PR Basketball / Volleyball Practice Facility General Contractor Pre-qualification
Agenda Introductory Remarks Overview Construction Goals Submittal Requirements Questions / Answers
Welcome
Project Team Client – UCB Athletics – Tom McGrath, Sr. Assoc. Athletic Director – Tom McGann, Dir. Game Mgmt & Operations UCB Planner – Tom Goodhew UCB Project Mgr – Katherine Dunklau Architect – Sink Combs Dethlefs – Andy Barnard, AIA – Steve King, AIA
Overview - Project Description Addition to the north side of the Coors Event Center Approx. 36,000 sf, two practice courts Est. Construction Cost - $8M Est. Construction Period – March 2010 to March 2011
Project Location
Basketball / Volleyball Court
Construction Goals Bidding Period – Approx. February 2010 Begin Construction – March 2010 Substantial Completion – March 2011
Construction Issues Asbestos abatement approx. 100 lf tar impregnated black felt on 14” dia. HPS line Temporary steam line Site lay down area Utility relocations Fire sprinkler work within CEC Excavation – approx.15’ cut
Construction Issues (cont.) Working adjacent to occupied building Campus – faculty, staff, and students Parking
Submittal Requirements Be sure to meet the minimum requirements Please provide information in the order outlined with TABS Provide relevant information Include forms – Affidavit – MWBE
Submittal Requirements (cont.) Do not provide too much information KEEP IT SIMPLE
Question and Answers Submit in writing by Formal response will be issued by addendum Thank you for coming