Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.

Slides:



Advertisements
Similar presentations
K. Long, 18 April, 2015 Beam-line status — red sky at night?
Advertisements

Summary of MICE 4/4/2008 shift during the ISIS machine-physics period Goals for 04 Apr08 MICE shift: 1. Radiation survey in MICE Hall with target operating,
1 MICE Video Conference Installations to date Future installation work Plans for May shutdown MICO organisation Use of Technical Board.
MOM Summary 19/01/10 Water Now the ice has cleared I am able to get on the roof again. Could do with getting the conductivity readings fed back similarly.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 27, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009.
MOM Report Michael S. Zisman MICE Operations Manager Center for Beam Physics Lawrence Berkeley National Laboratory MICO March 16, 2009.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Video Conference 114 September 18, 2008.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
Spectrometer Solenoid Report and Coupling Coil Update Michael S. Zisman MICE Operations Manager Center for Beam Physics Lawrence Berkeley National Laboratory.
Linda R. Coney – 24th September 2009 MOM Update End of Sept Run Linda R. Coney 05 October, 2009.
MICO 1 st February 2010 Terry Hart (MOM). MICO 1 st February June 2015 Decay Solenoid DS will not be ready for Machine Physics. Matt Hills spent.
Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.
Spectrometer Solenoid and RFCC Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
MICE Commissioning Issues Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO Meeting—RAL.
MICO Meeting, 1 st March 2010 Terry Hart (MOM) - Decay Solenoid - Targets - DAQ - March User Runs Plans - Suggestions.
Spectrometer Solenoid Testing Update S. Virostek and M. Zisman Lawrence Berkeley National Laboratory MICO Meeting—RAL May 17, 2010.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Spectrometer Solenoid Lead Testing Update S. Virostek and Mike Zisman Lawrence Berkeley National Lab MICO Meeting January 19, 2010.
1S. Virostek - LBNL Spectrometer Solenoid Fabrication Update Vendor still expecting to complete first magnet by the end of November, before X-mas more.
Spectrometer Solenoid Testing Update S. Virostek and M. Zisman Lawrence Berkeley National Laboratory MICO Meeting—RAL June 7, 2010.
Spectrometer Solenoid and RFCC Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.
MICE Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Spectrometer Solenoid and RFCC Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Detector Systems Update MICO Feb 25, MICE Detector Systems  CKOV u CKOV installation planned during March shutdown u Cable issues resolved. Geneva.
Spectrometer Solenoids and Coupling Coils Primary Activities and Risks Going Forward Spectrometer Solenoids Completion of SS#2 magnetic mapping Completion,
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
UKNF/MICE PSAG, 3/5/11 Spectrometer solenoids: –Repair plan still ‘in approval’, already two months late –Workshop/mini review at LBNL 10 th /11 th May.
MICE Magnetic Field Mitigation Review Potential impact on ISIS of MICE Stray Magnetic Fields 24 th September 2013 Martin Hughes.
MOM Report Galina Vankova RAL, MICE Video Conference.
Project manager report paul drumm CM16 October 2006.
Linda Coney MC VC May 19, 2011 MICE Operations Manager Report.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
1M. Ellis - MICE VC - 1st November 2007 Cosmic Ray Test Preparations  The cosmic ray test was initially planned to be held in R12, but this proved to.
Technical Board and Safety Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Spectrometer Solenoid: Plans to Fix Magnet 2 Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
Target Status CM19 RAL October 2007 P J Smith – University of Sheffield.
Linda R. Coney – 24th September 2009 MOM Update Linda R. Coney 24 September, 2009.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 6, 2009.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
MICE VC Alain Blondel 1 MICE NEWS MICE VC 161 Agenda Overall schedule Magnetic field mitigation review Status of things.
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab NFMCC at LBNL January 25, 2009.
22 October 2005MICE Meeting at RAL1 Tracker Solenoid Overview Michael A. Green Lawrence Berkeley Laboratory MICE Collaboration Meeting 22 October 2005.
MICE MICO Alain Blondel 23 December MICE Commissioning needs 22 December 08.
SPOKESMAN’S UPDATE K. Long Imperial College London/STFC.
1 MICE PM Report General Update –Phase I nearing completion –MICE Power –Actions for Decay solenoid & target –Follow-ups from last VC –Conclusions MICE.
Spectrometer Solenoid Background Info Steve Virostek Lawrence Berkeley National Lab MICE Spectrometer Solenoid Review: Phone Meeting October 5, 2009.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICE Video Conference May 20, 2010.
MICE CM23 Introduction and Meeting Goals Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Malcolm Ellis – Brunel University – 8th April The International Muon Ionization Cooling Experiment.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
Spectrometer Solenoid Documents and Review Plans Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National.
MICE Operations Scenario Run 1
MICE PM Report Progress with the Infrastructure A few problems
Spectrometer Solenoid Fabrication Status and Schedule
Presentation transcript:

Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO Meeting—RAL September 15, 2008

MICO: Zisman2 Status (1) MZ, MAG, and SV visited vendor on Friday, Sept. 12 Discussed options and agreed upon plan to move forward —complete magnet 2 first, then open magnet 1 and fix it —modifications to include o improved thermal connection between stage 1 of coolers and shield o improved design of liquid He piping to minimize risk of frozen nitrogen plug –enter cold mass vessel from 7 o’clock position (now it is 6 o’clock) –enlarge He tubes to 0.5-in. –redesign manifold to eliminate low spots o generate written cool-down procedure o modify stand to eliminate interference with iron disk bracket –favored approach will make magnet stands for magnets 1 and 2 have different positions  is this an issue for interface with false floor?

September 15, 2008MICO: Zisman3 Status (2) Magnet 1 will subsequently get the same modifications —will also correct alignment errors when magnet is opened up Schedule —aim for completing magnet 2 by early November o somewhat skeptical that this will happen on time —magnet 1 should be ready about 2 months after magnet 2 Implications of schedule —it does not seem likely that magnet 2 could be run at RAL before the end of the year even if we skip magnetic measurements at FNAL o unless we can shorten the 6-week preparation time by several weeks –this potentially leads to resource conflicts with decay solenoid repair if that cannot be accomplished in October —Executive Board needs to decide priorities

September 15, 2008MICO: Zisman4 Commissioning Needs (1) Need to get Decay Solenoid power supply operating —and then begin tests of magnet o use signs and barricades if no indicator light —need DL help for this —potential to interfere with DSA roof job if we’re not careful o could do off-hours after PSU is fully operable Need to develop optics for electron beam (Tilley, Apollonio) —used for calibrating CKOV and TOFs o must extend all the way past Q9 (i.e., into the Hall) Need to extend permission to operate target parasitically during ISIS user run

September 15, 2008MICO: Zisman5 Commissioning Needs (2) Need to make beam loss measurements to compare with model calculations (Adams, Dobbs) —also need extended run at “enhanced” loss rates to determine activation effects of a given instantaneous loss rate Need to test MBS once installed —logic of interlock to ISIS needs definition o maybe already done (?) Need to incorporate key ISIS BLMs and BPMs into MICE target data stream —and eventually into DAQ stream —cables are available, but need to be connected on both ends

September 15, 2008MICO: Zisman6 Issues Need suitable lock-off on DS PSU (safety issue)...hope springs eternal o ideally, should look the same as the other big PSUs Need network access to e-log from RAL-VIS network —Gareth Smith (PPD) trying to get this sorted out —this is a real pain and MUST get fixed soon! Need to decide how to proceed with off-line target —best guess: magnetic and mechanical axes are misaligned o need to confirm this or find another explanation –it is clear that we still do not have sufficient understanding of target requirements Need to resolve need to lock Hall when target operating and MBS is closed