ASSIGNMENT 1 Model Answers. Question 1 Q1) Consider building a garden shed project, which involves designing the shed, figuring out what materials are.

Slides:



Advertisements
Similar presentations
Gantt Chart.
Advertisements

WBS: Lowest level OBS: Lowest level
USING MS PROJECT Project management software programs such as Microsoft Project can be used to compute the earliest and latest start and finish times and.
EGR Defining the Project Step 1:Define the project scope Step 2:Establishing project priorities Step 3:Create the work breakdown structure Step.
WEEK 4 Introduction to Project Management 1. Communication Plan Objectives Objective is to determine: ◦ Who needs to know what? ◦ How will they be told?
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
2 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Project Management 2.
PROJECT MANAGEMENT. Outline What is a “project”? Project Management Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time.
CONSTRUCTION SCHEDULING. steps to effective time management Examine the Contract List Major Contractual Obligations Divide Project into Major Work Areas.
CPA Setting up an ICT system. A consultancy company has divided the work into a number of activities. The table below shows the details. ActivityImmediate.
P449. p450 Figure 15-1 p451 Figure 15-2 p453 Figure 15-2a p453.
Using MS Project To draw a Network diagram. Add tasks Add the 8 tasks listed for making a cup of tea. Add the duration of each –Note: MS Project doesn’t.
Mary Lou Maher University DECO2005, Semester 2, 2005 Project Management.
Chapter 11: Operations Management in Manufacturing and Service Industries Facility Layouts Managing the Production Process in a Manufacturing Company Graphical.
Project Management tools BTEC National. General planning & scheduling tools Project management software helps you manage the administration, planning.
Winter 05 Project Schedule A Gantt Chart is a means of presenting the master schedule of activities for your project –Named for Henry L. Gantt ( ),
BAR CHART Develop by Henry Gantt. Definitions Activity
USING MS PROJECT Project management software programs such as Microsoft Project can be used for developing the project schedule We demonstrate the use.
Gantt and PERT charts. Representing and Scheduling Project Plans Gantt Charts Useful for depicting simple projects or parts of large projects Show start.
CS 160: Software Engineering October 20 Class Meeting Department of Computer Science San Jose State University Fall 2014 Instructor: Ron Mak
Managing Project Scheduling. What is Project Scheduling? The process of: – defining project activities – determining their sequence – estimating their.
USING MS PROJECT 2010 Project management software programs such as Microsoft Project 2010 can be used for developing the project schedule and budget, and.
BAR CHART Develop by Henry Gantt. Definitions Activity
Project Management A project is an undertaking whereby a problem or a series of problems are solved. The project must be completed on time and within.
Lecture 5 – Gantt Chart GANTT Charts Constructing GANTT Charts
WEEK 4 Introduction to Project Management 1. Communication Plan Objectives Objective is to determine: ◦ Who needs to know what? ◦ How will they be told?
Introduction to Project Management
Lean Project Management
TA. MARAM AL-KHAYYAL NET481 MS Project Overview. Outline Introduction to project management.  Project 2007 can help you manage project time, resources,
3 - 1© 2011 Pearson Education 3 3 Managing Projects PowerPoint presentation to accompany Heizer and Render Operations Management, 10e, Global Edition Principles.
Unit 9.2_Lesson 2_CD Resource 2f_Plenary Gantt charts From the Gantt Chart answer the question.
Manipulating data. Manipulating data means: Putting it into a structure (e.g., tables in a database) Putting it into a computer model.
Objectives 4 Understand the basic concepts of project planning and control 4 Explain PERT and Timeline (Gantt) charts.
5/22/00 Models in I.E. Lecture 5 Project Management Network Models.
EGR Project Management Planning Techniques Project manager responsible for developing project implementation plan. Duties includes: Defining.
Project Management Part 5 Project Scheduling. Topic Outline: Project Scheduling Identifying relationships among activities Project network diagrams Identifying.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Welcome to MM305 Unit 7 Seminar Dr. Bob Project Management.
Information Systems System Analysis 421 Chapter 3 Managing the Information Systems Project.
Project Management Organization Scheduling 31 January.
Chapter 6: Project Time Management Information Technology Project Management, Fourth Edition Using Critical Path and MS Project 2003 Tuesday, February.
University of Southern California Center for Systems and Software Engineering MS Project Tutorial CSCI-577a Software Engineering I Fall 2008 Itti Charoenthongtrakul.
Irwin/McGraw-Hill  The McGraw-Hill Companies, Inc Project Scheduling IENG 321 IENG 321.
Orthographic Drawings
Project Management Planning Techniques
Scheduling and Budgeting Engineers Without Frontiers CEE 402.
Managing the Information Systems Project Cont’d
Scheduling Scheduling : is the process of converting a project action plan into an operating time table. Why scheduling ? To answer the following questions:
Animation of a planning
Introduction to Project Management
Gantt Chart Presentation Name Course Name
Learning Objectives When you complete this chapter, you should be able to : Identify or Define: Work breakdown structure Critical path AOA and AON Networks.
Fall 06 ECE 361 Project Schedule
Project scheduling Precedence diagram method Project Management
Hospital Establishment
Creating team solutions
Project scheduling Precedence diagram method Project Management
Project management.
Project Scheduling Chapter 14.
Gantt Charts.
Tools for project scheduling.
PLANNING ENGINEERING AND PROJECT MANAGEMENT
Assignment #3 Group 3.
Making a cake.
Project Management: A Managerial Approach
Gantt Chart.
Planning assignment in MS-Project
In-Class Scheduling Exercise
Building a Car.
Presentation transcript:

ASSIGNMENT 1 Model Answers

Question 1 Q1) Consider building a garden shed project, which involves designing the shed, figuring out what materials are needed, ordering or purchasing the materials, and putting together the various parts. Some of these tasks depend on the others, some must be scheduled a. develop a table showing each task, preceding events and expected duration. b. Draw the Gantt chart of the activities using any CASE tool.

The answer of Question 1 (a) TasksPreceding events Expected Duration 1. Design the shed-1 day 2. Preparing Materials18 days 2.1. Develop Materials List11 day 2.2. Order Materials11 day 2.3. Deliver Materials2.1, 2.27 days 3. Constructing shed parts2.36 days 3.1. Pour Foundation2.31 day 3.2. Build frame3.12 days 3.3. Install roof3.22 days 3.4. Install siding3.21 day 3.5. Finishing3.31 day

The answer of Question 1 (b) Gantt Chart: (using EDRAW MAX Software)

Question 2

The answer of Question 2

The answer of Question 2 [cont.]