18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page

Slides:



Advertisements
Similar presentations
Status of EC-C assembly at Liverpool C Buttar EC PAR, Nikhef Nov 04.
Advertisements

SCT BARREL PAR - RAL May 2003 Status of Barrel Mechanical Structures - Cylinder manufacture - Bracket and small components manufacture - Dry assembly.
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
Tracker Subsystem1 GLAST LAT Project FM8/14 PSR, Oct. 5, 2005 GLAST LAT Tracker Towers 8/14 Pre-Ship Review INFN-Pisa.
27 September 2005A.Ciocio - ID Week1 SCT Service Installation Overview Status of Type IV Cable Installation Type II/III Cable Installation Plan for the.
Seog Oh/ Duke University/June, 2003 TRT/ ATLAS week at CERN Duke Production Status.
SCT Power Supply Installation Schedule Jan Bohm, Prague AS, 4 th November 2005 The SCT Power Supply System will be installed in 22 LV&HV racks situated.
GLAST LAT ProjectMonthly Review, September 1, Tracker SubsystemR. Johnson 1 GLAST Large Area Telescope: Tracker, W.B.S August Status Meeting.
Atlas SemiConductor Tracker Andrée Robichaud-Véronneau.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Lab5 Production Status: Optics and RBX integration Pawel de Barbaro U. of Rochester.
California Friendly ® Landscape Training Irrigation System Troubleshooting The Metropolitan Water District of Southern California and the Family of Southern.
Walls crates cables gas chambers electronics CERN adb.
31 January 2006A.Ciocio - SCTSG1 Type IV cables and PP3 Installation Type IV installation Connector in situ work Status of PP3 Testing.
29 November 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status of Type IV installation Connector in situ work Status of PP3 Testing.
ECAL status Outline: Signal cable connectors quality check results: –ADC side –PM side ECAL PM/C-W channels commissioning status Access activities Further.
Preparation of SPD Cabling Calo comissioning meeting – 19th July 2006 – CERN I.Status of cables II.Cable reels III.Labelling IV.Cabling inside a VFE box.
CALICE ECAL/AHCAL Electronics 5-6 July DESY L.Caponetto, H.Mathez 1 Developments and Planning towards 1 m 3 Technological DHCAL Prototype Didier.
Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005.
14 February 2006A.Ciocio - ID Week1 SCT Services Procurement & Installation Type IV PP3 Type II-III and PP1 Fibres Heaters DCS Testing MTF Workpackage.
25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.
ID week - 26 September 2006 A. Ciocio1 SCT Services Installation SCT Cables Web page
ATLAS Upgrade ID Barrel: Services around ‘outer cylinder’ TJF updated According to the drawing ‘Preparation outer cylinder volume reservation’
Electrical and Optical Cables Installation at P5 What When How H. Breuker
Pippa Wells25 October Procurement and manpower for service installation Services readiness dates Planning for type ii/iii Fibre installation dates.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia DAQ, DCS, Power Supply and Cables Review CERN, March Electrical PP1 Basic features Electrical.
8 June 2006A.Ciocio - SCTSG1 SCT Services Installation Type IV PP3 Type II-III and PP1 Testing & Installation Plan Workpackage
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
Abe Seiden December 2003 SCT Week S USA SCT Barrel Module Assembly SCT Week CERN December 2003 Presented by Abe Seiden U.C. Santa Cruz.
ATLAS SCT End-Cap C Integration 1.Introduction: to the SCT within ATLAS 2.End-Cap C Reception at CERN 3.Final Assembly 4.Integration with the TRT 5.Combined.
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
Straw Working Group Status assembly at CERN Plans 10/2/14Straw WG.
TE/MPE/EE J. Mourao T/MPE/EE 23 December 2012 LHC Machine Redundant Power supply (DQLPUR) & interface Module (DQLIM) assembling during LS1.
14 December 2005A.Ciocio - SCTSG1 Services and Patchpanels Installation Type IV installation Connector in situ work Status of PP3 Type II/III Testing.
E.Guschin (INR,Moscow) 17 July 2007 CALO commissioning group meeting CERN Status of PS/SPD LED system.
Status of NA62 straw electronics Webs Covers Services Readout.
IDE DCS development overview Ewa Stanecka, ID Week, CERN
Chiho Wang Duke University 1 TRT Barrel integration Status / Schedule Chiho Wang.
November 04 Jason Tarrant CCLRC1 SCT EC Interconnects l Progress of SCT EC Interconnects »Services (Required for Disc Insertion 2004 / Integration 2005)
7 March 2006A.Ciocio - SCTSG1 SCT Services and Patch Panels Type IV PP3 Type II-III and PP1 Fibres Heaters DCS Testing Workpackage
9 May 2006A.Ciocio - SCTSG1 SCT Services Installation Type IV PP3 Type II-III and PP1 Fibre Cables DCS Testing & Installation Plan Workpackage
13 September 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Delivery Installation Connector work Testing Summary.
SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:
MPE Review – June 2, 2015 A. Erokhin, TE-MPE-EE Upgrade, IST and Powering tests of the Upgrade, IST and Powering tests of the 600A Energy Extraction Systems.
M. Gilchriese Pixel Update October 3, M. Gilchriese 2 Outline Barrel status and repair strategy Revised ATLAS installation schedule Finishing pixel.
25 October 2005A. Ciocio - SCTSG1 Type II/III Cables and PP1 Status & Plan.
8 June 2006A.Ciocio - SCTSG1 Status of Type IV Cables Cables production –resumed in February after 3 months stop –See ID week February ‘06 Delivery of.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities.
31 January 2006A.Ciocio - SCTSG1 Type ii-iii and PP1 Production Timescale for installation Plan PP1and Testing.
9/12/2003Ivan Hruska1 First box prototype –Box design in July ‘03 –Box produced during August ’03 Tested last week in few fingers Small changes necessary.
Executive Committee, Toronto August 3, 2005 TRT Barrel WBS 1.2/3.2 Harold Ogren Indiana University.
August 04 Jason Tarrant CCLRC1 SCE EC Design & Manufacture l Progress of SCT EC »Support Structure (Required for Disc Assembly 2004) »Services (Required.
March 12 th 2013 Muon LS1 operation meeting1 Muon LS1 Status Outline Recap of last week P1 weekly schedule Muon related activities Open issues and discussions.
Chiho Wang ATLAS TRT Duke University CERN, Sep Barrel integration status.
Steinar Stapnes, LHCC June The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels uWhole ID sits inside bore.
1 PST Heater Panel Design The PST heater panels are internally redundant resistive circuits printed onto a Kapton sheet with an aluminum backing. They.
ATLAS 1 Beam Pipe Support SCT TRT Side CSide A Services and Beampipe Support Frame Services and Beampipe Support Frame Pixel Detector Composite support.
Service channels between Tracker and PP1
Service channels between Tracker and PP1
Optoelectronics internal report, 17 August 2007
Services – First Considerations Sigi Wenig / Nicolas Massol ATLAS Tracker Upgrade Workshop Valencia December 2007 Existing services (in cryostat.
G. Carboni for the Muon Group
Nearly the end of a long story...
DT Infrastructure: LV, HV, Gas
Radiation Laboratory Meeting
Installation plans from mid 2005
CNGS horn / reflector in 2005: The story of the glass ring insulator
Presentation transcript:

18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page Workpackage

18 July 2006A.Ciocio -SCTSG2 Type II/III cables – Installation 3594 cables installed and tested All 2112 barrel cables (sectors 1,3,7,9,11,15) All endcap cables for sectors 1,3,7,9 494 (sector 11&15) will be installed in August Yield: <1% cables with defects or to replace - Mechanical defects - Damage during installation or preparation - Failed electrical test (most probably due to splice damage) after installation (replaced) Additional inspection of damage and final verification that individual wires are strongly fixed inside the JST and FCT when they will be disconnected from dPP1.

18 July 2006A.Ciocio -SCTSG3 Type II-III and Fibre Cables by Sector S5 S3S7 S1S9 S15S11 S13 US PP3 racks USA PP3 racks 384 Barrel 494 EC 384 Barrel 494 EC 336 Barrel 247 EC 336 Barrel 247 EC 336 Barrel 247 EC 336 Barrel 247 EC Level 7 Level 6 Level 2 Level 8 Level 5 & 2 Level 1 & 2 18 Fibre cables (EC) 27 Fibre cables (9 EC, 18 Barrel) 18 Fibre cables (Barrel) 27 Fibre cables (9 EC, 18 Barrel) Fibre Cables to USA15

18 July 2006A.Ciocio -SCTSG4 SCT Cables by Sectors Sequence Sector 5 (top) and Sector 13 (bottom) –heater cables, and DCS cables (completed) Sector 9 - Installation completed on May 1 –878 SCT cables (384 Barrel, 494 EC) –18 Fibre cables (EC) Sector 3 - Installation started on May 2 – completed on June 4 –583 SCT cables (336 Barrel, 247 EC) –27 Fibre cables (9 EC,18 Barrel) Sector 1 - started in parallel mid May – completed on June 13 –878 SCT cables (384 Barrel, 494 EC) –18 Fibre cables (Barrel) Sector 7 – started on June 7 – completed on June 29 –583 SCT cables (336 Barrel, 247 EC) –27 Fibre cables (9 EC,18 Barrel) Sectors 11, 15 – 336X2 barrel cables installed – July 18 – SCT cables (336 Barrel, 247 EC) – Fibre cables (9 EC,18 Barrel) Installation sequence in a sector is: –Tubes, fibres, heater cables, SCT cables, (Muon cables), –TRT cables, pixel cables

18 July 2006A.Ciocio -SCTSG5 Type IV Cables - Installation All type IV cables (2044+spares) going from PP3 racks in the ATLAS cavern to PS racks in US15 installed (+ connectors) Type IV going to USA15 almost completed –64 double harnesses to install (128 cables) –6 more days Testing in racks after installation and first cut ongoing Completed installation is expected in one week

18 July 2006A.Ciocio -SCTSG6 Type IV – Connectors in situ All connectors (2000+) in US15 completed on March 10 (a few were left but they are done now) Many racks are tested before and after plug into PS (Petr with Prague team) Very good yield but some rework was necessary One rack (the very first one made more than an year ago) needs cables rerouting (cables were cut too long by previous company) 2+1 CPE techs returned in mid-April for a few weeks –US side was reworked –Started 2 USA racks but left again because more USA15 racks were needed to be completed for the full team to operate efficiently A team of 6 techs (1 supervisor) will return this week Estimated completion of connectors in USA racks: End of August

18 July 2006A.Ciocio -SCTSG7 PP3 Assembly and Installation completed Checks for shorted units and problems in progress Plug-in of type IV cables Problems found after installation in the last few months –Insulation –Sliding units in subracks –Failed units (2+) PP3 units installed in racks Channel Spare units in racks PP3 - failed (back for inspection and rework)10 Subracks (30 PP3 units in a shell)137 Subracks - special (shells of 30 partially filled with PP3 and the rest with empty boxes) 9 Subracks – mini (shells of 5 units for spares PP3 in a full rack) 4 Extra PP3 units Shells Mini shells Empty boxes

18 July 2006A.Ciocio -SCTSG8 Installation & Testing Activities Type IV Acceptance test (done) Test in rack after installation Test of cut cables after connector in situ work Plug-in cables into PS crates Test with feedtrough Type II-III Preparation ----ALL DONE Acceptance test (partial) Visual inspection Folding the shield and cut it the right amount, fix it Organize boxes with right cables to send for installation Type II-III Installation Mount dPPB1 and dPPF1 (Barrel) Squeezing the cables to fit between pin and clamp holder Plug-in of the delicate JST/FCI connectors to dPPB1 Placing the clamp (now), placing the clip (later) -- DONE (ENDCAP) crimp group of drain wires in a ferrule and catch the ferrule with the grub screws into clamp’s holes Plug in the dPPF1 Type II-III Testing Type II-III replacing bad cables PP3 Burn-in of units -- DONE Assembly into subracks -- DONE Installation into racks of subracks -- DONE Plug-in the cables to PP3 Test of whole chain

18 July 2006A.Ciocio -SCTSG9 Schedule Type II-III barrel installation completed today Endcap cables of sector 11&15 to install after the Solenoid Field Mapping (July 19- Aug 14) Type II-III installationmid-July (Barrel) end of August (last Endcap cables – 494) Type IV installation24 July Connector in situ+testingend of August PS cratesend-July (US side) – September (USA side) PP3 assembly, installation end-July All cables plugged into PP3mid-July- begin August (type IV) end-August (type II-III) Test of whole chainnow – mid September

18 July 2006A.Ciocio -SCTSG10 Plan

18 July 2006A.Ciocio -SCTSG11 PS priorities

18 July 2006A.Ciocio -SCTSG12 Issues PP3 –We find problems as we plug in and test –Type IV all connected by end of July –Hopefully OK when Type III are connected Tester –Different flavor that work with different configuration of cable chain –Multiple laptops failure (~ok now) –Need help at CERN of experts (Ljubljana) when testing whole chain Defective dPPF1 –Some faulty cables were actually due to a bad channel on dPP1 (3 endcap 3 barrel) –Still missing some dPPF1 Connector in situ –Delay will move installation of PS later Need more HELP with testing until end of August (mid September)