Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,

Slides:



Advertisements
Similar presentations
Update on FCPS Construction/Renovation Projects June 2009.
Advertisements

Update on FCPS Construction/Renovation Projects July 2009.
Update on FCPS Construction/Renovation Projects September 2009.
Update on FCPS Construction/Renovation Projects May 2009.
MARPLE NEWTOWN SCHOOL DISTRICT FACILITIES. Maintenance & Small Projects Planned for Summer 2007 New carpet at Worralls office New fencing at Worralls.
Update on FCPS Construction/Renovation Projects April 2009.
PM – TECHNICAL ANALYSIS WORK BREAKDOWN STRUCTURE PRESENTED BY: RASHMI TAK PGDM 09/40.
Harding Elementary School Exterior Repairs & Select Roofing Replacement 08/12/2014.
Update on FCPS Construction/Renovation Projects August 2009.
April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.
Current Project Update October 25th 2012 Good Evening!!!
Bryan Station Middle – Renovation Architect: Clotfelter-Samokar Architects General Contractor: Preston Construction Group Substantial Completion Date:August,
Progress Report 12/13/11. Progress Schedule December 2011 Work Completed December: Installed Concrete topping on roof Rough In M&E East side screen wall.
Arlington Elementary – Renovation Architect: RossTarrant Architects General Contractor: W/S Construction Substantial Completion Date:August, 2010 Contract.
October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara.
Leestown Middle – Renovation Architect: Lucas/Schwering Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 GC Contract.
SCHEMATIC DESIGN PRESENTATION
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
Facilities Modernization Program Funded by Measure B Project Report April 16, 2012.
Bryan Station Middle – Renovation Architect: Clotfelter-Samokar Architects General Contractor: Preston Construction Group Substantial Completion Date:August,
Kyle Goodyear BAE in Construction Management Pennsylvania State University Senior Thesis Presentation April 12, 2010.
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
MAIN ENTRANCE SOUTH EAST VIEW NORTH EAST VIEW.
Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.
Architect Drawing of New Entrance. Location Location of Phase II Construction Project – Old tennis courts west of the existing building.
LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.
General Contractors  Over 10 years of Service  Commercial  Military Institutions  Government Agencies  Female Owned and Operated Firm  Teamed with.
Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. April 28, 2008 Prepared by:
Board of Education Presentation 2015 Referendum Projects September 9, 2015 Update.
John F. Kennedy High School – Science Wing, Richmond, CA Progress Report POWELL & PARTNERS, ARCHITECTS WCCUSD FACILITY SUB-COMMITTEE MEETING March 12,
Progress Photos Goodnoe Elementary School Additions and Renovations Project November 2013 Goodnoe Elementary School.
Update on FCPS Construction/Renovation Projects March 2009.
Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. August 2007 Prepared by:
Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. November 5, 2007 Prepared.
Deerfield Elementary School Deerfield Elementary Overview of Deerfield Renovation October 8, 2015.
Prof Ralph V. Locurcio, PE CON 2001 CVE Sequence Single Family House - 3,000 square feet Duration 1 General Conditions 21 2 Apply for Permits.
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
F ACILITIES, P LANNING, AND C ONSTRUCTION December 14, 2015 – Monthly Construction Report.
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
Elevating the Quality of Life in the District. AFTER RENOVATION BEFORE RENOVATION.
Residential Construction Drawings
Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
October 19, 2011 Construction Progress Report. Construction Progress Report – October 19, 2011 Contract sum to date:$ 162,736,722* Total completed to.
Salmon River CSD Capital Project Phase II Monthly Status Report March & April 2016.
1 Guinn School Restoration Update Presented by Transportation and Public Works Department February 17, 2009.
Miller Driscoll Building Committee Construction Update Thursday April 7, :00 PM - 7:00 PM Presented by: Turner Construction, CMA 1 Additions & Alterations.
LIFE CYCLES OF AIKEN COUNTY PUBLIC SCHOOLS CONSTRUCTION PROJECT October 8, 2013.
April 2016 Bond / Facilities Update Presentation
Bond Oversight Committee
UPDATE ON DOE RUN ELEMENTARY CONSTRUCTION PROGRESS
Upcoming Activities Fun Fact Click here to view the live WEBCAM
Drawing Interpretation
Capital Improvements Presentation
Pinole-Hercules Water Pollution Control Plant Upgrade Project
Minuteman Vocational Technical Regional High School Progress
Progress Report 11/10/11.
Minuteman Vocational Technical Regional High School Progress
2007 Bond Issue Capital Improvement Program
Troy School District Bond Program – Series 1 Construction Update
Capital Outlay Workshop
In-Class Scheduling Exercise
Minuteman Vocational Technical Regional High School Progress
WEST ADA SCHOOL DISTRICT BOARD OF TRUSTEES UPDATE JUNE 28, 2016
Minuteman Vocational Technical Regional High School Progress
North Augusta High School – Phase 2A and 2B
Troy School District 2013 Bond Program – Series 1 Construction Update June 2016 Barton Malow | TMP.
Troy School District Bond Program – Series 1 Construction Update
EAST PENNSBORO AREA SCHOOL DISTRICT
Presentation transcript:

Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August, 2010 Contract Sum:$5,001,150 Change Orders to Date (1):$0 Current Phase:1 (On Schedule) Estimated Completion:16% July 2009

Russell Cave Elementary – Renovation Rendering of Final Façade July 2009

Russell Cave Elementary – Renovation Work Completed in Last 30 Days: Exterior concrete block walls are being installed. Interior of Kitchen/Cafeteria has been demolished and renovation has begun. Renovation of (4) classrooms on the south side has begun. Concrete slab at the new addition has been poured. Masonry restoration on the exterior of the original building in process. Existing elevator has been upgraded. Current Work Effort (July): Roof trusses at the new additional will be set. Kitchen/Cafeteria renovation will be completed. Interior work on the new addition and the (4) classrooms on the south side will continue. They are scheduled to be completed in October. Complete new electrical and mechanical systems in Kitchen/Cafeteria. July 2009

Russell Cave Elementary – Renovation New Addition July 2009 Masonry Restoration Interior of Cafeteria