

9 Funding Profile -

10 Contingency by FY-

11 Schedule Overview -

12 Major Milestones Summary

13 Daya Bay Near Hall Critical Path Install AD's and fill pool Install calibration units DB Near Hall ready to take data Filling hall ready for beneficial occ. Prepare filling hall liquid storage tanks Mix all required LS in filling hall Prep filling hall for first filling operation Fill DB near, install cover gas & seal Muon PMT system test in DB Near Empty DB Near pool 4 weeks float Install muon PMT’s, cables in supports Install muon PMT support modules Install tyvek sheeting on PMT frame 4 weeks float PMT procurement, testing and prep Availability of PMT's for muon system Install muon PMT’s, cables in supports 3 weeks float DB Near Hall ready for beneficial occ. DB Near Hall prepped for installations Fill first AD pair in filling hall 4 weeks float 1st pair steel & acrylic vessels at SAB Prep SSV’s and install acrylic vessels Install PMT ladders & tank covers Connect PMT cables, debug & test (SAB) Transporter delivered to SAB 4 weeks float

14 Ling Ao Near Hall Critical Path LA Near Hall available for beneficial occ. LA Near Hall prepped for installations Install pool lining in LA Near Hall Install AD support structure Install PMT support modules in pool Install Tyvek sheeting on muon frames Fill DB near, install cover gas & seal 3 weeks float Install AD's and fill pool Install calibration units Checkout & commissioning of LA Near LA Near Hall ready to take data LA Near Hall available for beneficial occ. Install RPC HV elements in LA Near Hall Install RPC supports in LA Near Hall Install RPC panels in LA Near Hall Test RPC's in LA Near Hall Muon PMT system test in LA Near Empty LA Near Hall pool Fill 2nd AD pair in filling hall

15 Far Hall Critical Path 5 weeks float Fill 2nd AD pair for Far Hall Install 2nd AD pair in Far Hall Fill pool in Far Hall Install calibration units Far Hall ready to take data Delivery of PMT mounts and ladders for Far Hall 2nd AD pair Assembly of PMT ladders for 2nd AD pair for Far Hall Installation of PMT ladders in 2nd AD pair for Far Hall Far Hall available for beneficial occ. Install FAR hall pool lining Install AD support in FAR Hall Install PMT support modules in pool Install Tyvek sheeting on muon frames Fill pool, install cover gas & seal Muon PMT system test in Far Hall Empty LA Near Hall pool Fill 1st AD pair for Far Hall

16 Long Lead Items (CD-3a)  Highest to lowest $ value :  Phototubes & bases (full spec & RFP exists)  Acrylic Vessels (PDR done; FDR in Dec)  Transporter (full spec written)  Hi-Resistivity Water System elements  PMT High-Voltage System  Teflon-lined ISO tank (filling Hall)  Gd-LS production processing equipment  Gd-Chloride, acids and Bis-MSB

17 Summary -  US scope well defined – international scope split complete – per MOU Detailed Deliverables List  US cost estimate is very mature – Basis of Estimate is well detailed  Integrated and resource loaded Project Schedule is complete lines  Budget is sufficient; very adequate contingency – problem has been the funds profile, especially FY08  University Agreements have made it possible to begin experiment operations early (FY10)  Project Cost and Schedule is ready to be baselined

18 Backup slides