EARNED VALUE MANAGEMENT (EVM)

Slides:



Advertisements
Similar presentations
Connoizor Enabling Performance for Businesses through Software Website: Contact:
Advertisements

Presenter: Sohel Akhter, PMP, CCNA,ISMS
©2003 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third party, or used.
Budget Management. 57 Budget Management Budget Development Good scheduling skills and abilities Understanding of the project scope Well developed WBS.
 Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration.
Copyright , Dennis J. Frailey CSE7315 – Software Project Management CSE7315 M30 - Version 9.01 SMU CSE 7315 Planning and Managing a Software Project.
Monitoring and Control Earned Value Management (EVM)
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
Microsoft Project 2002 Sessions 5-6. Entering Tasks During this first session we will enter a set of tasks that comprise building a shed – data sheet.
Chapter 10: Monitoring and Controlling Change
Earned Value Project Management: a powerful tool for software projects
Project Monitoring and Control. Introduction Goal: ensuring that the project is on time and on budget and/or highlight any deviation from the plan Areas.
Project Management Process Project Description Team Mission/ Assignment Major Milestones Boundaries Team Identification Measures of Success Roles & Responsibilities.
Earned Value Management
Advanced Project Management Project Cost Management Ghazala Amin.
Chapter 10 Project Monitoring and Control
Project Management Software Tools Cheryl A. Wilhelmsen Lee Ostrom.
CPM-400: xxx Lesson B: EV Data Analysis I Instructor Ellen Udell
EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool
Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.
This work is licensed under a Creative Commons Attribution 3.0 Unported LicenseCreative Commons Attribution 3.0 Unported License (CC-BY). Project Management.
Project Monitoring and Control. Monitoring – collecting, recording, and reporting information concerning project performance that project manger and others.
Project Management Methodology Project monitoring and control.
Understanding Earned Value Analysis
1. Earned Value Analysis (EVA) Earned value is a measure of progress enables us to assess the “percent of completeness” of a project using quantitative.
Earned Value JOEL VIRAY TOPICS What is Earned Value Management? –Why do I need it? –How do I do it? Earned Value Reporting Earned.
Chapter 15 Cost Control.
9-1 Project Management from Simple to Complex. 9-2 This work is licensed under the Creative Commons Attribution-Noncommercial-Share Alike 3.0 Unported.
Earned Value Management System (EVMS). Given: –total budget of $100,000 –12 month effort –produce 20 units Status: –spent to date: $64,000 –time elapsed:
10/19/ :26 AM 1 Project Cost Control. 10/19/ :26 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
Earned Value SOS section Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much.
Project Management Part 6 Project Control. Part 6 - Project Control2 Topic Outline: Project Control Project control steps Measuring and monitoring system.
Project Cost Management
UU Master Class Earned Value 17 July Earned Value Contents What is Earned Value / Earned Value Analysis Why and where is it used A brief history.
CSE SW Project Management / Module 30 - Managing with Earned Value / Measurement Issues Copyright © , Dennis J. Frailey, All Rights Reserved.
Introduction To Earned Value November 14, Definition Earned Value is a method for measuring project performance. It compares the amount of work.
Department of CS & Eng. MSSE Program, © Fissure 1 SOFTWARE PROJECT MANAGEMENT COURSE Executing, Monitoring and Controlling Session #7.
Earned Value Analysis Tracking Project Progress. Introduction | Components | Project Scenario | Values | Calculations | Forecasts | Summary l What Is.
Where Module 04 : Knowing Where the Project Is 1.
Project Management Information System What?? Objective: –Record & report relevant information and status of various components of project –Highlight the.
1 Earned value analysis Planned value (PV) or Budgeted cost of work scheduled (BCWS) – original estimate of the effort/cost to complete a task (compare.
PMP Study Guide Chapter 11: Controlling Work Results.
EARNED VALUE MANAGEMENT & ORACLE PRIMAVERA P6 TREY MILLER, MBA, PMP ORACLE PRIMAVERA P6 EPPM CERTIFIED IMPLEMENTATION SPECIALIST GLOBAL PROJECT MANAGEMENT,
EVM – Do You Really Know What the Numbers Mean? Booz | Allen |Hamilton Seth Huckabee EVP, PMP, PMI-SP.
1 Understanding Earned Value in Under an Hour Breakout Session # A11 Name: Wayne Brantley, MS Ed, PMP, ITIL Senior Director of Professional Education.
EARNED VALUE  Earned Value Management Systems  Earned Value Analysis.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
Schedule Control (Earned Value)
Project Cost Con trol. 1.To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2.To forecast.
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
Earned Value Management
Measuring Progress HNC Project Management. Measuring Schedule Performance Break project tasks up into small work units. Work units that are too large.
Earned Value Analysis by Miles M. Hamby, PhD Copyright©2014 Miles M
Project Monitoring
“PMP® Exam Prep” Earned Value Management
TOPIC-8B- PROJECT COST CONTROL
PROJECT MANAGEMENT AND CONTROL
Budget Planning.
CHAPTER:7 Project Cost Management
Earned Value Management
Project Management – PTM712S
Earned Value Management
Project Cost Management
Work Packages / Deliverables Completed
Progress and Performance Measurement and Evaluation
Earned Value - What is it
An Introduction to Earned Value Performance Measurement
Earned Value Measures Planned Value (PV) Earned Value (EV)
فرآيند كنترل پروژه.
Earned Value Management
Presentation transcript:

EARNED VALUE MANAGEMENT (EVM)

Introduction EVM is a project management technique which measures the progress of a project by combining technical performance, schedule performance, and cost performance. Work Accomplished Schedule Budget

Introduction EVM compares PLANNED work to COMPLETED work to determine if work accomplished, cost, and schedule are progressing as planned. The amount of work actually completed and resources actually consumed at a certain point in a project TO The amount of work planned (budgeted) to be completed and resources planned to be consumed at that same point in the project

Key Definitions Budgeted Cost of Work Scheduled (BCWS) The cost of the work scheduled or planned to be completed in a certain time period per the plan This is also called the PLANNED VALUE. Budgeted Cost of Work Performed (BCWP) The budgeted cost of the work done up to a defined point in the project. This is called the EARNED VALUE. Actual Cost of Work Performed (ACWP) The actual cost of work up to a defined point in the project

Variance Formulas Schedule Variance: SV = BCWP - BCWS Schedule Performance Index: SPI = BCWP / BCWS Cost Variance: CV = BCWP - ACWP Cost Performance Index: CPI = BCWP / ACWP

Results SV, CV = 0 Project On Budget and Schedule SV, CV < 0 Over Budget and Behind Schedule SV, CV > 0 Under Budget and Ahead of Schedule CPI, SPI = 1 Project On Budget and Schedule CPI, SPI < 1 Over Budget and Behind Schedule CPI, SPI > 1 Under Budget and Ahead of Schedule

Example Project description We are supposed to build 10 units of equipment We are supposed to complete the project within 6 weeks We estimated that 600 man-hours to complete all the units It costs us $10/hour to build the equipment

Example We are supposed to build 1.67 units each week Each unit costs $600 We will spend $1,000 each week

Example Project status: Week 3 4 units of equipment completed 400 man-hours spent How are we doing? Are we ahead or behind schedule? Are we under or over budget? Results: Accomplished Work: 4/10 = %40 complete Schedule: 3/6 = %50 over Budget: 400/600 = %67 spent

Example BCWS=(600 man-hours*$10/hour)*(3/6 weeks) = $3000 BCWP=(600 man-hours*$10/hour)*(4/10 units) = $2400 ACWP=400 man-hours*$10/hour = $4000 The price of the job that we have done is only $2400 Schedule: in 3 weeks, the price of the job that we should have done was $3000 Cost: We spent much more; we spent $4000 SV = BCWP – BCWS = $2400 - $3000 = -$600 SV is negative; we are behind schedule CV = BCWP – ACWP = $2400 - $4000 = -$1600 CV is negative; we are over budget

Example SPI = BCWP / BCWS = $2400 / $3000 = 0.8 SPI is less than 1; we are behind schedule CPI = BCWP / ACWP = $2400 / $4000 = 0.6 CPI is less than 1; we are over budget

PROJECT PERFORMANCE PREDICTIONS Earned Value analysis results are used to predict the future performance of the project NOTE: There are various names in the literature. Budget At Completion (BAC) = The total budget (PV or BCWS) at the end of the project. If a project has Management Reserve (MR), it is typically added to the BAC. Amount expended to date (AC) Estimated cost To Complete (ETC) ETC = (BAC – EV) / CPI Estimated cost At Completion (EAC) EAC = ATC + AC