Management Brent Fultz California Institute of Technology Report from the Baseline Review Project Execution Plan Purpose of IDT.

Slides:



Advertisements
Similar presentations
Ad Hoc Bulk Electric System Task Force Update RPIC February 19, 2009.
Advertisements

CATIA V4 Software Deployment Project Proposal
Chapter 7: Key Process Areas for Level 2: Repeatable - Arvind Kabir Yateesh.
Project Control Techniques
Summary Role of Software (1 slide) ARCS Software Architecture (4 slides) SNS -- Caltech Interactions (3 slides)
Overview of the ARCS Project Plan: The View at One Year Doug Abernathy ARCS Instrument Scientist ARCS IDT Meeting Lujan Center, LANL September 30, 2002.
IDT Meeting Welcome Brent Fultz California Institute of Technology Broad-brush overview of Hardware, Software, Management.
Date Instrument Systems ORNL SEQUOIA Overview Garrett Granroth (Instrument Scientist) David Vandergriff (Lead Engineer) ARCS/SEQUOIA IDT meeting March.
Hardware Progress Doug Abernathy ARCS Instrument Scientist ARCS IDT Meeting Lujan Center, LANL September 30, 2002 SNS Instrument SystemsArgonne/Oak Ridge.
Baseline Review The Path of ARCS from Science to a Project Brent Fultz California Institute of Technology.
LIGO-G P LIGO Project Accounting Presentation June 27, 2000.
Interfaces with the SNS Project for the ARCS Instrument Doug Abernathy ARCS Hardware Project Manager ARCS Construction Project Review DOE Germantown Aug.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
Overview of the Schedule and Budget for the ARCS Instrument Doug Abernathy ARCS Hardware Project Manager ARCS Construction Project Review DOE Germantown.
Brent Fultz Prof. Materials Science and Applied Physics California Institute of Technology ARCS Project Inelastic Scattering Scope of Software Project.
IS&T Project Management: How to Engage the Customer September 27, 2005.
Railroad 101 Equipment April 9, Next Generation Corridor Equipment Committee  Established by Section 305 of the Passenger Rail Investment and Improvement.
@ Industrial Engineering by Bopaya Bidanda David I. Cleland.
HYSPEC Instrument: Status and Performance M. Hagen Neutron Facilities Development Division, SNS, Oak Ridge National Lab. W.J. Leonhardt and A. Ruga Condensed.
Department of Energy Review of the SNS Instruments –Next Generation (SING) Project HYSPEC Instrument: Status and Performance Mark Hagen Instrument Scientist.
The Key Process Areas for Level 2: Repeatable Ralph Covington David Wang.
New Procedures for Sourcing Public Works Construction Webinar Presentors: Richard Sawyer / GSFIC Darryl Mitchell / SPD.
Server Virtualization: Navy Network Operations Centers
Experimental Facilities DivisionOak Ridge SNS INSTRUMENTS OVERVIEW R. K. Crawford Instrument Systems Senior Team Leader September 10, 2004 HYSPEC IDT Meeting.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
Kaname Ikeda, October Status of the ITER Project Status of the ITER Project Kaname Ikeda ITER Nominee Director-General October 2006.
1 BROOKHAVEN SCIENCE ASSOCIATES Project Performance & Risk Management Aesook Byon, Deputy Project Director NSLS-II PAC Meeting February 8-9, 2011.
Deakin Richard Tan Head, Information Technology Services Division DEAKIN UNIVERSITY 14 th October 2003.
In-Kind Contribution Management Update Allen Weeks March 20, Lund.
LIGO-G M Management of the LIGO Project Gary Sanders California Institute of Technology Presented to the Committee on Programs and Plans of the.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Slide 1 6-Nov-98PHOBOS Review: Cost & Schedule Cost & Schedule S. Steadman, MIT PHOBOS Cost & Schedule Review Technical Advisory Committee BNL November.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
John Peoples for the DES Collaboration BIRP Review August 12, 2004 Tucson1 DES Management  Survey Organization  Survey Deliverables  Proposed funding.
AGS RSVP Weekly Meeting P. Pile 16 September 2004 AGS RSVP Weekly Meeting, 16 Sep 2004 AGS Project Office - status of funding, comments on RSVP
LBNE Working Group Meeting December 20, :00– 5:00 PM Snake Pit.
M. Reichanadter LCLS Project November 2008 FAC Meeting Slac National Accelerator Laboratory Report to the LCLS.
7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.
1 Zoe Van Hoover 1 User Safety: Commissioning and Early Experiments NEH ARR User Safety: LCLS NEH Commissioning and Early Experiments.
Project Management Process Transition & Closure Project Management Process Project Description Team Mission/ Assignment Major Milestones Boundaries Team.
Response to TAC8 and Annual Review Recommendations John Haines Head of Target Division April 2, 2014.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
Paul Drumm, cm10, 27 Oct 2004 MICE Project Report Paul Drumm Collaboration Meeting 10 Rutherford Appleton Laboratory October 2004.
Project Management Process
VOWTAP Progress Report VOWDA December 2, DOE Grants VOWTAP Extension No Cost Time Extension until May 31, 2016 Conditional upon achievement of two.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
APA CONTRACTS TO POST-2017 ALLOTTEES July 24 - Letter to all Allottees Inviting Comment August 10 - Allottee Response August 21 - Workshop August 28 –
23-Nov-1999STScI Projects Monthly Status Review1 of 8 SpaceTelescopeScienceInstitute COS Status Report for period December, 1998 to November, 1999 Tony.
HYSPEC IDT HYSPEC: Our Instrument at the Spallation Neutron Source. Outline Spallation Neutron Source (SNS) and the BNL Overview of the SNS instrument.
Collaborating for Quality Quality Assurance (QA) & Quality Control (QC) in the Accelerator Project (ACCSYS) Matthew Conlon ACCSYS QA/QC
DOE Review of LARP – Feb 17-18, 2014 DOE Critical Decision Process Ruben Carcagno February 17,
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
IV&V Facility 7/28/20041 IV&V in NASA Pre-Solicitation Conference/ Industry Day NASA IV&V FACILITY July 28, 2004.
Rob Connatser NSS Instrument Work Packages and XLPM.
Construction Work Packaging
Green Line Extension Project
S4 will be a “big” Collaboration:
Enterprise Content Management Owners Representative Contract Approval
Preparations for a Lehman Review
X-ray Pump-Probe Instrument
1 Zoe Van Hoover 1 User Safety: Commissioning and Early Experiments NEH ARR User Safety: LCLS NEH Commissioning and Early Experiments.
ANTICORRP ANTICORRP General Assembly Meeting Administrative update
Xoserve IX Refresh Customer Update 03/01/2019.
The Common Shielding Project
Imaging & Engineering STAP Meeting 12th-13th of April 2018
PORTFOLIO COMMITTEE ON SOCIAL DEVELOPMENT 13 MARCH 2019
NSS integrated installation plan workshop Introduction
Preliminary Project Execution Plan
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

Management Brent Fultz California Institute of Technology Report from the Baseline Review Project Execution Plan Purpose of IDT

Baseline Review March 14, 2002, Caltech First of its kind for SNS IDTs -- Technical and Management Review Jim Richardson (Chm), Steve Bennington, Collin Broholm, Richard Boyce, Jon Kapustinsky, David Lichty, Toby Perring, Frans Trouw Report from Committee received Sept, Generally very favorable. – We agree with most of the points. – We began response immediately after the review. DOE (Iran Thomas) wants a written response before Dec. 1.

Issues from ARCS Baseline Review Detectors inside vacuum Shielding Moderator poison depth Disk chopper Soller Collimators Software Plan Project management - Project Execution Plan - Memorandum of Agreement (Caltech-SNS) - Budget Authority - Role of IDT - Reporting Requirements

Proposed DOE 9/2001 9/2006

Project Execution Plan -- Now a BES Requirement Concept: Given that a project plan exists, how does it get executed? Who does what? responsibilities / authority (mostly inter-institutional, some intra-institutional) select measures of progress, approvals, funding identifies policy documents (MOA, construction standards, IP, ES&H) technical baseline for scope, cost, schedule control of changes to baseline (cost, schedule, scope)

Project Execution Plan -- Advice from IDT ARCS IDT can help on: - Milestones - Control of Changes in Cost, Configuration, Schedule - Role of Executive Committee - Close of Project ARCS IDT should know about: - Budget Authority - MOA - Contingency management

Milestones Level 2 Division of Materials Sciences and Engineering Approval Software Baseline Design January, 2003 Confirm Detector in Vacuum Design February, 2003 Place Guide Procurement February, 2003 Place Vacuum Vessel Procurement December, 2003 Begin Installation August, 2004 Software Beta Release March, 2005 Software Release 1.0 January, 2006 Operational Readiness Review April, 2006 Complete Installation September, 2006 Commissioning Completed November, 2006 End ARCS Project November, 2006

Project Schedule

Change Control Thresholds DOE MSE Div. Change Control Board Technical Changes in Key Parameters:Changes in Design Parameters m secondary flight path Not Affecting the Key Parameters: - detectors to 140 o e.g., deletion of frame overlap chopper, - guide in primary flight path switching of Fermi choppers Schedule Any Delay in Level 1 Milestone Any Delay in Level 1 or 2 Milestone Cost Any Increase in Total Project Cost Any Increase >$k 75 at WBS Level 2

Contingency Management What Is It? Best guess estimate of ARCS hardware is 10 M$ We are allowing for up to 12 M$ ARCS contingency is 20 % (calculated by summing contingencies on all 220 tasks in WBS) 20% is reasonable, but not large.

Project Execution Plan -- How is Contingency Managed? Requirement -- No carryover of funds between budget periods. Approach -- Budget everything we can within the budget period. Optimistic -- Best estimate is that we should end up 20% ahead on funds, perhaps ahead of schedule. Enlarge scope of project later. Pessimistic -- Less work completed than we thought. Descope project later. Comment: DOE expectation is on time and on budget (neither below nor above)

Project Execution Plan -- How is Contingency Managed? Problem -- Rate of spending is not arbitrary. Possibilities: - work with BES to change BA profile (issue in Review) - phased funding of detector contract - large commitments near boundaries of budget periods - launder money through subcontracts to National Labs

Role of IDT Past: IDT was essential in preparing the proposal (large group) Executive Committee: Fultz, Abernathy, McQueeney, Beyermann, Nagler?, Osborn Change Control Board: Abernathy, Fultz, McQueeney, ? Future: Later, near end of ARCS project in 2006, IDT will organize scientific program negotiate for beamtime (maybe) friendly users during commissioning, testing instrument and sample environments (Big role-- this may be 2 years)

Role of IDT Present Problem: How to engage the IDT during construction? Secure funds for sample environments Test single crystal goniometer on Pharos Use Pharos data to test ARCS software (maybe with LRMECS, HRMECS, Mari, MAPS) Sign in CCCP Restaurant: “It is an insult to tip the waiter” (bribe the IDT) Waiter: “Go ahead sir, insult me.”

Project Closure Readiness Review in Early 2006 (safety) Transition of Documentation Transition to Operations Expect a role for IDT during commissioning Software Release for ARCS Report Lessons Learned ARCS project ends when money ends -- Nov. 2006

Post – Project Role of IDT in formulating inelastic PAC Expect a Big role for IDT during commissioning Software Distribution to SEQUOIA, CNCS Hardware maintenance by SNS both spectrometer and sample environment equip. Doug will be at Oak Ridge Software maintenance by SNS maintain open-source coalition

Summary and Request for Comments PEP in draft form — comments needed soon. key parameters, change control thresholds, contingency management, milestones close of project, Present and future of IDT? executive committee membership, commissioning, beamtime allocation, other funds