Presentation is loading. Please wait.

Presentation is loading. Please wait.

A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN

Similar presentations


Presentation on theme: "A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN"— Presentation transcript:

1 A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
LEP cryostat Design A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN Internal review of IR2 LEP cryostats (WP11/WP5)– 17 May 2017

2 Summary Introduction Requirements Basic concept Structural design
Cryogenic design Instrumentation A. Vande Craen

3 Introduction Build to print design
Use of standard LHC components when possible New concepts to Ease assembly Limit welding work Avoid deformations during fabrication and life cycle A. Vande Craen

4 LE requirements : LHC-LE-ES-0001
LHC equipment requirements for pressure, temperature and leak tightness LE requirements : LHC-LE-ES-0001 A. Vande Craen

5 Basic concepts A. Vande Craen

6 Concept Concept Goal Cold bore in helium vessel
Limit maximum cold bore temperature Pipes in continuity of standard interconnection lines Limit helium inventory (vs. large helium vessel) Shuffling module at LEN extremity Adaptation of line layout Installation of busbars lyras Installation of heat exchanger Bolted supporting structure Limit welding work during assembly LEP-A mirror of LEP-B Limit components inventory A. Vande Craen

7 LEP vs LE A. Vande Craen

8 Existing connection cryostats LEP : No shielding needed
Beam lines shielding Existing connection cryostats 20 mm lead shielding around beam lines LEP : No shielding needed RadWG meeting, 06/07/2016 Courtesy C. Bahamonde A. Vande Craen

9 Structural Requirements and solutions A. Vande Craen

10 Specific requirements
Golden class magnet (most stringent) Tolerances distribution Source +/- Vertical [mm] +/- Horizontal Geometry (sag) 0.015 Geometry (straightness) 0.2 Play in V/V’ assembly Play in alignment system 0.1 0.35 Alignment tolerance 0.05 Stability over time Total 0.465 0.7 Maximum 0.5 0.8 A. Vande Craen

11 Cold bore/V’ supporting
Goal V’ for cooling of cold bore with helium Insure positioning of cold bore inside V’ lines (play ~ 0 mm) No deformation of cold bore Solution Local “Punching” of V’ line to make contact with cold bore 3 deformation at 120° A. Vande Craen

12 Solution validated V/V’ support Tooling : lathe chuck
Development campaign to find correct procedure Zero gap between tubes No deformation of cold bore Solution validated A. Vande Craen

13 Cold bore alignment system
Goal Align beam lines within tight tolerances Solution Sleeve on V’ (tack welded) to improve pipe geometry Brass/Stainless steel contact to avoid seizing X-Y table for positioning Source Requirement Result V’/support +/- 0.1 (V) +/ (H) +/- 0.05 Play in alignment system < +/- 0.05 A. Vande Craen

14 H-beam Ease access during assembly No structural welds
No deformation/stresses Mechanical assembly for cold mass alignment Tight tolerances easy to achieve Machined plates  flatness = 0.2 mm/m Stress relieving  no later deformation due to stress relaxation Light cold mass (~ 2 tons) Lower mechanical rigidity than closed profile A. Vande Craen

15 Flexible M lines Tolerances and forces in interconnection
Solution : reduce interconnection forces > 90% due to M lines bellows Negligible deformation of cold mass (<< 0.1 mm deformation due to weight) (See M. Moretti’s presentation) A. Vande Craen

16 Flexible line prototype
Test : 5 mm vertical offset 25 bar (water) External radial excitation Results : Small line displacements V = 0.07 mm H = 0.1 mm No buckling Solution validated A. Vande Craen

17 H-beam supporting Two supports (spacing = 1985 mm)
Support identical to 11T magnet Standard LHC dipole sliding support posts Fixed support post : dipole/SSS hybrid Standard Dipole height Fixed to vacuum vessel as in SSS Sliding support Fixed support A. Vande Craen

18 Cryogenics Requirements and solutions A. Vande Craen

19 Specific requirements
Cold bore < 2.7 K in any point The cold bore temperature shall remain < 2.7 K, where H2 saturated vapour pressure is higher than the HL-LHC beam vacuum baseline N/M link for filling and cooling of N line Heat exchanger (LEP thermally independent) A. Vande Craen

20 Cold bore cooling Goal Solution
Beam line heat load = 0.65 W/m (LHC-LE-ES-0001) Warmest point bellow 2.7 K Solution Addition of a V’ line around cold bores Filled with superfluid helium Connected to shuffling module Cooling by conduction through superfluid helium A. Vande Craen

21 Shuffling module Goal Solutions Create space for busbars lyras
Transition between position of lines in standard interconnection and LEN House bayonet heat exchanger Solutions 2 welded stainless steel dished ends with nozzles 12 mm thick for deformations ~ bar A. Vande Craen

22 Bayonet heat exchanger
Standard LHC heat exchanger tubes Stainless steel to Cu-OFE transition at extremities Cu-OF tube electron beam welded to transitions HX = 0.32 m long  maximum K Estimated total heat load of LEP at 1.9 K : 6.6 W A. Vande Craen

23 N/M hydraulic link Goal : Solution
Filling N line during cool-down Cooling N line to 1.9 K by superfluid conduction to M lines circuit Solution Rigid line with loop for thermal contractions (flexible hose in LE) Increased inner diameter : 22.3 mm  23.7 mm Connected to “M4 nozzle” on shuffling module  shift of ~ 2.5 m from LE Maximum temperature in N line (0.1 W/m2) LE : K LEP : K A. Vande Craen

24 H-beam cooling Goal Solution
Uniform cool-down of the cold mass (no hot spot, no deformation) Cooling of the cold mass from 300 to 80 K < 1 week (on test bench) Solution Copper clamps on M1 and M2 lines  vertical symmetry Copper plates on H-beam for heat distribution Copper braids to connect clamps to plates All bolted solution Cooling time 300  80 K ~6 days (conservative assumption) (See M. Moretti’s presentation) A. Vande Craen

25 Instrumentation A. Vande Craen

26 Temperature measurement
Instrumentation Temperature measurement Temperature sensors on beam line (warmest point) to give “Cryo-OK” (LHC-LE-ES-0002) For cold test : temperature sensors to measure temperature gradient during cool-down Voltage taps No voltage taps needed in the connection cryostats (A. Verweij, 23/03/2017) A. Vande Craen

27 Thank you ! A. Vande Craen


Download ppt "A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN"

Similar presentations


Ads by Google