1 Fulvio TESSAROTTO the new RICH beam pipe the new RICH beam pipe - pipe production, gluing and tests - measurement and removal of the old pipe - fixation.

Slides:



Advertisements
Similar presentations
Liquid H 2 Absorber Production Contents (1)MICE Absorber Status (2)MICE Absorber Modification (3)Plan/Schedule (4)Summary MICE CM-23 in HARBIN Shigeru.
Advertisements

TPC meeting, NBI, 2-3 September 2002Børge Svane Nielsen, NBI1 Status of laser system TPC meeting, Copenhagen, 2-3 September 2002 Børge Svane Nielsen, Jørn.
Richard Soluk – University of Alberta. The LHCb VELO Region R. Soluk --- University of Alberta --- MoEDAL Collaboration Meeting --- CERN June
31/03/11FV 1 CEDAR from flammable gas safety point of view.
2/9/2004DC status - BVR1 1.Mechanics 2.Foil 3.Frame and Print Anode Inner cathode Hood 4.Pressure control + He bag + target 5.Electronic 6.Schedule Status.
1 Fulvio TESSAROTTO Update on the thin RICH beam pipe project - tests on prototypes - pipe production by Lamina - gluing exercises - time schedule - conclusions.
V. Carassiti - Princeton (USA) 9-13/01/ BABAR IFR UPGRADE DETECTOR ASSEMBLING AND MOUNTING.
Christine KOURKOUMELIS University of Athens ATLAS Muon Chamber construction in Greece and alignment studies for H  ZZ  4μ decay Como, 8/10/03.
The LHCb Inner Tracker LHCb: is a single-arm forward spectrometer dedicated to B-physics acceptance: (250)mrad: The Outer Tracker: covers the large.
Thin ladder development Status of ladder development for the thin ladderfest.
Don Lynch 9/15/05 HBD Safety Review 1 Mechanical Design And Installation Hadron Blind Detector (HBD) Don Lynch.
SPACE FRAME Interface between the LGT and the IST 21/06/2011 Marco Ciapetti.
Ans Pardons 30/11/2006CNGS Reflector Technical Review CNGS reflector: Status Work remains to be done… 30/10 Introduction Drain connection Event analysis.
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
18 November 2010 Immanuel Gfall (HEPHY Vienna) SVD IR Mechanics 7 th B2GM.
1 Fulvio TESSAROTTO Update on the thin RICH beam pipe project - prototypes validation and pipe production - microflanges and fixation system - the intervention.
Equipment and Tool Institute June 18, Challenger Body Structure Diane Coopmans, Body Structures Engineering.
Dec. 4, 2001 CERN-1 Hans de Vries VELO Mechanics  RF/vacuum foil  Rectangular bellow  Wake field suppressors  Cabling Summary & Outlook VELO mechanical.
1 Mechanics news from KEK S.Tanaka (KEK) SVD/PXD meeting SVD parallel session.
26 April 2013 Immanuel Gfall (HEPHY Vienna) Belle II SVD Overview.
Preparation of wall position Alignment of A and C side in closed position Creation of reference system Translation of reference system to open position.
C ONCENTRIC TUBE H EAT EXCHANGER TEST SETUP AT C RYOLAB CO2 FOR CMS T RACKER WEEK MEETING. Theodoros Katopodis PH-CMX.
1 Advanced Endplate - mechanics: Development of a Low-Material TPC Endplate for ILD Dan Peterson Laboratory for Elementary-Particle Physics, Cornell University.
Update on Alignment kit and Stave 250 frame and thoughts for Stave 130 M.Gibson (RAL) 2/5/13 1 Status of the frame for stave 250 Status of infrastructure.
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
Jochen Ebert, Uni Karlsruhe1 Powering via cooling pipes very first results.
MWPC sandwich panels C.Forti INFN-LNF / LHCb-MUON EDR CERN 16 th April sandwich panels typologies of cathodes the mould the production procedure.
News on mechanics Photon veto F. Raffaelli INFN – Sezione di Pisa CERN, January r 02 th, Status of tender Anti Status of the supporting.
SD-HCAL technological prototype – Chamber and cassette production Nick Lumb Lyon, 3 February 2011.
THE VACUUM BOX FOR COMPASS CRYOSTAT MUNICH 23/10/2007 G. GIRAUDO I.N.F.N. TORINO 1.MECHANICS – OVERWIEV 2.WINDOWS 3.INTEGRATION WITH HODOSCOPE.
TRT active gas leak repairing F. Perez, C. Degeorge, S. Katunin, I. Zhukov, V. Myalkovskiy, S. Konovalov, A. Romaniouk, H. Danielsson, A. Catinaccio, K.
9 September 2004The Straw Tube Chamber1 The CDC Curtis A. Meyer Carnegie Mellon University Physics Requirements and Specifications Prototype Construction.
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
19 January 2006VELO installationEddy Jans 0 VELO-installation meeting CERN, January 17, 2006 preparation IP8-area SX8 moving SX8 -> IP8.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
Lav meeting F. Raffaelli INFN – Sezione di Pisa C. Capoccia LNF, A. Cecchetti INFN – Sezione di Frascati CERN, Dec13 th, Feet friction studies. -Installation.
Integration with LDC & Push-pull impact on LumiCal Wojciech Wierba Institute of Nuclear Physics PAN Cracow, Poland FCAL Workshop, LAL Orsay,
18 June 20031Integration Review B. Schmidt Outline: Overview of the support structures Requirements –Some details on electronics, cabling and piping Constraints.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
IPN Lyon ILD integration April 2015 Jean-Christophe Ianigro & Imad Laktineh - IPN Lyon -
LHCb MUON - ADDITIONNAL SHIELD BEHIND M5 – UNIT AREA Dimensions of 1 iron brick  100 x 100 x 200 mm3 1 ROW of 1200 mm length  12 iron blocks.
1 2S Module meeting, 24 September 2012 S tudies on module support inserts Refers to work by Riikka Häsä, Helsinki Institute of Physics, summer student.
MQXFB design, assembly plans & tooling at CERN J.C Perez On behalf of MQXF collaboration team MQXF Workshop on Structure, Alignment and Electrical QA.
1 Fulvio TESSAROTTO GDD meeting, CERN, 01/10/2008 Trieste THGEM news New THGEM test in the COMPASS hall New THGEM test in the COMPASS hall Preparation.
Chamber mechanics Chamber mechanics Production in China Peking University Group – 20 Aug
 1) Introduction  2) GEANT simulations  3) NEW DESIGN : Technology and Assembly  4) Conclusions Reported by G.Feofilov, CBM meetings, Dubna.
LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness.
Vacuum conditions in PANDA pbar-line Alexander Gruber, SMI, Vienna, Austria.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
24 September 2012 Immanuel Gfall (HEPHY Vienna) Annekathrin Frankenberger (HEPHY Vienna) SVD Status of Mechanics PXD-SVD Meeting Göttingen.
NA 62 – straw detector Content Detector Specifications Chamber design Straw design and specifications Calculations and measurements Prototyping Plans Straw.
Thousand Kernel Weight For small seeds, 1000 kernels are weighed and a parameter known as the thousand-kernel weight (TKW) is determined. An electronic.
Four OTRs for ATF2 OTR History Current OTR setup New OTR design.
Planning for Proto-DUNE PD Installation and Cabling at CERN
Ferrara MECHANICAL SUPPORT for forward tracking detectors Federico Evangelisti INFN - Ferrara GSI – 2-6 march 2009.
Stress and cool-down analysis of the cryomodule
T980 STATUS AND CHANGES FOR
Ti/SS transitions A.Basti INFN-PISA*
NA62 LAV Anti1 REMOVAL & TESTS
VELO-installation meeting CERN, January 17, 2006
New field cage LP2 Ole Bach, Bernd Beyer, Volker Prahl
Preliminary Y-chamber specifications – First draft
Backward Calorimetry For SuperB
Ongoing and to do work M.Lenti.
Tracker Outer Barrel COOLING Antti Onnela, CERN.
LumiCal mechanical design, integration with LDC and laser alignment
G. Carboni for the Muon Group
XFEL Collimation and Beam Switchyard Vacuum Issues
Final Design CGEM Workshop HIEP, 14/03/2017 M. Melchiorri - INFN FE.
Single Detector Design
Presentation transcript:

1 Fulvio TESSAROTTO the new RICH beam pipe the new RICH beam pipe - pipe production, gluing and tests - measurement and removal of the old pipe - fixation system - installation of the new pipe - characteristics of the new pipe COMPASS TB meeting, CERN, 12/04/2012 Fulvio Tessarotto

2 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 02/02/2012 Slide from the last TB: Issue status Removal of presently used pipe Extremely difficult behind the mirrors Material for the thin pipe 5 layer aluminized Mylar, 0.6 ‰ X Geometry 2 pipes 100 mm diam., 1570 mm long Gas He, few l/h, 15 mbar overpressure End caps alum. Mylar glued on Al microflanges Fixation system Thin stainless steel wire ropes Extremely difficult behind the mirror wall: still to be defined

3 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012 tubes, microflanges, gluing tests weight = 15 g

4 Fulvio TESSAROTTO Simulations for the new pipe max = 0.1 Mpa, yield strength = 85 MPa COMPASS TB meeting, CERN, 12/04/2012

5 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012 half-pipe He leak tests Measured leak, including connections: 0.5 ml/h

6 Fulvio TESSAROTTO “Safety is the first of our priorities” - RICH is a “confined space”: access is allowed to authorized persons only - Authorization requires a confined space formation course and a medical certification - New procedure: CERN asks for medical certification to be provided by the Institutes. - Inside the RICH we needed a scaffolding: the old scaffolding is not complying to the rules. - The new scaffolding can only be mounted by authorized people. - The authorisation requires …. 1) a general CERN confined space course was organized and people sent to attend it 2) a medical check and certification protocol was defined, agreed upon and applied in Trieste 3) the activity inside the RICH was defined in detail and an access protocol was produced 4) the supervisor was changed 5) special exception to allow access for radioprotection experts, scaffolding responsible, etc. 6) a scaffolding was borrowed / built and certified by the responsible in Clean Area 7) authorization to mount the scaffolding by ourselves was obtained 8) authorization to use the scaffolding (after check) with a use protocol was provided 9) … 10) … All involved persons have been extremely collaborative! Firenze, 22/03/2012

7 Fulvio TESSAROTTO RICH opening, old pipe removal 1) Radiation level: < 0.2 μSv/h 2) Surveying of the old pipe 3) Large scaffolding installation 4) Small scaffolding installation 5) Removal of the old pipe 4) Mirrors surveying COMPASS TB meeting, CERN, 12/04/2012

8 Fulvio TESSAROTTO After the removal of the old pipe - We confirmed it is not possible to access the area downstream of the mirrors - We decided to change the fixation system and the gas pipes to reduce the material 1) We prepared two beam pipes of 1.6 m and tested them: measured leak rate: 0.5 ml/h 2) We decided to produce a unique pipe by gluing two halves on 1.6 m 3) The vertical middle gluing needed a special microflange and a system for vertical operation 4) We continued to put pressure on Lamina, despite the denials, to try producing a 3.2 m tube 5) One 3.5 m long tube arrived in Trieste just in time. 6) The microflanges and the system for gluing were ready: the long pipe was glued and 7) Tested together with the “Tygon” pipes and plastic strips for gas connection: 0.6 ml/h 8) Both long pipes (single piece and two-halves shipped to CERN) 9) We checked that two suspensions are enough (pipe rigidity better than expected)  Two fixation points are enough COMPASS TB meeting, CERN, 12/04/2012

9 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012 gluing end-caps on the single pipe

10 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012 Careful packaging

11 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012 And transport

12 Fulvio TESSAROTTO Preparation for the new pipe 10) Putting in place the top fixation systems was challenging but successful 11) Dummy flanges positioned using a laser system 12) Pipe introduced in the RICH and put in place 13) Surveying to check the position found several millimeter offsets 14) Position partially corrected and fixation system tensioned at 2 kg COMPASS TB meeting, CERN, 12/04/2012

13 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012 Pre-alignment of pipe holders

14 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012 the new pipe inside the RICH

15 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012 The polycarbonate suspension ring

16 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012

17 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012 New fixation system and gas pipes

18 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012 Pipe specifications Inner diameter: mm ( ) Thickness: 140 μm Length: 3140 mm Material: Mylar (PET) + 1 μm Al Single pipe, front and rear window: same material: 140 μm Mylar + 1 μm Al Microflanges: “F” shape Al, 0.5 mm thick Upstream microflange acts as holder, Downstream holder at 80 cm from edge, Policarbonate 8mm x 8mm + 2 nylon screws Fixation via stainless steel microwire ropes: 4 ropes (90 degrees) per holder, 1 x 7 wires 90 μm diam. (limit = 9 kg) + 10 μm nylon coating, tensioning: 2 kg, thermal expansion +- 2 mm, equiv. 1 kg Adjustement and tensioning microsystems placed out of the acceptance

19 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012 Upstream fixation and gas connections Total amount of material in the acceptance: Fe (8 m microwire ropes): 5 g Al ( 2 m pipe + microfl.): 60 g Mylar: 180 g Polycarbonate (fixation): 20 g Epoxy: 6 g Cu: 0.5 g Tygon: 5 g Nylon: 4 g Old gas pipes: 6x4 mm stainless steel tubes, new pipes: 6x5 mm Al pipes (10 times less X 0 )

20 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012 Measurement and adjustment

21 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012 position regulation and surveying

22 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012 Material budget actual pipe material budget: (0.15 mm / 17.6 mm)8.523 ‰ X 0 goal for the material budget of the new pipe:10% actual =0.852 ‰ X 0 5 layers of 27 μm thick Mylar : (0.135 mm / 287 mm) ‰ X 0 5 layers of 200 nm thick Al coating: (1.0 μm / 89 mm)0.011 ‰ X 0 4 layers of 6 μm thick Mylar glue: (24 μm / 280 mm) ‰ X total material budget for orthogonal crossing:0.567 ‰ X 0 total material budget for parallel crossing (r < 42 mm):2.26 ‰ X 0 parallel crossing (42 mm < r < 49 mm):1.9 % X 0 6 mrad particle crossing the pipe (old value = 1.4 X 0 )9 % X 0 The contribution from end caps, fixation rings, gas connections has been minimized

23 Fulvio TESSAROTTO COMPASS TB meeting, CERN, 02/02/2012 time schedule RICH opening February 21 Scaffolding mountedFebruary 24 Old pipe measurement March 6 Removal of the old pipeMarch 7 Mirror measurementMarch 16 Installation of the new pipe April 5 He leak testApril 17 Scaffolding dismountingApril 18 RICH closingApril 19 or April 25