BSC Cable Trays … again: Evaluation of an LLO Proposal for an Alternative Design G1200110-v31.

Slides:



Advertisements
Similar presentations
Levolors New Size-In-Store Blind Cutting Machine.
Advertisements

WP7 ATLAS ID Barrel End Services T.J.FRASER UCL Aim: Using experience gained from work on the current ATLAS SCT Barrel, attempt an improved design and.
IP Area Reconfiguration Conceptual Design Five Phases: 1.Transport (A) 2.Gas Chamber 3.Injection Chamber 4.Compressor 5.Transport (B) M. Litos July 24,
Present Procedure for cutting stuck casing on Drilling PLATFORM
Growing Fish in a Recirculating System: Advanced Teacher’s Workshop An Inexpensive Recirculating System Blan Page & PJ Waters.
The software process A software process is a set of activities and associated results which lead to the production of a software product. This may involve.
CMS ZDC Crane Emergency Payload Removal Procedures This document proposes the viability of using a portable hydraulic actuator Hand crane (Davit crane)
How to Construct a Robot Part 7: Wiring and Controller Installation Copyright © Texas Education Agency, All rights reserved. 1.
MICE Hall – South Mezzanine Jason Tarrant - STFC l Contents »Device checks with current South Mezzanine »South Mezzanine change summary »Conclusion.
Cable Restraint Proposal Current design does not work. Objective: Find an alternate way of securing the LAT cables using as much of the existing design.
Modern Systems Analysis and Design Third Edition Chapter 11 Selecting the Best Alternative Design Strategy 11.1.
Traffic Congestion Around Parking Garage #6 By: Brandon Chase, Sean Pfaff, Anthony Sebastian, Brian Zuccaro.
Dennis Coyne Excomm Jan 26, 2004
LIGO-G M Photon Calibrator DRR & CDR: Response to Reviewers’ Report Phil Willems, Mike Smith.
Copyright 2004 Prentice-Hall, Inc. Essentials of Systems Analysis and Design Second Edition Joseph S. Valacich Joey F. George Jeffrey A. Hoffer Chapter.
Sector 13 Canted Undulator Upgrade Hutch Modification Requirements ( )
SDLC. Information Systems Development Terms SDLC - the development method used by most organizations today for large, complex systems Systems Analysts.
LINAC LASER NOTCHER READINESS REVIEW August 5 th, 2014 Kevin Duel – Mechanical Support Engineer.
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
Preliminary studies for Muon shield modification to accommodate LCLS II Alev Ibrahimov December, 2010 BSY.
Improving Productivity on an SEI Level IV Project presented by Kelly Ohlhausen.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
Test Mass Discharging System (TMDS) Design Review 20 Nov 2014 Rich Abbott, Dennis Coyne, Eddie Sanchez, Calum Torrie 1 LIGO-G v1.
NCSX Vacuum Vessel Joint Design Mike Viola PPPL July 1 st, 2003.
VELO workshop, Amsterdam, april ‘00M.Ferro-Luzzi Difficulties with current mechanical design recent FEA results: to obtain sufficient stiffness of center.
Introduction to Controlling the Output Power of a Transistor Stage A load network will be designed to maximize the output power obtainable from the Mitsubishi.
MICE Integration Engineering Jason Tarrant - STFC l Contents »South Mezzanine change summary »Integration Envelope Model »A/C Move »Maus Geometry »AFC.
ATLAS Upgrade ID Barrel: Services around ‘outer cylinder’ TJF updated According to the drawing ‘Preparation outer cylinder volume reservation’
Super hospitals world class facility innovation  focus  pertinent approaches  governance.
Design Process.
Chapter 14 Part II: Architectural Adaptation BY: AARON MCKAY.
E v3 aLIGO SEI Testing and Commissioning Overall Plan
Progress Completed Order/Fabricate SS Piping for HBD Purge gas from all detectors DAQ tests Prep. for Shutdown work (open doors, move carriages, etc. Pave.
11/30/20151Robin Lafever The existing 300 K Flange This is certainly an older version but is useful to illustrate The proposed modifications.
Status of and Installation Plan for DC Gas Control System and Target Work Scheduling Meeting 4 August 2006 PSI W. Molzon, Feng Xiao.
Long Bo for LAPD Hans Jostlein10/20/2011 December 15, 2015 Long Bo for LAPD 1.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.
1 Jim Thomas - LBL A proposal to close the Grid Leak “it will never die” Yuri Fysiak, Jim Thomas & Gene VanBuren Eric Anderssen, Howard Wieman & Jon Wirth.
Proposal for the assembly of the PHOBOS ring counters (H.P. 3/20/98) I would like to propose and discuss with you an alternative layout and assembly procedure.
LAT Transport Container1 GLAST LAT Project8 September 2005 LAT Transport Container Design Review 8 September 2005 LAT Transport Container Design Review.
Chapter 11 Selecting the Best Alternative Design Strategy Modern Systems Analysis and Design Third Edition 11.1.
Easy Reach 7.0 Honda Element Packing List QtyDescriptionPacked 115ft 10ga Red Wire 16ft 10ga Black Wire 140amp Breaker 23/8 Yellow Ring Terminals 25/16.
Engineering Division 1 Phased Cone Proposal Eric Anderssen, LBNL.
Thanks to Tom Bockman, of Prescott, Arizona who created this slideshow.
Comments on Engineering talk by A. Catinaccio at Inner Tracker Engineering Meeting CERN ) Fixed length barrel layout drawing by C. Bault (Strawman.
GLAST LAT ProjectEnv Test Planning,15 March 2005 LAT System Engineering 1 LAT Thermal Vac EGSE Cabling.
Future Work: LAPPD 6cm system and device Lei Xia.
Terminal Splitters in a Cabinet December Terminal Splitters in a Cabinet The purpose of this presentation is to share our findings around the.
Russian Engineers Workshop
Mounting TPCs in SVX Dock During Phase II Tomorrow I will meet with a company engineer to update the BEAST TPC vessel design. I've attached some slides.
ATLAS ID Services Mock Up - Proposal Presented by Ian Wilmut at DESY, update from John Hill 4th May, 20101ATLAS Upgrade - RAL.
MICE Partial Return Yoke Mechanical Design
PANDA Collaboration Meeting , BINP Sergey Pivovarov.
Easy Reach 7.0 Honda Element 2003
Easy Reach 7.0 Honda Element 2003
TPC Support and Constraint TPC Support
EILERSEN The Weighing experts.
Engineering Design Process
Mastering Autodesk Revit MEP 2016
Systems Analysis and Design
Modern Systems Analysis and Design Third Edition
D7 or C1: -1: Tip-tilt B-OSEMs, D25 -2: VOPO suspension A-OSEMs, D25
Cryomodule Assembly Plan
Modern Systems Analysis and Design Third Edition
Chapter 11 Selecting the Best Alternative Design Strategy
1.11: Robot Controller.
Chapter 7 Selecting the Best Alternative Design Strategy
Modern Systems Analysis and Design Third Edition
Chapter 11 Selecting the Best Alternative Design Strategy
Modern Systems Analysis and Design Third Edition
Presentation transcript:

BSC Cable Trays … again: Evaluation of an LLO Proposal for an Alternative Design G v31

Baseline BSC Cable Tray Design Design calls for wire frame tray cut in sections, supported from the welded stiffener ring (just below the electrical feed-through ports) via custom machined brackets Tray sides are cut away in front of feed-throughs Tray proximity to feed- throughs provides strain relief (cable weight does not hang from the connector as in iLIGO) D v2 D v1 G v32

Baseline BSC Cable Tray Design Implementation at LHO on WBSC8 and WBSC6 uses a mix of custom machined brackets and use of off- the-shelf hardware Design approach is flexible enough to accommodate chamber-to- chamber differences, e.g. annulus ion plumbing interference Found location for SEI CPS Demodulation modules on extended tray supports just outboard of tray (photo would help) LHO experience? – Any problems? No – Adequate capacity? Yes – Difficulties implementing? No – Difficulty replacing conflat flange feed-throughs with tray in place? No – Difficulty removing BSC chamber door with the engine hoist? No, but the engine hoist end was modified. G v33

Alternative BSC Cable Tray Design proposed by LLO Staff G v34

Alternative BSC Cable Tray Design G v35

Alternative BSC Cable Tray Design G v36

Alternative BSC Cable Tray Design Pros – Easier installation – Easier access to the feed-throughs – Easier to route cable? – Easier to clean (will we ever clean the cable/tray?) – When cabling is disturbed, the accumulated particulates which will shower down are further from BSC door – Less expensive (iff we can re-use iLIGO tray) – Potentially allows for greater cable tray capacity (assuming no interference with Cleanroom or Work Platform, etc.) Cons – No cable restraint – 3 to 4 ft long unsupported cable lengths from feed-through to tray – Limits the positioning of the BSC Cleanroom – OK? – Interferes with Work Platform  Fatal Flaw, but see possible modifications – Interferes with BSC Cleanroom corner braces  Fatal Flaw, but see possible modification – Unsupported tray length likely too long  but see possible modification – Adds significant mass to HEPI support piers which effect dynamics  potentially fatal flaw G v37

Interference with Work Platform (D ) CROSS-SECTION G v38

Lower the tray to avoid interference with Work Platform? G v39

Reduce Unsupported Tray Length G v310

Cable Lengths OK? Cable lengths in E (corner) and E (end) are based on ½ circumference around BSC for baseline design, or 125” Alternative design adds ~113” per BSC, so ~19 ft for LBSC1 to electronics room Cable lengths margin/contingency for LBSC1 & LBSC3 is 19 ft, so length is probably OK – but with no margin Now that the specific feed- through ports have been assigned, one could look at each & every specific cable run, rather than worst case cable length G v311

Modified, Alternative BSC Cable Tray Design Possible problems: – Is ~3-4 ft. of unsupported cable length OK? Not if there is no cable restraint at feed-through – Can cable restraint be added to this design concept? Likely yes, but no design or concept in hand – Limits the positioning of the BSC Cleanroom – is this OK? Don’t know G v312

Evaluation of Modified, Alternative BSC Cable Tray Design Is the alternative proposal an attempt to solve any problem(s) with the baseline design? – Not really. Confusion about what the baseline design is. Follow- up actions: Revise BSC tray drawing set (D ) to indicate final design, as implemented at LHO Complete the drawings specifically for LLO (don’t rely upon LHO versions) and cite minimum tray size & point to BSC tray drawing set (D ) Are there any significant risks with the baseline design? – No We need a decision now (can’t wait for additional evaluation) – Decision is to proceed with the baseline design G v313