1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.

Slides:



Advertisements
Similar presentations
Andrew Moss ASTeC MICE Project Board 28 th June 2011 MICE RF System.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
Collaboration meeting, RAL, 4 th – 7th November 2009 Andrew Moss ASTeC Collaboration meeting, RAL, 10 th – 13 th november 2009 MICE RF Amplifier Status.
MICE Target Report Chris Booth (for target team) Sheffield 7 th May 2009.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
Target: K. Long, 16Nov2009. Schedule for T2 re-instatement: T2#2: – Inspection of T2#2 documented in MICE Note 272 Some issue with Notes site … couldn’t.
1 MICE Video Conference Reception of FC magnets Andy Nichols, STFC,
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
1 UKNF/MICE OsC PM report Summary assessment of MICE Risks, pressures and worries Project management Electrical substation, accommodation Redefining the.
MOM - M.ApollonioMICO meeting - RAL - 17/3/20081 NEXT steps + proposed aims Today - START Cherenkov INSTALLATION (?) Tuesday 25 MARCH - MICO Meeting (?
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Stator Plan & Schedule Chris Booth 2 nd March stators to construct for mid-April. One complete coil assembly recovered from ISIS drive. Coils recoverable.
Target: K. Long, 21Dec2009. Schedule for T2 re-instatement: T2#2: – Next steps: Non-DLC bearings: – Continuing delay in material delivery! » Vespel delivery.
Spectrometer Solenoid and RFCC Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Target: K. Long, 16Nov2009. Schedule for T2 re-instatement: T2#2: – Next steps: Non-DLC bearings: – Continuing delay in material delivery! » Vespel and.
Andrew Moss ASTeC 7 th December 2011 MICE RF System.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.
1 MICE RF Daresbury Laboratory Support Joe Orrett - ASTeC.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
UKNF/MICE PSAG, 3/5/11 Spectrometer solenoids: –Repair plan still ‘in approval’, already two months late –Workshop/mini review at LBNL 10 th /11 th May.
Infrastructure Update As at 11 th March 2009 Remaining four plates now fitted to North shield wall North & South walls and all galleries are considered.
1 MICE PSAG PM report Brief overview Re-planning the project Solenoids, decay and spectrometer Open issues and worries Andy Nichols, STFC, PSAG, 5/5/10.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
Project manager report paul drumm CM16 October 2006.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
1 MICE CMPB Contents: Progress to date Project management things Plans for the May shutdown Steps towards Phase Two Problems and open issues summary Andy.
Electrical & Control Power Supplies Trevor Hartnett.
Andrew Moss ASTeC CM32 9t h February 2012 RAL MICE RF System.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
MICE VC Alain Blondel 1 MICE NEWS MICE VC 161 Agenda Overall schedule Magnetic field mitigation review Status of things.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MPB 31 October 2012 and FAC 15 November monitor how well we are doing in assembling step IV ! -- should deliver a ‘realsitic schedule scenario’
1 MICE CM27 PM Report Re-defining the UK project this FY Schedule things Apologies and accommodation Andy Nichols, STFC 7 th July, 2010.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
1 MICE PM report – status of Phase II Target update Spectrometer solenoid FC & coupling coils Schedule considerations Project accommodation & management.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
MICE VC Alain Blondel 1 1. MOM is now Victoria 2. Linda Coney is new MICE Online Group coordinator (rep Jean-Sebastien) May we held.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
Programme for “Target 3” – test of alternative bearing materials (from Jason Tarrant) –Drawing updates by 11 th November –Bearings: Material approval –
1 MICE PM Report General Update –Phase I nearing completion –MICE Power –Actions for Decay solenoid & target –Follow-ups from last VC –Conclusions MICE.
Andrew Moss ASTeC TIARA Mid term meeting 12 th 14 th June 2012 CIEMAT ICTF Progress on the MICE RF System.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
MICE RF System Overview Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory Andrew Moss STFC Daresbury Laboratory MICE UK.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
MICE RF – Installation at RAL Tim Stanley RAL 7 November 2013.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Next Collaboration meeting will be at Cosener’s14-16 February meeting at Coseners House.
1 MICE CM29 Engineering Summary Cooling channel moving platforms – Norbert Floor Beams and plates – Andy L Magnetic modelling – Mike RF Engineering – Andy.
1 MICE CM25 Engineering Session Summary Contents: Infrastructure Diffuser Coupling Coils Radiation Shutter AFC module EMR Andy Nichols, STFC, 4-7 th November.
Andrew Moss ASTeC, Daresbury Laboratory October 2010 MICE RF Amplifier Status.
MICE Spectrometer Solenoids Step IV running
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
Stator Plan & Schedule Chris Booth 2nd March 2009
Resource Loaded Schedule and Budget Profile
MICE CM28 Engineering Session Summary (On behalf of Wing)
MICE Target Report Video Conference 29/11/07
MICE CM31 Schedule summary
MICE PM Report Progress with the Infrastructure A few problems
Renovation of the 45-year old PS magnets
Presentation transcript:

1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009

Target News Online target working well Now part of routine MICE shifts Regular inspections, nothing to report Offline target/re-engineering going OK T3, all new parts are made except bearing liners Waiting for plastic bearing material, Torlon/Vespel Quite clear now that DLC coating of metallic bearings is problematic, so have dismissed it Also DLC on DLC working in vacuum not such good idea First thing is to re-build T2 with plastic bearings and run it and see Some minor open issues with plastics, but nothing thought serious 2

Target news Plans and Dates (only based on informal discussion): Mid January – aim to have T2 rebuilt with Plastic bearings Mid January – March – Run T2 and then assemble T3 in identical format if worth doing Easter shutdown – aim to have two identical targets to resume on-line/offline programme Stator considerations: In parallel to above, stator QA programme is underway: Mechanical field survey rig (G.Barber) to assess magnetic assymetries ASD at RAL have been asked to help Sheffield group with precise coil winding – square conductors and precision coil formers and uniform vacuum impregnation Worry is that Jason Tarrant leaves MICE in January

Outcome of the Spectrometer Solenoid Review Very productive review held at Berkeley on 18 th, 19 th November, chaired by Pasquale Fabbricatori Briefly the important points are: The overall thermal balance of the magnet is still not completely understood, but this is being addressed by an ANSYS model and more experimental data Given the circumstances and schedule constraints, the addition of a fourth single-stage CCR to the HTS lead area is the right thing to do Operating margin of magnet two to be measured during cooldown The more complete fix to magnet one should be continued with 4

Spectrometer solenoid 5

Spectrometer Solenoid Dates and decision points: –December – cooldown and training of magnet #2 –Mid January, 2010: Magnet perfoms against acceptance criteria Deliver to FNAL for field mapping, then RAL by mid April, or: Fails to meet acceptance criteria, so: More complete fix required, then approx ten months’ work Likely outcome here is that magnets one & two deliveries converge Important to remember: neither scenario will get Step II taking data before August 2010 (long ISIS shutdown) So, the plan will have to change

New plans for Steps II & III At MICE TB this Monday, agreed that STEP II is abandoned And that we go straight to STEP III and have it ready for data-taking by February, 2011 (end of long shutdown) The scientific case for Step III.1 (LiH solid absorber is re- visited) Yet to be agreed by MICE EB – next week FC #1 will arrive July ‘10, will need storage, but in reality the ‘spare’ time will be very useful Actions: Means we integrate two magnets in parallel More space required, opened negotiations for R79 Installation staff profile will look different Top-level schedule to be re-built around these dates 7

RF Power Lifted from Andy Moss! Retest of medium power amplifiers have been done in the last month Electrical checks of large amplifier auxiliary electrical systems underway CERN HT connection used to speed up testing Connecting together medium and large power amplifiers Should have results of testing with RF in December for entire system into test load 8

RF Power 9 This is what we have to fit in R5.2, More complex than it was, this is a huge unknown! Really need to get on with design work as early as we can

RF Power Present RF project plan: Test large 116 amplifier Design hall coax in detail and work out how to fit it all in space for steps 5 and 6 Assemble CERN amplifier and test with current power supplies Autumn 2010, move first amplifier system to MICE hall and install Conclusion: Large amplifier ready and will re-commission to 1MW using old tubes Will run for as long as possible to develop understanding and look for weak points CERN amplifiers on site awaiting build Hall layout needs careful work search for smaller key coax components if possible Two new TH116 tubes have been delivered to DL, two more due soon 10