LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank.

Similar presentations


Presentation on theme: "LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank."— Presentation transcript:

1 LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank
LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank

2 LIU-SPS: a-C coating & impedance reduction
Preparing SPS for HL-LHC beams Reduce longitudinal impedance by adding shielding at chamber interconnections Reduce SEY with a-C where scrubbing may not be sufficient MBB MBA SSS QD QF a-C + Imp’d Drift 64 m arc cell Recommendations of LIU-SPS Scrubbing Review 8-9 September 2015 LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank

3 SPS beam pipes to be a-C coated.
Dipoles Quadrupoles SSS & drifts QF type QD type Includes: Ø80, Ø159, QF, MBA profiles In-situ a-C, 6.5 meter x 2

4 Flange impedance reduction (QF SSS only)
Existing flange impedance reduction (pumping port & 10 convolution bellows) SSS flange impedance reduction (4 convolution bellows) LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank

5 QF sequence - aC & IR Mandate: EYETS – up to 1 ARC
LS2 – complete 6 arcs Prevessin site (magnet lift) (LS2) 8 QF (YETS 2017) 9 QF (EYETS 2016) BA3 (magnet lift) RF BA2 BA4 TT20 ext TT40 ext Injection & Dump Future dump BA1 BA5 TT60 ext ECX5 BHA5 BA6 Meyrin, P1 LHC (magnet lift) QF activity includes QF & SSS QF treatment (aC & IR) LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank

6 MBB work sequence Mandate: EYETS – aC in-situ learning
LS2 – 1 sextant to industrialise LS3 – all SPS if required Prevessin site (magnet lift) (LS3) 2 cells (EYETS 2016) 0.5 to 1 arc (LS2) 1 cell (YETS 2017) BA3 (magnet lift) RF BA2 BA4 TT20 ext TT40 ext Injection & Dump Future dump 2 cells - done BA1 BA5 TT60 ext ECX5 BHA5 BA6 Meyrin, P1 LHC (magnet lift) MBB aC activity includes QD & SSS QD treatment (aC & IR) LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank

7 Remainder drift (YETS 2017)
LSS drift Ø159 - aC Mandate: EYETS – 10% of inventory LS2 – complete 6 LSS Prevessin site (magnet lift) (LS2) BA3 (magnet lift) RF Remainder drift (YETS 2017) BA2 BA4 10% drift (EYETS 2016) TT20 ext TT40 ext LS2 Drift Chamber Sequence: BA1 – new layout, % new chambers < LS2 BA2 – activated, new chambers < LS2 BA3 – new layout, % new chambers < LS2 BA4 – done in EYETS & YETS BA5 – new layout, % new chambers < LS2 BA6 – coat existing chambers Injection & Dump Future dump BA1 BA5 TT60 ext ECX5 BHA5 BA6 Next steps: Study each BA layout for new chamber needs What % drift new layout, % drift existing. What ‘impedance reductions’ to implement Create aC to do list – before LS2, during LS2. Meyrin, P1 LHC (magnet lift) LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank

8 Does TE/VSC have all needed information from LIU
Scrubbing review – agreed scope, timeline and budget of the aC coating (and flange impedance reduction) Documentation LSA – done List of hazards – approval process to start Safety File Descriptive Part 1 – approval process to start Functional spec for impedance reduction – engineering check Functional spec for aC coating – approval process to start ECR (for EYETS) in preparation LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank

9 Are TE/VSC preparatory activities within expected timeline?
aC coating for EYETS Validation of 13 m MBB string in 181 Validation of QF profile coating in 181 Setting up of long test station in 867 (MBB, QF, SSS girder) – trials and training Job open for manufacturing of replacement drift chambers. Procurement of components for benches (tunnel & 867) Setup of benches in 867 vacuum lab to do Flange Impedance Reduction for EYETS. Shielding design finalised for EYETS implementation Based on design applied during 1999 impedance reduction Cannot wait for RF measurements/simulations on flexible fingers Cannot wait for soft clamp tests (by-pass of insulated flanges) Detailed design and manufacturing will be tight Planning for EYETS All tunnel activities in same arc Takes account of learning objectives - time margin for surprises VSC activities are staff dominated Methodologies will be confirmed – eg SSS girder/individual magnet handling Drift chambers manufactured and coated in advance of EYETS Detailed planning to be elaborated with EN-ACE-OSS LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank

10 Has all the LIU required work been declared in PLAN
Has all the LIU required work been declared in PLAN? (Are all dependencies on other groups defined…?) Dependencies on other groups identified during costing exercises for aC & flange impedance reduction in 2015. Weekly deployment meeting with representatives of involved group TE-MSC, EN-ACE-SU, EN-HE, TE-VSC, BE-RF, EN-ACE-OSS, HSE-RP, Data entered in PLAN (EYETS, LS2) LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank

11 Are the LIU EVM timeline & budget correct?
Annual work units based on APT data (agreed budget) Need to establish EVM data to reflect deliverables LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank

12 Are the VSC-CONS items linked to the operation of LIU approved, in time and within specification?
All TE-VSC SPS Cons requests up to 2020 have been approved Ion pumps, ion pump power supplies, spare chambers, flanges, bellows, valves, pumping group renovation, … On-going clarification of SPS controls consolidation (PLC replacements) request. Postponed during 2015 CONS arbitration exercise but now understood to be within ‘CONS envelope’ attached to HL-LHC during C&S. LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank

13 Thanks for your attention
LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank