Contract 60X10 Informational Meeting Weber I-55

Similar presentations


Presentation on theme: "Contract 60X10 Informational Meeting Weber I-55"— Presentation transcript:

1 Contract 60X10 Informational Meeting Weber Road @ I-55
Normantown Rd. to 115th St. Will County Division of Highways Villages of Romeoville and Bolingbrook, Illinois Contract 60X10 Informational Meeting October 25, 2018 – 4:00 PM

2 OVERALL PROJECT LOCATION
NTS Rodeo Dr/Remington Blvd OVERALL PROJECT LOCATION Total length: 1.55 miles Remington Blvd/Windham Pkwy Lakeview Dr Village of Romeoville Village of Bolingbrook Will County Normantown Road

3 Contracts Overview Contract 62F12 – Advance Tree Removal Contract
Project Letting Date – 6/16/2017 Project Completion Date - 11/22/2017 – Project Completed Contract 60X10 – Main Contract Project Letting Date – 3/09/2018 – Construction Underway Project Completion Date - 8/6/2021

4 CONTRACT COSTS 62F12 – Tree Removal - $ 68,424.00
60X10 – Main Contract - $ 47,970,125.23 Totals = $ 48,038,549.23

5 Proposed Improvements
Reconstruct Weber Rd – 1.55 miles Weber Rd - 6 Lanes Reconstruct I-55 Ramps Dual Bridge Structures Interconnected traffic signals through the interchange Sidewalk and 10’ Wide Shared-Use Path Retaining Wall installation Continuous LED Roadway Lighting with 4 High Mast Light Towers Enclosed Drainage System with In-Line Detention Overhead Sign Structures Signing and Pavement Markings CCTV Cameras and Fiber-optic Connection Intersection Improvements at Normantown Rd., Rodeo Dr/Remington Blvd & Remington Blvd/Windham Pkwy

6 Proposed Improvements – Normantown Rd.
3 Through Lanes in each direction on Weber Rd. New dual left turn lanes for SB & EB traffic Right turn lanes for 3 legs of intersection

7 FENCE STONE SOUND WALLS Adjacent to Residential Areas

8 Pavement Design Weber Road Mainline PCC Pavement 10-1/4” (Jointed)
Aggregate Subgrade 12” Expressway Ramps – HMA Pavement (Full Depth), 12-1/4” Polymerized HMA Surface Crs,2” Polymerized HMA Binder 2-1/4” HMA Binder Course 8” Side Street Pavement Widening & Resurfacing HMA Surface Crs, 1-1/4” Polymerized HMA Leveling Binder 3/4” HMA Binder Course 8-3/4”

9 Who has heard of a Diverging Diamond Interchange?

10

11 Diverging Diamond Interchange – How To Drive a DDI

12 Traffic Lanes Open During Construction
Pre-Stage – Off-Peak lane closures Stage 1 – 2 lanes open each way NB & SB Weber Stage 2 – 2 lanes open each way NB & SB Weber Stage 3 – 2 lanes open each direction on Weber Stage 4 – Partial Ramp closures on I-55 for 9 days Cleanup & Punchlist – Off-Peak lane closures

13 Pre-Stage Work Median removal and temp pavement
Temporary Traffic Signals Temp Storm Sewer Utility Relocation Now to Mid-Late June 2019

14 Stage 1 Traffic on east side, Normantown to 115th
West half of Weber Rd. Reconstructed New northbound bridge constructed Ramp Reconstruction July 2019 to June 2020

15 Stage 2 Traffic on west side, Normantown to 115th
East half of Weber Rd. Reconstructed Reconstruct existing bridge deck for future southbound traffic Ramp Reconstruction June 2020 to May 2021

16 Stage 3 Traffic on new pavement, Normantown to 115th
Construct new medians Complete ramp reconstruction Complete sidewalk and multi-use-path in bridge area May 2021 to August 2021

17 Stage 4 Traffic on new pavement, Normantown to 115th
Partial I-55 exit ramp closures for 9 days requiring detours July 2021/August 2021

18 SB I-55 Exit Ramp Detour

19 NB I-55 Exit Ramp Detour