LATLAT CU Beam Test 3rd May 2006 1 GLAST Program CU Beam Test CU Integration Francesco Nicola

Slides:



Advertisements
Similar presentations
MODULE TRANSPORT CLIC Module Working Group 27 September 2010 Keith Kershaw CERN EN-HE.
Advertisements

Vibration Sensors for Cooling Towers Challenges Cooling towers offer the vibration analyst many challenges in sensor selection, mounting and environmental.
Cable Restraint Proposal Current design does not work. Objective: Find an alternate way of securing the LAT cables using as much of the existing design.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test One and Two Tower Integration Readiness Review.
IFCT Plan for Next 3 Months Larry Wai June 26, 2003.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test Two Tower Integration Readiness Review Safety Overview.
GLAST LAT ProjectNovember 04, 2005 Phase 0 TRR 1 GLAST Large Area Telescope: Integration and Test -Electrical Test- Phase 0 TRR Key Requirements Documents.
July GLAST Project Installation Review LATLAT 1 Tracker Tower Installation Review Peter Amnuaypayoat
GLAST LAT Project I&T Meeting – Jan 29,2004 E. Gawehn 1 GLAST Large Area Telescope: MGSE Status Report Eric Gawehn SU-SLAC I&T MGSE Engineer
GLAST LAT ProjectApril 27, 2006: LAT Pre-Ship Review 1 Presentation 8 of 12 Integration and Test GLAST Large Area Telescope: Pre-Shipment Review Integration.
GLAST LAT ProjectCDR/CD-3 Review May 12-16, 2003 Document: LAT-PR-01967Section 15 Manufacturing & Processes 1 GLAST Large Area Telescope Manufacturing.
The CU Beam Test at CERN Status Report and highlights from workshop II Luca Latronico LAT C&A Meeting May
GLAST I&T January T Borden 1 Tracker EM Mechanical Mock-up T Borden I&T Tracker Mock-up.
GLAST LAT ProjectSLAC Pre - Baseline Review, April 16, 2002 ` 1 GLAST Large Area Telescope: I&T Overview WBS: Elliott D. Bloom Stanford Linear Accelerator.
GLAST LAT ProjectJune Cost/Schedule Status Meeting 07/23/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to June Cost/Schedule.
1 GLAST LAT Arrival at Spectrum Assuming That the LAT Transport Container Arrives on Flatbed Truck Question: Can Transport Cover Support Crane Lift With.
Pre-alignment solutions applied to girders 1/19 Sylvain GRIFFET, 06/07/2010.
Automated HIC assembly A. Di Mauro ITS-MFT mini-week
High Bay Operations1 GLAST LAT ProjectMarch 2005 LAT Engineering Meeting 14 March March 2005 LAT High Bay Operations Supporting Test Events LAT.
GLAST LAT ProjectIntegration and Test CDR Peer Review, March 28, 2003 Document: LAT-PR Section 7 - Page 1 GLAST Large Area Telescope: I & T Peer.
GLAST LAT Project ACD CDR Jan 7-8, Section 7 Mechanical Ground Support Equipment GLAST Large Area Telescope: AntiCoincidence Detector (ACD) Mechanical.
GLAST Large Area Telescope:
LATLAT Beam Test Workshop 20th March GLAST Program Beam Test Workshop CU Outer Shipping Container Michele Pinchera
High Bay Operations1 GLAST LAT ProjectMarch 2005 LAT Engineering Meeting 16 March 2005 LAT High Bay Operations Supporting Non-Test Events LAT Engineering.
GLAST LAT ProjectI&T PDR Presentation (IFCT Dept.) – January 9, 2002 Larry Wai Integration and Test Organization Chart I&T Manager Elliott Bloom WBS
M. Gilchriese Module Assembly and Attachment at LBNL M. Gilchriese for F. Goozen April 2000.
January 25, 2005GRETINA 2004 Review1 GRETINA 2004 Annual Review Steve Virostek Lawrence Berkeley National Lab Mechanical System.
GLAST LAT ProjectCDR/CD3 Review May 12-16, 2003 Document: LAT-PR Section 15 Manufacturing Process 1 GLAST Large Area Telescope Manufacturing Process.
GLAST LAT ProjectFace to Face Managers Meeting 04/14/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Face to Face Managers.
GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 1 Integration and Test Presentation 11 of 12 GLAST Large Area Telescope: LAT Pre-Shipment Review.
NIKHEF B-field monitors Paul Balm November 11 th, 1999.
GLAST LAT ProjectMarch 08, 2004 Page 1 ACD Installation, Post LAT CDR Response to GLAST LAT CDR RFA Number 13: MGSE Detailed Dimension Study [for ACD Installation]
GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager
Sling Load Capacity and Sling Angles
GLAST LAT Project Page 1 ACD Installation, Post LAT CDR Response to GLAST LAT CDR RFA Number 13: MGSE Detailed Dimension Study [for ACD Installation] –A)
LAT Environmental Test PDR1 GLAST LAT Project3-4 May 2005 LAT Environmental Test Planning and Design Review 3-4 May 2005 Operations and Logistics LAT Environmental.
1 03/21/2006 GLAST CU Beam Test Workshop Scanning Table.
GLAST LAT Project Integration and Test IFCT Peer Review 1 GLAST Large Area Telescope: I&T Integration Readiness Review Integration, Facility, Configuration.
GLAST LAT ProjectCAL Peer Design Review, Mar 17-18, 2003 P. Dizon Naval Research Lab Washington DC GLAST Large Area Telescope Calorimeter Subsystem Gamma-ray.
1 InnoSys Quick Connect End Effecter Service and Maintenance Procedures Shreveport Assembly 14 MAY, 2008.
MH...CH LECT-021 SYSTEMS CONCEPT Adopting a materials handling systems from overall optimization point of view. Adopting a materials handling systems.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct 2, 2001 Darren Marsh1 I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist.
1 MICE CM27 Engineering integration Andy Nichols, STFC 9 th July, 2010.
DON LYNCH NOVEMBER 6, AGENDA November 4, BABAR Magnet Update Global Design Concept – Update Outer HCal Structural Analysis (2 nd pass) sPHENIX.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 5.3 Fab & Assy Plans 1 GLAST Large Area Telescope:
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/04 LAT I&T MGSE Page 1 of 11 GLAST Large Area Telescope: I&T Integration Kickoff Meeting MGSE March.
GLAST LAT Project Test Beam Meeting, Apr 18, 2006 E. do Couto e Silva 1/2 Beam Test Hardware Delivery Status Eduardo do Couto e Silva February 18, 2006.
SPS movable table Joanna Swieszek, Kurt Artoos (EN-MME) 14/04/2016.
HGC Cassettes Jim Freeman September 17, Director's Review -- Calorimetry – HGC Cassettes Jim Freeman, 2015 Sept 17.
PRELIMINARY VERSION Mechanical integration in the ESS Accelerator tunnel HENRY PRZYBILSKI.
6-Mar-2016 Dan Wenman | FC Installation 1 APA installation and integration at CERN Shipment of APAs APA handling Acceptance testing Tools needed.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
WORK STUDY HOW THE TOTAL TIME OF A JOB IS MADE UP (IE411)
Tracker Subsystem GLAST LAT Project 1 ANNEX 1 to NCR/FM/INFN/PI/372 STATIC TEST TORQUE LOSS OUT OF SPEC’S ON BOTTOM TRAY S/N 005 Andrea Tenze
1 Target Station Design Dan Wilcox February 2012.
SOAR AZIMUTH DRIVE The SOAR azimuth drive systems has 4 motor+gearbox units, two pairs with backlash tuning. (600 kg box) Each subsystem is bolted to.
LARP Phase II Secondary Collimator RC1
Mechanical Integration
Peer Review Agenda (Suggested).
GLAST Large Area Telescope:
GLAST Large Area Telescope: I&T Integration Kickoff Meeting
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Mechanical System P09045: Membrane Characterization Test Stand
Integration and Test Organization Chart
LAT Environmental Test Planning and Design Review
Introduction and Overview
GLAST Large Area Telescope:
Tracker to Tracker Clearance Reduction Contributors
Presentation transcript:

LATLAT CU Beam Test 3rd May GLAST Program CU Beam Test CU Integration Francesco Nicola

LATLAT CU Beam Test 3rd May Overview  Highlights of the INFN Integration Procedure: Requirements Towers Integration CALs Integration  INFN CAL Integration MGSE: Main feature Comparison with SLAC philosophy Proof Test

LATLAT CU Beam Test 3rd May Highlights of INFN Integration Procedure LAT-PS Requirements: –Critical components Part of the components of the CU are FLIGHT HARDWARE CAL: Cesium iodide crystals of calorimeter have an allowable relative humidity range of 35 to 50%. (Bagging and N 2 flow at all times) –Environmental All operations will be performed in Class 100,000 Clean Room Electrostatic Discharge Control Per NASA-STD –Quality Assurance Assembly and Inspection Data Sheet QC inspection at the completion of each assembly sequence Quality assurance will maintain surveillance of the operations required by this procedure

LATLAT CU Beam Test 3rd May Towers Integration: Performed according to LAT-PS Tracker Integration Procedure Towers are integrated from above the 1x4 Grid in two adjacent bays towards one of the sides (Bays 2-3) TKR Tower to Grid interface Hardware (Studs and Cones) very well known by the INFN Integration Team (18 TKR Towers!!!) 2 3 Highlights of INFN Integration Procedure LAT-PS-08132

LATLAT CU Beam Test 3rd May CAL Integration: Different approach from that of LAT-PS Calorimeter Integration & Processing Procedure : –CAL’s are integrated from underneath the 1x4 Grid instead of lowered into respective Bays. Reasons: »INFN Clean Room lacks necessary ceiling clearance »No overhead travelling crane –New MGSE and Procedure developed for this purpose Challenges: »Replicate same restraints and degrees of freedom during the entire operation »Use consistent safety precautions for the hardware and personnel »Adapt SLAC philosophy to INFN needs or absence of needs (e.g. CAL inversion) »Optimize use of available space (INFN Clean Room is not devoted entirely to GLAST!) »Maximize value of training performed at SLAC Highlights of INFN Integration Procedure LAT-PS-08132

LATLAT CU Beam Test 3rd May INFN CAL Integration MGSE Main Features: X direction Table Y direction Table Vertical Drive Unit (Z direction) Rotating Support Plates (θ angle) Thrust Ball Bearing, Sphered Housing Washer (φ & ψ angles - small) Torque Limiter Z Y X θ ψ φ

LATLAT CU Beam Test 3rd May INFN CAL Integration MGSE Comparison with SLAC philosophy: SLACINFN Degrees of Freedom Allowed 6 – provided by overhead crane and suspension 6 – provided by the dedicated MGSE (see previous slide) Alignment Provided by SLAC Alignment Tool and Rods Provided by SLAC Alignment Tool and Rods (shortened) Mechanical Safety Feature Proper travel of CAL monitored by Load Cell Any overload is stopped by the Torque Limiter Electrical Safety Feature Voltmeter connected between CAL and Grid Different approach, same philosophy!!

LATLAT CU Beam Test 3rd May INFN CAL Integration MGSE Putting it all together:

LATLAT CU Beam Test 3rd May Proof Test Performed according to: NASA-STD Standard for Lifting Devices and Equipment NASA-STD-5005AGround Support Equipment ASME B30.1 Jacks Load Applied: Tower Mass Simulator123 kg+ LAT-DS kg= ___________________________________________ Total132 kg Actual load(CAL+TEM/TPS)~95 kg

LATLAT CU Beam Test 3rd May Proof Test Proof Load applied in the worst position for the structure (midspan of Y-table) No appreciable distorsion or failure Proof Test Successful!

LATLAT CU Beam Test 3rd May Conclusion Ready for Integration – In any case we will perform a full dress reharsal of the procedure using non-flight material But if anything goes wrong…. …we are outta here!! Anywhere fun darn!!