Caltrans District 4 Contractors’ Outreach Meeting August 31, 2005
Caltrans District 4 Introductions Janet Adams SFOBB East Span Project Manager, Caltrans
Caltrans District 4 Welcome Bijan Sartipi District 4 Director, Caltrans
Caltrans District 4 Welcome Olivia Fonseca Deputy Director Civil Rights Program and Small Business Advocate
Caltrans District 4 SFOBB Self-Anchored Suspension Span Contract Janet Adams SFOBB East Span Project Manager, Caltrans
Caltrans District 4 San Francisco - Oakland Bay Bridge East Span Seismic Safety Replacement Project
Caltrans District 4 Contract F4 This contract constructs the self-anchored suspension portion of the new East Span Advertised on 8/1/05 Bids open on 2/1/06 Estimated cost is $1,450,000,000 Project funded by Toll revenues and State funds, therefore Buy America is not required Contract duration is 2130 working days (7 days/week)
Caltrans District 4 Contract F4 Contract consists of the following components: –Two steel orthotropic box girders and decks –Steel tower consisting of 4 tower shafts with elevator –Concrete cap beam at Piers W2 and E2 –Steel bike path –Steel prefabricated parallel wire strand cable system – All steel fabrication will be off-site
Caltrans District 4 Self-Anchored Suspension Span
Caltrans District 4 SAS and Skyway
Caltrans District 4 View from Yerba Buena Island
Caltrans District 4 District Contracts Bob Finney Deputy District Director - Construction
Caltrans District 4 Fiscal Year Construction Workload ($1000s)
Caltrans District 4 North Counties Upcoming Projects Son 101 HOV SR 12 – Steele Ln SON 101 Steele Ln IC Mrn 101 HOV Central San Rafael 580 Mrn 580 RSR - Polyester Deck Overlay Napa 29 - St Helena Roadway Rehabilitation Mrn 101 Blithedale Off-Ramp Napa 121 – Replace Tulucay Bridge
Caltrans District 4 Richmond San Rafael Bridge Polyester Deck Overlay Complete Bridge Deck Overlay, Deck joint Cost: $18.6 M Adv: Dec. 2005
Caltrans District 4 Marin 101 HOV Gap Closure Central San Rafael Mrn 101 HOV Widening Central San Rafael Cost $42.5 M Adv: Oct. 2005
Caltrans District 4 East Blithedale Off Ramp N U1 Mrn 101 E. Blithedale Off Ramp Cost $5.8 M Adv: Feb. 2006
Caltrans District 4 Napa 29 St. Helena Roadway Rehabilitation Napa 29 Pavement Rehabilitation Cost: $4.7 M Adv: Sept Rehabilitate Roadway : Curve Improvements Super elevation Correction Shoulder Widening Drainage Modification Digout and AC Overlay N 29 St Helena Project Limit – York Creek Bridge Project Limit – Bale Lane
Caltrans District 4 Sonoma 101 HOV Widening Route 12 - Steele Lane Son 101 HOV Route 12 to Steele Lane Cost: $52.1 M Adv: Sept N Route 12 / 101 I/C Ramp Modification College Ave. Bridge Replacement and I/C Modification 6 th Street New Undercrossing 4 th Street Bridge Widening Santa Rosa Creek Replace Bridge Soundwall Route 101 Widening Bicentennial Way - Earle Street OC Auxiliary Lane - Steele Lane - College Avenue Santa Rosa
Caltrans District 4 Sonoma 101 HOV Widening Steele Lane IC Son 101 HOV Steele Lane I/C Cost: $12.4 M Adv: Sept Route 101 Widening Cleveland - Edwards Avenue Steele Lane Bridge Widening Steele Lane NB On Ramp Metering Steele Lane Off Ramp Relocation Soundwall 101 N Santa Rosa N
Caltrans District 4 San Francisco, San Mateo and Santa Clara Counties Projects Devil’s Slide Tunnels SCl 680 Median Barrier SM 101 Auxiliary Lane SCl 101 Grind PCC Pavement SF 101 Presidio Viaduct SF 80 SFOBB Resurface Upper & Lower Deck
Caltrans District U1 – Overlay SFOBB Upper/Lower Deck 0105U4 SFOBB Resurface Upper and Lower Deck Cost: $25.0 Million Adv: 8/29/05 Resurface SFOBB : ¾” Polyester Deck Overlay Grind ¾” Existing Epoxy Asphalt Lower Deck - Replace 9 Expansion Joints Project Limits – YBI N 80 Project Limits – SFO SFOBB Anchorage
Caltrans District 4 SF Presidio Viaduct Rehabilitation and Repaint Rehab and Paint Presidio Viaduct Cost: $19.6 Million Adv: Dec. 2005
Caltrans District 4 SM 101 Auxiliary Lanes Auxiliary Lanes : NB and SB Auxiliary Lanes Reconstruct Peninsula OC Monte Diablo Ped. Bike OC Soundwall and Retaining Wall Drainage Improvements Project Limits – Millbrae Avenue Project Limits – E 3 rd Avenue N SM 101 Auxiliary Lanes 3rd Ave – Millbrae Ave. Cost: $74.2 M Adv: June. 2006
Caltrans District 4 Devil’s Slide Tunnels and Approach Roads 1123U1 Devil Slide – Construct Tunnels Cost: $225.0 Million Adv: Apr North Portal Bridge South Portal South Rock Cut New Roadway Tunnels Operation Maintenance Center N
Caltrans District 4 0C890 SCL 101 Grind PCC Pavement 0C8901 SCl 101 Grind PCC Pavement Cost: $19.9 M Adv: 8/15/05 Grind PCC Pavement : Grind PCC Pavement Slab Replacement AC Overlay Mainline & Ramps Fog Seal Shoulders Project Limits – San Mateo County Line Project Limits – Quadalupe River Bridge N
Caltrans District 4 SCl 680 Upgrade Median Barrier SCl 680 Upgrade Median Barrier Cost: $13.7 M Adv: Sept Upgrade Median Barrier : Replace MBGR w/ Concrete Barriers Minor Drainage Modifications Project Limits – Alameda County Line Project Limits – I 280 / 101 IC N
Caltrans District 4 Contra Costa County Upcoming projects Richmond San Rafael Bridge Benicia Martinez Bridge Antioch Bridge Carquinez Bridge CC 680 Auxiliary Lanes CC 80 Westbound HOV Lanes
Caltrans District 4 I 80 WB HOV Extension CC4 - Cummings Skyway I 80 Widening I/C Modification Auxiliary Lanes I/C Modification CC 80 Extend WB HOV SR4 - Cummings Cost: $19 M Adv: Oct. 2005
Caltrans District 4 Construct Auxiliary Lanes Diablo Road - Bollinger Canyon Road CC 680 Construct Auxiliary Lanes Cost: $15.2 M Adv: Nov Construct Auxiliary Lanes: NB And SB Auxiliary Lanes Relocate Existing Soundwalls Widening Laurel Drive UC Retaining Walls N Project Limits – Bollinger Canyon Rd. Project Limits – Diablo Road. Project Limits – Sycamore Valley Rd. Project Limits – Crow Canyon Rd. 680
Caltrans District 4 Alameda County Upcoming Projects Dumbarton Bridge San Mateo Hayward Bridge SF Oakland Bay Bridge th Avenue IC Retrofit High Street IC Retrofit I 238/580 Widening and Rehabilitation MacArthur Blvd. On Ramp Distribution Struct. Retrofit SR 84 Pigeon Pass Realignment I 580 PCC Pavement Rehab.
Caltrans District 4 Ala I 80 / 580 / 880 Distribution Structure Retrofit - Utility Corridor Retrofit I 80/580/880 Distribution Structure Cost: $13.2 M Adv: Dec. 2005
Caltrans District U4 Ala 880 – 5 th Avenue Interchange Retrofit Cost:$102 Million Adv: Aug Alameda th Avenue Interchange Retrofit Replace Existing Structure: Maintain Existing Capacity Raise Profile of New Structure Auxiliary Lane, from Oak St. Off Ramp Standard Shoulders Bike and Pedestrian Lane Lake Merritt Channel Project Limits – Oak Street Project Limits – 10 th Avenue N
Caltrans District 4 Alameda High Street Interchange Retrofit Ala 880 – High Street Interchange Retrofit Cost:$60.7 Million Adv: Sept Replace Existing Structure: Maintain Existing Capacity Reconfigure SR 77 / 42 Ave./880 IC- Partial diamond w/ at grade intersection Reconstruct Frontage Road: - Oakport Street - E. Eight Street Standard Shoulders Bike and Pedestrian Lane Project Limits - Fruitvale Avenue Project Limits-.9 km S. of High Street N
Caltrans District 4 I-238 Widening and Rehabilitation I-238/580 IC to I-238/880 IC I-238 Widening and Rehabilitation Cost: $82.4 M Adv: Jan Widening and Rehabilitation: Widen I-238 from 4 to 6 Lanes Rehabilitate I-238 with LLP SB I-880 Aux. Lane from I238/880 IC to A Street Off Ramp Widen NB I-880 to I-238 to 2-Lanes Widen NB I-238 to I-880 to 2 Lanes N Project Limits – A Street Project Limits – I-238/880 IC Project Limits – I-238/580 IC
Caltrans District 4 PCC Pavement Rehabilitation Hacienda Drive - I Ala 580 PCC Pavement Rehab Cost: $28 M Adv: 8/8/05 Project Limits – Hacienda Dr. Project Limits – I Upgrade Existing Pavement : Replace Cracked Slabs Grind All Lanes Repair Shoulders Replace Approach Slab AC Overlay Ramps Rehab Bridge Decks Install Bridge Rails N
Caltrans District 4 State Route 84 Realignment Pigeon Pass Ala 84 Roadway Realignment Cost: $21.3 M Adv: Aug Project Location Livermore Dublin Pleasanton N Roadway Realignment : Improve Horizontal / Vertical Alignment Median Buffer Current Design Standard Standard Outside Shoulder Guardrail Steep Terrain Environmental Sensitive Habitat
Caltrans District 4 Networking Network session