MICE VC 15/3/07Chris Nelson MICE Hall. Issues Realistically, I would expect D2 drawings to go for tender by end next week 23/3 but I hope we can use same.

Slides:



Advertisements
Similar presentations
Software for Quantity estimation and Project management.
Advertisements

Spectrometer Solenoid Update Steve Virostek - LBNL MICE VC 150 August 23, 2012.
Attending International Exhibitions :  International exhibitions attended :  Achema 2009 : o Country name : Frankfurt, Germany o Booth Number : 5.1 stand.
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
MICE: Hall Infrastructure Chris Nelson CEng CM15 8 th June 2006.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
June 26, 2009TLH, NFMCC Friday Meeting1 MICE Updates MICE News Overview ISIS and MICE Schedules DAQ Review Spectrometer Update Aspirational Schedule Terry.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
Technical Coordinator’s Report (KL for PD) Solenoid problems & Schedule Actions on –KL/CN: plan for work to December shutdown –KL/CN: plan for work in.
AFC engineering group meeting on the 26 th of Jan 2004 MICE Absorber Focus Coil work schedule for the next 6 months By Wing Lau, Oxford.
Downstream PID Review Alan Bross MICE CM 16 October 8, 2006.
K. Long, 12 June 2015 Project manager report WBS revision Technical Board Membership Meetings.
MICE: Hall Infrastructure Chris Nelson CEng CM16 8 th Oct 2006.
128 April 2008 Spectrometer Solenoid Fabrication Update MICO Meeting 19 May 2008 S. Virostek, M. Zisman LBNL.
Upstream PID Review Alan Bross MICE CM 16 October 12, 2006.
K. Long, 16 June, 2015 MICE Muon Beam. Beam line and decay solenoid: Pressure reducing valves: Fitted to Q7—9; To be fitted to Q4—6 Upstream MLI: Plan.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
Spectrometer Solenoid Update Steve Virostek - LBNL MICE Video Conference #129 February 25, 2010.
1 MICE Radiation Shutter Description Present status Plans, schedule and remaining work MICE CM26, 24-27th March, 2010.
MOM - M.ApollonioMICO meeting - RAL - 17/3/20081 NEXT steps + proposed aims Today - START Cherenkov INSTALLATION (?) Tuesday 25 MARCH - MICO Meeting (?
1S. Virostek - LBNL Spectrometer Solenoid Fabrication Update S. Virostek and M. Green are visiting vendor today for progress update Vendor expects to complete.
K. Long, 27 June, 2015  Target K. Long, Monday, 06 July 2009.
UK Funding PPRP Meeting on Monday 30 th June Accepted need for urgent work this year –no discussion on this –but also no indication of the level of funds.
Integration March 18, 2004 Latest MICE integrated lattice layout Edgar L.Black IIT.
Spectrometer Solenoid Tech Board Schedule Discussion
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
Spectrometer Solenoids and Coupling Coils Primary Activities and Risks Going Forward Spectrometer Solenoids Completion of SS#2 magnetic mapping Completion,
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
MICE MICO September ‘07 Chris Nelson. Beamline and Hall Shielded area virtually complete –SW corner –Replacement West wall concrete ordered, corner pieces.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
1 Beamline 1. Beamline Target/Misalignment problem 2. Magnet measurements 3. Everything that’ critical and outstanding – eg d/str beamline monitors final.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 6, 2009.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
WEEK 1 You have 10 seconds to name…
Hall clearance completed Revisiting Water & Cryo Plant Prepare for shutdown ’04 –beam tube –Contract hole cutting Negotiating with DF to help target work.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
Available Review Cycles Tokyo to Vienna Assumptions: ExC Review limited to 5 days Specification submitted for QR by 11/2 Editing/Integration limited to.
Status of Anti project. F. Raffaelli,A. Checchetti,C. Capoccia. INFN CERN, July 14 th, Status of the Anti construction test and schedule. -Status.
VC117 February 2009Jean-Sébastien GraulichSlide 1 MOM Report o Yagmur Torun ( June 15 - July 14) o J.S. Graulich ( July 13 - August 7) Jean-Sebastien Graulich,
MICE VC Alain Blondel 1 1. MOM is now Victoria 2. Linda Coney is new MICE Online Group coordinator (rep Jean-Sebastien) May we held.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
Work Organisation for Splice Consolidation Francesco Bertinelli 20 minutes presentation, 10 minutes discussion: 12 slides First LHC Splice Review, CERN,
WBS ? Proposed by IPRP … –Preparation for a review –MICE Costs & Time Scales need to be more accurate & Justified –Technical Leaders arranged by technology.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
Status of MICE RF for Step V’ (at LBNL) Derun Li Lawrence Berkeley National Laboratory December 6, 2014.
MICE Coupling Coil Vacuum Vessel Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
MI/RR Shutdown 2012 Dec Gev Lines/Injection region: Staging equipment, cleaning and prepping new part to start vacuum work. Preparing to modify the.
Step IV Step IV extended through 2016 QP/QD – in progress at FNAL Target dates SSU ECE for Feb now only 20% probability – no-field Feb Remainder for April/March.
Hydrogen System Update
MICE CM31 Schedule summary
Spectrometer Solenoid Fabrication Status and Schedule
Project Management
Project Management
Project Management
Project Management
Why School Should Be Shortened
BSBWOR301 Organise personal work priorities and development

Draw dots using 2 colors to find the “Make 10” fact.
Thing / Person:____________________ Dates:_________________
Presentation transcript:

MICE VC 15/3/07Chris Nelson MICE Hall

Issues Realistically, I would expect D2 drawings to go for tender by end next week 23/3 but I hope we can use same manufacturer as D1 hence eliminate tender time – back on schedule. Realistically, Quad stand drawings to go for tender by end week following 30/3 The solenoid prep for vacuum work I have proposed for 21/22 March. This allows just enough time to prepare. Hence nose repair hopefully complete by 22nd Trolley weld now complete The plinth is out for tender, I expect to get quotes by end this week, so will achieve date in schedule of placing order by 30/3 latest.