20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 1.

Slides:



Advertisements
Similar presentations
MODULE TRANSPORT CLIC Module Working Group 27 September 2010 Keith Kershaw CERN EN-HE.
Advertisements

Vacuum Vessel Production Readiness Review
F.Brinker, DESY, July 17 st 2008 Injection to Doris and Petra Fitting the detector in the IP-region Radiation issues Beam optic, Target cell Polarisation.
Engineering Integration of the Double- Double Bend Achromat (DDBA) into the Diamond storage ring Jim Kay Diamond Light Source Low emittance ring 2013 workshop.
Preliminary studies for Muon shield modification to accommodate LCLS II Alev Ibrahimov December, 2010 BSY.
Tagger and Vacuum Chamber Design. Outline. Design considerations. Stresses and deformations. Mechanical assembly.
Addendum to EDMS document “Instruction Manual for inserting the CMS ZDCs using the HXTC crane” In addition to the ZDC detectors in the TAN instrument.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
ZDC/Dummy Absorber Exchange Crane Proposal Paul Debbins Ianos Schmidt Univ. of Iowa - Nov. 5, 2007.
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
Carbon for SPS, state or the art and scrubbing runs, P.Chiggiato, P.Costa Pinto, P.Cruikshank, J.Ferreira Somoza, H.Neupert, A.Sapountzis, M.Taborelli,
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
SPS vacuum modification G.Vandoni SPS vacuum modification, 1.
ATLAS Upgrade ID Barrel: Services around ‘outer cylinder’ TJF updated According to the drawing ‘Preparation outer cylinder volume reservation’
Status of handling studies for PSB-LIU Caterina Bertone EN-HE LIU-PSB 17/09/2015 Courtesy: A. Newborough EDMS
BDS 11 Vacuum System for BDS [Completeness of RDR] Y. Suetsugu J. Noonan and P. Michelato Design principle Basic design Cost estimation.
1 Discussion for basic options — engineering video conference July 12, 2006 Outline Water pool — advantages — issues, problems, engineering options Aquarium.
ELENA Support system 6/11/2014 Antti Kolehmainen on behalf of WP Support system
ATC / ABOC Days – Session 4 – January D. Smekens AT-MCS-MNC 1 MAGNETS FOR SPS & BEAM LINES MTTR & Spare Policy for the LHC Injectors & Exp.
Scrubbing Review, 8/9/2015 Paul Cruikshank1. Contents SPS Layout aC factory options Assumptions & Scenarios Transport issues Radiation issues Coating.
1 Target Station Design Dan Wilcox High Power Targets Group, Rutherford Appleton Laboratory EuroNu Annual Meeting 2012.
April 23rd-24th 2013Handling Engineering Group. Introduction to CERN April 23rd-24th 2013Handling Engineering Group2  CERN: European Organization for.
Transport of the CLIC Modules and Elements CLIC Workshop October 2007 Two Beam Hardware and Integration Working Group Keith Kershaw (CERN)
SPS Dump relocation Radioactive Dump storage alternatives JL GRENARD EN-HE
Peter Hülsmann, GSI RF-Group, Tel: Task SIS18-1: h=2 Cavity P. Hülsmann GSI, Gesellschaft für Schwerionenforschung.
TAS at IP5 Present situation and plans François BUTIN TS/LEA.
PSB dump replacement 17 th November 2011 LIU-PSB meeting Alba Sarrió.
ILC TRANSPORT AND INSTALLATION Questions from last CES: Beam height explanation, Transport implications of sloping access tunnels proposed for access to.
Transport & Handling of Detectors TAN Workshop S. Prodon –
LIU-SPS, 29 April 2015 Paul Cruikshank1. Variants today: Starting point: Assume same boundary conditions as 15/4/2015 presentation Analysis is for SPS.
Special interventions Status of production and QC Nicolas Bourcey TE-MSC-MDT Fourth LHC Splice Review November 2013.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
LIU-SPS, 15 April 2015 Paul Cruikshank1. In the beginning…. First slide that Brennan gave me – everything decided ! LIU-SPS, 15 April 2015 Paul Cruikshank2.
Additional muon stations for the Upgrade of the Elevator Regions in the ATLAS Muon Spectrometer. Installation scenario, status on the installation tools.
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
The integration of 420 m detectors into the LHC
CLIC MODULE TRANSPORT AND INSTALLATION Keith Kershaw CES, 8 October 2008.
IEFC Workshop 9 th March 2012 – Magnet activities in IEF during LS1 – J. Bauche 1 Magnet activities during LS1 J.Bauche, on behalf of the TE/MSC/MNC section.
TE-CRG Activities D. Delikaris, TE-CRG.
AT-VAC SPC Nicolaas KOS Beam Screens for Inner Triplet Magnets LHC Upgrade Phase 1 Nicolaas KOS  LHC Upgrade phase 1  Inner triplet BS Requirements.
SPSU – May 19, 2009 – Resources needed for SPS coating project– J. Bauche 1 Coating of the SPS Main Dipoles Vacuum Chambers: Resources Needed for Project.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 1 SPS Magnet Test Campaign and Consequences for LS1 J. Bauche*, P. Catherine,
LIU-SPS planning – provisional LS1 / LS2 BLM, BPM MKE/MKDV/H aC 1 sextant aC 5 sextants RF 200 MHz LSS3 RF 200 MHz preparation RF 200 MHZ building.
Facility to coat the SPS magnets with carbon Objective: coat at least 90% of the SPS with a carbon thin film with low secondary electron emission in order.
Cost Evaluation of Storage Ring Magnets Claudio Sanelli March 19, 2012.
Status Report of the Realignment for J-PARC 3GeV RCS N. Tani, H. Hotchi, M. Yamamoto, J. Kamiya, K. Horino, M. Kinsho J-PARC Center, JAEA 1 Outline 1.
Logo area Handling Engineering Requirements EN-HE Group Bruno Feral – EN/HE EDMS HL-LHC CE Consultant Kick-Off Meeting – 31/05/2016.
DTU A VISION OF SUPPORTING NEUTRON CHOPPER ESS PT 1 - BUNKER SYSTEMS Discussion Document.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
Magnet activities in SPS during EYETS
LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
Updated Design of Detector Hall
TE-MSC activities in SPS during LS2
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
AD consolidation activities in LS2
Arc magnet designs Attilio Milanese 13 Oct. 2016
EN-HE SPS works during EYETS
Pierre-Alexandre Thonet
TE-MSC activities in SPS during YETS
High Pressure Water Jetting
The 11T cryo-assembly: summary of design and integration aspects
Proposal for the modification of building 151 in view of the LS2 PS main magnet and TT2 consolidaiton projects Dominique Bodart TE-MSC-MNC 29/09/2017.
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
Magnet electrical and hydraulic (dis)connections for coating
XFEL Collimation and Beam Switchyard Vacuum Issues
Progress and plans, Mechanics system of CEPC
LS3 Study & Readiness Meetings
Status of QQXF cryostat
Presentation transcript:

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 1

2  Introduction  Coating project: hypothesis of work  Strategy 1: coating in the tunnel Previous experiences Implementation of the method in the coating project Pros & cons Rythm, bottlenecks  Strategy 2: coating in an underground workshop Previous experience Workshop Transport Pros & cons Rythm, bottlenecks  Strategy 3: coating in a surface workshop Previous experience Transport Pros & cons Rythm, bottlenecks  Conclusion

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 3 General overview of the SPS main dipoles  744 MBA/MBB dipoles form the main bending magnet system of the SPS.  MBA and MBB dipole magnets have similar outside dimensions, but different apertures. Each magnet is about 6 meter long, 18 tons and consists of two identical laminated half- cores, a coil assembly composed of inner and outer coils and a captive stainless steel vacuum chamber.  The assembly is welded into a rigid self- supporting unit.  The 744 dipoles are powered and cooled via a copper bus-bar system

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 4 Transport of dipoleInstallation of main dipole in the SPS Handling and transport of SPS main magnets  done with the ‘Dumont’ machines: - Trailers equipped with 2 handling manipulators, not motorized - Hydraulic system, not automated - Tare: 12 tons

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 5  Coating process → Vacuum chambers: no disassembly of vacuum chambers from the magnets to perform the coating (process would take 3 weeks / magnet) → Time of coating process: 48 hours, including installation of equipment, vacuum pumping, coating and dismantling of equipment → Position of magnet during process: horizontal  Magnets treated → Only SPS main dipoles ≈ 5 km of vacuum chambers (>70 % of SPS vacuum system length)  Time → Duration of shutdown period: 14 weeks of access in the machine  Ressources → Equipment: use of existing vehicles for transport (2 Dumont handling machines + trailers), possibly with some adaptations (No new vehicules.) → Manpower: work done mainly during normal working hours, 5 days/week

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 6  Previous experiences Installation of synchrotronic shieldings in some SPS magnet vacuum chambers in the 80’s Installation of RF shieldings in the pumping port cavities of the magnet vacuum chambers between 1999 and 2001 → Method used: 1 over 2 magnets removed from its position and put in the passageway on the Dumont handling machines to allow accessing interconnections on all the magnets → Figures (RF shieldings): 1200 bellows equipped during 2 long shutdowns 370 main dipoles and a hundred of auxiliary magnets removed from their position Rate of treatment: 3 magnets / day removed and reinstalled to their position Time of process / magnet: a few hours, including handlings RF shielding model

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 7  Implementation of the method to the coating project Idea to take out of its position 1 over 2 magnet to allow access to all vacuum chambers  OK BUT with a coating process time ≈ 2 days, doing it in the same way means to let 370 magnets, 2 days each one, on the Dumont in the passageway. Since only 2 Dumont are available  project would be realised in about 370 days… more than 5 shutdowns !  Alternative: lifting the magnets about 500 mm above their position instead of bringing them in the passageway + stabilizing them with supports in order to free the Dumont + removal of SSS girders Access for cathode Insertion SPS typical half-cell

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 8 BUT space available above the magnet is too small to realize that with the Dumonts  need to purchase or manufacture a lifting device that pushes instead of pulling (like a lifting table) SPS tunnel dipole position

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 9  Pros Minimize handling to the very minimum No transport The method gives access to both side of each quadrupole that could so be treated too (≈10% of SPS ring vacuum length) Quadrupoles stay in place  survey reference kept, time won for alignment  Cons Radioactive environment Space available is small External conditions more difficult than dedicated workshop Bulky equipment to move around Interference with other activities Requires numerous specific supporting structures

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 10  Bottlenecks Number of coating equipment available Number of supporting structures available  Rhythm Assuming in 2 days: 1 team disconnect-reconnect 6 dipoles from the busbars; 1 team lift and put back in place 6 dipoles ; 1 team remove-reinstall 3 SSS girders; 1 team clean 12 dipole vacuum chambers; 1 team align 3 half-cells Assuming 12 supporting units are available 12 coating equipments are available  Rhythm = 6 magnets / day  Project completed in 120 jours ≈ 2 shutdowns

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 11  Previous (and current) experience MBB manifold consolidation program: complete refurbishment of all the manifolds on the MBB magnets equipped with Lintott coils in operation in the SPS → Method used: magnets removed from their positions and transported with the Dumonts and trailers to ECX5 cavern converted in radioactive workshop → Figures : 255 magnets treated over 3 years (shutdowns 2007, 2008 & 2009) Refurbishment rate: 4 magnets / day Time of process / magnet (machining, welding, assembly and tests): ≈ 2 hours Before After

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 12  Workshop → Radioactive workshop in ECX5 cavern - Underground instead of surface: to limit the risks of transport and handlings and to win time - In the ECX5 cavern: → polar 40 tons crane available (refurbished in 2007) → enough space to refurbish 4 magnets / day → low radiation level ECX5 worshop for MBB manifold consolidation (top view) ECX5, workshop sideECX5, storage side

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 13 → Layout of ECX5 workshop with 18 magnets in 2 layers ECX5 coating workshop (top view) ECA5 & ECX5, concrete separation wall removed (top view) ECX5 coating workshop (front view) 210 m m 2

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 14 Journey with Dumont machines - Average speed ≈ 2 km/h - T 1 sextant = 36 min Journey with trailers - Average speed ≈ 5 km/h - T 1 sextant = 14 min Transfer Dumonts ↔ trailers - Possible in LSS2-TT20, LSS4-ECX4 and LSS6-TT60 - T transfer ≈ 20 min Sectors type 3 Sectors type 2 Sectors type 1 Half-cells 131 and 304: positions from which going through journey of sector types 2 or of type 3 takes the same time  Transport

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 15 Sectors Sector type Average time install or remove magnet [min] Dumont journey Average time Dumont-trailer transfer [min] Trailer journey Average time loading or unloading in ECX5 [min] Total time go and return [min] Quantity of magnets per sector type Total time for transport per sector [h] Average distance [sextants] Time / sextant [min] Average time of journey [min] Distance [sextants] Time / sextant [min] Average time of journey [min] / , / ,73625, / ,33610, Total transport time (all magnets) [h]1816 Average time of transport / magnet [h]2,44 Working time / day for each Dumont (6 magnets / day) [h]7,3 Total transport time (all magnets) with 2 Dumont [jours]124  Transport time estimate, based on MBB consolidation experience:

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 16  Pros Workshop environment with lower radiation level than in the tunnel Much space available, possibility to pile up magnets Equipment regrouped in a dedicated workshop Equipment and supporting structures to perform the coating stay in place No special supporting structure required, can use concrete blocks  Cons Interference between transport and other activities Risks inherent to handling and transport increased Time lost with transport

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 17  Bottlenecks Only 2 Dumont vehicles are available Number of coating equipment available Space available in ECX5 (  could extend in ECA5)  Rhythm Assuming same rhythm for connection to busbars, alignment and vacuum than strategy 1 Assuming transport teams work a bit in overtime or in 2 shifts with 2 Dumont + trailers  Rhythm = 6 magnets / day  Project completed in 120 jours ≈ 2 shutdowns

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 18  Previous experiences None in big projects, only preventive and corrective annual magnet exchanges (5 to 10 / year) → Method used: magnet removed from its positions and transported with the Dumont to BA3 lift and pulled by electro tractor to magnet workshop in bdg. 867, replaced by a spare BAs equipped with hoist: BA2, BA3 & BA6 - T lift ≈ min  Transport Need to implement an important logistic in surface in addition to the one underground Choice of the hoist(s) could be linked to the choice of workshop(s), many possibilities Hoists need to be refurbished ?

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 19  Candidate workshops 867 or another workshop in Prevessin site to allow coming out of the machine through BA3 hoist  no need for lorries for the surface transport Workshop in Meyrin site, with same advantages if we come out from BA6 hoist Workshop in BHA5  if we open the concrete block wall between ECA5 and ECX5, we can lift the magnets with the BHA5 crane (no more need for hoists)

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 20  Pros Work in a non radioactive environment, and not underground  Cons Heavy logistics, more difficult to manage and time consuming Increase of risks inherent to handlings and transport compared to strategy 1 and 2 More costly than strategy 1 and 2

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 21  Bottlenecks Only 2 Dumont vehicles are available Number of coating equipment available Transport teams and vehicles available  Rhythm Should not be better than strategy 1 and 2, probably worse  Rhythm = 6 magnets / day ?  Project completed in 120 jours ≈ 2 shutdowns ?

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 22  Which strategy ? Depending on evolution of studies of coating process (operating mode, process duration, conditions needed…) Depending on deadline Depending on ressources allocated to the project (budgets, manpower) Depending on shutdown durations  Impossible to choose before having fixed these parameters  Next milestone ? Definitely define the process of coating Tests on several magnets in the machine ?

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 23 Special thanks to David Smekens and Marc Ainoux for their help

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 24  Reducing the sps machine impedance, P.Collier, M. Ainoux, R. Guinand, J-M Jimenez, A. Rizzo, A. Spinks, K. Weiss  New Strategy for the Repair of SPS Dipole Water Manifolds, J.Bauche, W.Kalbreier, D.Smekens (EDMS Doc. No.: )  Projet de Consolidation des Dipôles Principaux du SPS. Remplacements des manifolds de refroidissement des bobines dipôles, David Smekens (EDMS Doc. No.: )

20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 25 Rhythms of processes for the groups involved in the MBB manifold consolidation program (not including workshop) - TS/HE: average of 4 to 5 magnets / day (whole process of (un)installation, transports go and return, multiple handlings in the workshop) following the vicinity of the position with only one Dumont crane (2 available) + trailers - AT/VAC: average of 8 vacuum sectors opened and closed + 85 magnets disconnected – reconnected in a few weeks / shutdown - TS/SU: 6 to 8 dipoles / day realigned - AT/MCS: 6 to 8 magnets / day disconnected or reconnected to busbar system with only one induction brazing machine (2 available) - TS/MME: 4 magnets / day fitted with 4 TIG-brazed bronze sleeves