Available Review Cycles Tokyo to Vienna Assumptions: ExC Review limited to 5 days Specification submitted for QR by 11/2 Editing/Integration limited to.

Similar presentations


Presentation on theme: "Available Review Cycles Tokyo to Vienna Assumptions: ExC Review limited to 5 days Specification submitted for QR by 11/2 Editing/Integration limited to."— Presentation transcript:

1 Available Review Cycles Tokyo to Vienna Assumptions: ExC Review limited to 5 days Specification submitted for QR by 11/2 Editing/Integration limited to 10 days This means that some specifications could achieve a V2.0 status Cycle 1 Cycle 2 Cycle 1 Cycle 2 Cycle 1 Cycle 2

2 Review Cycles Available to Vancouver (Aggressive Schedule to Achieve V1.0 Vancouver) V1.0 Assumptions: ExC Review limited to 5 days Specification submitted for QR by 11/2 Editing/Integration limited to 10 days Cycle 1 Cycle 2

3 Review Cycles Available to Geneva (Schedule to Achieve V1.0 at Geneva) V1.0 Assumptions: ExC Review limited to 5 days Specification submitted for QR by 12/27 Editing/Integration limited to 10 days Cycle 1 Cycle 2

4 Review Cycles Available to Vienna (Schedule to Achieve V1.0 at Vienna) V1.0 Assumptions: ExC Review limited to 5 days Specification submitted for QR by 12/27 Editing/Integration limited to 10 days Cycle 1 Cycle 2

5 Infrastructure Deliverables-Worst Case March April 1 st QR Review Vancouver-Editing & Integration May Conduct Review Process Nov- January February ExC Review Public Review Conduct Edit & Integration Process 12……………14 21 28 7 14 21 28 7 14 21 28 7 14 21 28 7 14 21 28 6 weeks 2nd QR Review ExC Review London - XML-One Public Review 6 Weeks Vienna Geneva- Editing & Integration 6 Weeks


Download ppt "Available Review Cycles Tokyo to Vienna Assumptions: ExC Review limited to 5 days Specification submitted for QR by 11/2 Editing/Integration limited to."