Unscheduled Flow What direction for the Future

Slides:



Advertisements
Similar presentations
The Midwest ISO from a Transmission Owner Perspective.
Advertisements

Parallel Flow Visualization Data Requirements Parallel Flow Visualization Data Requirements NERC ORS Meeting Toronto, Ontario September 23-24, 2009 Jim.
NAESB Coordinate Interchange Version 1 Standard Revision 1, Draft 5 August, 2005.
NAESB Coordinate Interchange
Business Practices Subcommittee Update February 2, 2010.
Unscheduled Flow Administrative Subcommittee Report Robin Chung October 24, 2013 Anaheim, CA.
Definition of Firm Energy and Interruptible Transmission Two Issues Causing Problems for Business in the Western Interconnection.
NAESB Coordinate Interchange Standard, Version 1 / 0
NERC TPL Standard Issues TSS Meeting #146 Seattle, WA August 15-17, 2007 Chifong Thomas.
Operating Reserves --- Again A Discussion Primer
Enhanced Curtailment Calculator Task Force Report
Craig L. Williams UFAS Liaison Market Interface Manager ECC Cost Benefit Analysis Review July 17-19, 2013 Standing Committees Joint Session.
WECC OC Marina del Rey, CA October 30, 2008 UFAS Report Paul Humberson, UFAS Chair.
WECC Operating Committee Report WECC Member Meeting April 20, 2006.
1 Compliance Report WECC Board of Directors Meeting December 7-8, 2006 Steve Rueckert Director, Standards and Compliance.
Interchange Authority Recommendations Board of Directors Meeting December 7, 2007.
Standards Update WECC Board of Directors Technical Session December 5, 2007 Albuquerque, New Mexico Steve Rueckert Director of Standards.
BAL-002-WECC-1 Contingency Reserves
Unscheduled Flow Administrative Subcommittee Report David Lemmons March 27, 2013 Salt Lake City, UT.
Intra Hour Tagging/Oasis During System Contingencies The transmission tagging process was initially developed to solve an after the fact accounting issue.
Western Electricity Coordinating Council Status of NERC Standards Activity WECC PCC Meeting March 6-7, 2008.
POTF Status update.
Enhanced Curtailment Calculator (ECC) Task Force Joint Guidance Committee Presentation and Motion to the OC & MIC Standing Committee Meetings March 27-29,
Phase II – Analyze the Identified Issues from Perspectives of Alternative Approaches Determine which of the identified issues remain under alternate approaches.
MARKET INTERFACE COMMITTEE OC and PCC Approval Items March 6-7, 2008 Albuquerque, New Mexico.
FEBRUARY 27, 2013 BY NARINDER K SAINI ED SKIBA BPS-CO-CHAIRS Parallel Flow Visualization Overview 1.
Enhanced Curtailment Calculator (ECC) Jeremy West Sr. Operations Engineer.
Unscheduled Flow Administrative Subcommittee Report for ISAS Robin Chung January 28, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.
Jeremy West Sr. Operations Planning Engineer ECC Update January 28, 2015.
Enhanced Curtailment Calculator
UFMP methodology changes in the updated webSAS February 2015 A video presentation reviewing the webSAS UFMP methodology changes going into effect March.
SPP.org 1. 2 Aggregate Transmission Service Study (ATSS)
NERC Congestion Management Congestion Management Option 3 Vendor Meeting Julie Pierce – NERC IDCWG Chair.
Business Practices Subcommittee
WECC Market Interface Committee Update WSPP Spring 2008 Meeting April 8, 2008 Robert D. Schwermann MIC Chair.
Andy Meyers OC Update ISAS April 2014 Salt Lake City, UT.
Peak RCCo Performance Metrics Draft –November 2013.
Unscheduled Flow Administrative Subcommittee Report for ISAS Robin Chung August 20, 2014 Salt Lake City, UT.
Business Practices Subcommittee Update Executive Committee Meeting February 18, 2014.
Flowgate Allocation Option Parallel Flow Visualization Business Practices Subcommittee Meeting June , 2010.
Transmission Congestion Management – IDC Granularity Option 3A Larry Kezele and Jeff Norman June 28, 2005 NERC/NAESB TLR Subcommittee.
NAESB WHOLESALE ELECTRIC QUADRANT BUSINESS PRACTICES SUBCOMMITTEE ACTIVITIES UPDATE TO JOINT ELECTRIC SCHEDULING SUBCOMMITTEE JANUARY 5, 2012 BY ED SKIBA.
NAESB BPS Yasser Bahbaz– IDCWG Chair January 5 th, 2016.
Unscheduled Flow Administrative Subcommittee Report for MIC Pete Heiman October 14, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.
RAWG Agenda Item LAR Data WECC Staff. Data Elements Generator information – Existing – Changes Monthly Peak Demand and Energy (actual year and.
Unscheduled Flow Administrative Subcommittee Report Robin Chung October 8, 2014 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.
EIM/EDT Update ColumbiaGrid Planning Meeting June 2, 2011.
NAESB BPS UPDATE TO EXECUTIVE COMMITTEE AUGUST 21, 2012 BY NARINDER K SAINI ED SKIBA BPS-CO-CHAIRS PARALLEL FLOW VISUALIZATION PROJECT 1.
CPUC Resource Adequacy Program – LAO briefing May 25, 2009.
RELIABILITY COORDINATOR TOPICS 2006 FRCC SYSTEM OPERATOR SEMINAR.
Brett Wangen Director of Engineering, Peak Reliability
Western Electricity Coordinating Council
Unscheduled Flow Administrative Subcommittee MIC/OC Report
Doug Reese, USFEATF Chair
Kenneth Silver Los Angeles Department of Water & Power
Mgr. Interconnection Reliability Initiatives
Mgr. Interconnection Reliability Initiatives
Unscheduled Flow Administrative Subcommittee Report
Standard Review Subcommittee Update
Enhanced Curtailment Calculator (ECC)
Path Operator Task Force Kickoff April 3, 2013 Webinar
Doug Reese, USFEATF Chair
Unscheduled Flow Administrative Subcommittee Report
UFMP methodology changes in the updated webSAS
Standard Review Subcommittee Update
Path Operator Task Force Kickoff April 3, 2013 Webinar
Two-Tier Firm Curtailment Overview
NERC Congestion Management
Unscheduled Flow Administrative Subcommittee Report for MIC
Jeremy West Sr. Operations Engineer
Presentation transcript:

Unscheduled Flow What direction for the Future Unscheduled Flow What direction for the Future? Question for WECC members at the MIC Meeting June 15, 2007 David Lemmons, UFAS Liaison

Current Unscheduled Flow Mitigation Plan & Procedure Starts with phase shifters (PST) Follows with schedule curtailments During curtailment, responsible entities have choice of action: Curtail schedule that has TDF greater than 5% Create schedule that has a TDF lower than -5% Redispatch generation to provide relief

Current Unscheduled Flow Mitigation Plan & Procedure Paths with Unscheduled Flow history are Qualified via prescribed process Effects of every schedule from any zone to any other zone in WECC has a Transmission Distribution Factor (TDF). The set of TDF values is calculated on a seasonal basis The Qualified Path Operator calls for relief when loading meets criteria

Current UFMP Issues Transmission product is not factored into the relief requirement: no diff F vs. NF Should reliability issues be handled by reliability side entities or PSEs? Disparity between pre-existing and restricted (new) transactions. Should they be equalized? Plan is normally used on 7 of approximately 70 rated paths, should others be allowed? Contract issues related to failure to perform: PSEs could be charged liquidated damages for schedules they curtail outside contract allowances System model is intact only, no outage effects

UFMP Issues (cont.) FERC painted the Eastern Interconnection schedule curtailment (TLR) as ineffective, applauded the Phase Shifter component of WECC UFRP, but said NOTHING about schedule curtailment in the west !?! If someone other than PSE controls Procedure, PSE option$ likely go away. NERC Standards require Reliability Coordinator to initiate/control procedure (IRO-006-3), not how WECC currently does this. Current distributed responsibility to PSE community has many entities spending much time on UF management, training, compliance, etc. Would this be made more efficient if centralized?

Compliance History Previously, under RMS, the receiving entity was responsible for curtailment. Currently, The Version Zero UF Standard submitted under Tier 1 keeps that responsibility with the receiving entity. However, each responsible entity gets to choose which schedules to keep, as the requirement is only to “provide relief”, not to curtail specific schedules.

Current Standard Situation UF Version 0 has been submitted (part of Tier 1 package). Keeps responsibility with receiver. Version 1 (V1) has been completed and is ready to post for process. V1 is essentially the same with some clarification for the dc ties. The UF Plan itself is in need of rewriting. There are many appendices and several areas that do not immediately provide clarity. Future direction has huge impact

Improvements? Expand the Plan to be useful for more/all Paths ? Perform curtailments in order of transmission priority ? Study pre-existing and restricted (new) transactions for effects of equalizing ? Couple real-time outage information to system model in webSAS? Make schedule curtailment effective time to be “now”, not top of next hour?

Improvements? RC’s initiate/control procedure per IRO-006 and have a machine do the curtailment. The Eastern Interconnection does this. Relief is provided but there is no choice in which schedules get curtailed. However, there is no sanction on the receiver for failure to curtail.

The Good & the Bad Decrease workload for PSE/LSE entities - Good Decrease WECC Staff compliance work - Good Eliminate $ sanctions for Members - Good Decrease UF Training for Members – Good Increase workload on the RC’s – bad Shift costs for UF tool from 73 subscribers to one (WECC) or two (RC’s) – bad? PSE/LSEs lose choice of which schedule to curtail (often economic) – bad Does the Good outweigh the bad?

Crossroads ahead This is a Member choice So, in order to plan for the future, UFAS asks for your opinion

Today’s Straw Poll Keep responsibility (and sanctions) for UF curtailment with PSE/LSE (but they retain choice of action and the sanctions) OR Transfer responsibility for UF curtailment to the RC’s, (but give up choice of action and sanctions)