1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Beam Position Monitor System Om Singh Instrumentation Group Leader ASAC Review - October 22-23, 2009.

Slides:



Advertisements
Similar presentations
New Radiation Safety Interlock System for the SPring-8 Accelerator Complex C. Saji, M. Toko, T. Matsushita, R. Furuta, H. Hanaki, S. Hashimoto 1), Y. Hashimoto,
Advertisements

Muon Tracking FEE R.E. Mischke Los Alamos 10 September, 1999 presentation to the PHENIX Muon Arm Technical Advisory Committee.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Shielding Workshop S. Buda Personnel Protective Systems March 27, 2007.
Mark Heron Diamond Light Source Oct 2007 EPICS EPICS Interface to the Libera Electron Beam Position Monitor.
Progress of the sub-harmonic bunching system (i.e. upgrading progress of BEPCII present bunching system) Pei Shilun for the SHBS team Accelerator center,
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring - Conventional Facilities Interfaces Erik Johnson, Accelerator Systems Interface Manager Accelerator Systems.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II ASAC-2007, April. 23, 2007 Injection System with a Booster in Separate Tunnel T. Shaftan for the NSLS-II team.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
Bob Lill FAC meeting Cavity October 30, 2007 LCLS Cavity BPM Status and Testing.
Bob Lill Undulator Systems – BPM April 20, 2006 Undulator Cavity BPM Status and Plans.
Bob Lill Undulator Cavity BPM System April 16, 2007 Undulator Cavity BPM Status.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Accelerator Installation Plan Gregory Fries Project Engineer, Accelerator Systems Division CFAC Review of NSLS-II.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Stability Workshop April , 2007 NSLS-II Electrical Systems G. Ganetis NSLS-II Electrical Systems NSLS-II.
Status & operational experience of Liberas at SSRF Leng Yongbin, Yan Yingbing, Zhou Weimin, Chen Yongzhong Ye Kairong, Yuan Renxian, Zou Yi, Yu Luyang,
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
ERL Differential Current System Status Peter Cameron with contributions from Michelle Wilinski and Christophe DeFrance (Bergoz) 17 Sep 07.
Power Supply Controller Architecture
1 BROOKHAVEN SCIENCE ASSOCIATES LBT Diagnostics Installation Update Dan Padrazo Diagnostics & Instrumentation Group Feb 1, 2012.
1 BROOKHAVEN SCIENCE ASSOCIATES Commissioning Plans F. Willeke 9 th ASAC Meeting for NSLS-II Project February 1-2, 2012.
1 BROOKHAVEN SCIENCE ASSOCIATES Vacuum Systems H.C. Hseuh, Vacuum Group Leader 8 th ASAC Meeting for NSLS-II Project May 10-11, 2011.
1 BROOKHAVEN SCIENCE ASSOCIATES Preparations for Linac Commissioning Ray Fliller, Associate Physicist 8 th ASAC meeting for NSLS-II Project May 10-11,
Electronics for PS and LHC transformers Grzegorz Kasprowicz Supervisor: David Belohrad AB-BDI-PI Technical student report.
Beam Instrumentation for Orbit Stability I. Pinayev.
Characterization of Fast Orbit Feedback System Om Singh, APS, ANL NSLS-2 Beam Stability Workshop BNL, April 18-20, 2007.
Characterization of NSLS2 Storage Ring Beam Orbit Stability Weixing Cheng #, Kiman Ha, Joe Mead, Boris Podobedov, Om Singh, Yuke Tian, Li-hua Yu NSLS-II,
Fast Orbit Feedback - BPM to PS Yuke Tian Control Group, Accelerator Division Photon Sciences Directory Brookhaven National Lab EPICS Collaboration Meeting,
SR Vacuum Systems and Front Ends
BPMs and HOM-BPMs for the XFEL Linac N. Baboi for the BPM and the HOM teams (DESY, CEA-Saclay, SLAC, FNAL, Cockroft/Daresbury) XFEL Linac Review Meeting,
1 BROOKHAVEN SCIENCE ASSOCIATES Instrumentation Progress Om Singh Instrumentation Group Leader ASAC Review – October, 14-15, 2010.
Introduction to collimators Integration of BPM Mechanical design Electrical design Processing Simulations Results Conclusions & Outlook.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS II: the Accelerator System Briefing Conventional Facilities Advisory Committee May 8 - 9, 2007 Satoshi Ozaki Director,
1 BROOKHAVEN SCIENCE ASSOCIATES EFAC Review – May 11, 2007 S. Sharma NSLS-II Frontends and Canted Wigglers Options Sushil Sharma.
1 BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnet and Girder Integration Lewis Doom, NSLS-II Project National Synchrotron Light Source II (NSLS-II) will.
BI day 2011 T Bogey CERN BE/BI. Overview to the TTpos system Proposed technical solution Performance of the system Lab test Beam test Planning for 2012.
BPM System Status P. Cameron 13 Aug 07. Outline 1.Notes from NSLS-II Design Review (last Thursday) 2.System Block Diagram 3.Process Variables 4.DAQ status.
BROOKHAVEN SCIENCE ASSOCIATES 0 Top-Off Safety Yongjun Li ASAC Meeting October 22, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES Diagnostics & Instrumentation Om Singh - Group Leader 8 th ASAC Meeting for NSLS-II Project May 10-11, 2011.
1 BROOKHAVEN SCIENCE ASSOCIATES Installation & Integrated Testing Status & Plans Gregory Fries, ASD Project Engineer 9 th ASAC meeting for NSLS-II Project.
1 C. Simon CLIC Instrumentation workshop BPM C. Simon on behalf of the Saclay’s group CLIC Instrumentation workshop 2 nd - 3 rd June.
1 BROOKHAVEN SCIENCE ASSOCIATES Integrated Testing George Ganetis Integrated Testing ASAC Review October 14-15, 2010.
1 BROOKHAVEN SCIENCE ASSOCIATES Redundancy Requirements for Critical Devices R. Casey August 8, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Commissioning Samuel Krinsky-Accelerator Physics Group Leader NSLS-II ASAC Meeting October 14-15, 2010.
G5 Beam Instrumentation D. Gassner, E. Pozdeyev 4-09.
1 BROOKHAVEN SCIENCE ASSOCIATES Stability Issues NSLS-II PAC Meeting May 24, 2007 S. Krinsky.
The ATF Damping Ring BPM Upgrade Nathan Eddy, Eliana Gianfelice-Wendt Fermilab for the ATF Damping Ring BPM Team.
1 BROOKHAVEN SCIENCE ASSOCIATES ASAC Meeting NSLS-II Project July , 2008 G. Ganetis Power Supplies & Electrical Utilities ASAC Meeting National Synchrotron.
Experience Fabricating the Storage Ring Vacuum Chambers for NSLSII
Updated Overview of Run II Upgrade Plan Beam Instrumentation Bob Webber Run II Luminosity Upgrade Review February 2004.
1 BROOKHAVEN SCIENCE ASSOCIATES Power Supply Status George Ganetis Power Supply Status ASAC Review October 22-23, 2009.
Low Energy RHIC e - Cooling 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity.
Overall Layout 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity.
1 BROOKHAVEN SCIENCE ASSOCIATES Injector Status Timur Shaftan, Injector Group Leader 9 th ASAC meeting for NSLS-II Project February 1-2, 2012.
1 BROOKHAVEN SCIENCE ASSOCIATES Open-Source Distributed Deterministic Device Control Larry Doolittle Alex Ratti Bob Dalesio.
ATF DR BPM Upgrade Janice Nelson, Doug McCormick, Justin May, Andrei Seryi, Tonee Smith, Mark Woodley.
Overall Layout 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity Booster Cavity and Gun move (next slide)
S. Smith LCLS Facility Advisory October 12, Beam Position Monitors Facility Advisory Committee October 12, 2006.
LEReC BPM Status P. Cernigla, R. Hulsart, R. Michnoff, Z. Sorrell June 2, 2016.
Status of CEPC Beam Instrumentation Study Ma Huizhou On behalf of CEPC BI Group Beijing, China
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
Linear and Nonlinear Lattice Correction Via Betatron Phase
Controls CBETA controls will extend existing EPICS control system
GlueX Electronics Review Jefferson Lab July 23-24, 2003
Injector Performance Requirements Conventional Facilities Update
Beam Current Monitoring with ICT and BPM Electronics
Advanced Research Electron Accelerator Laboratory
Undulator Cavity BPM System Status
Undulator Cavity BPM Status
Breakout Session SC3 – Undulator
Beam Position & Charge Monitors LCLS Lehman Review July 11, 2007
Presentation transcript:

1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Beam Position Monitor System Om Singh Instrumentation Group Leader ASAC Review - October 22-23, 2009

2 BROOKHAVEN SCIENCE ASSOCIATES Outline Injector RF BPM Button Storage Ring RF BPM Button RF BPM Electronics Photon BPM

3 BROOKHAVEN SCIENCE ASSOCIATES Injector RF BPM buttons 4 Injection BPMs Qty Beam pipe dimension Cal Factor K x,K y *Peak PUE *Power level after 10 MHz BW filter Gun/ Linac340 mm cir V-13 dBm LTB Transport 540 mm cir V-13 dBm LTB Transport 140 x 90 mm182.8 V-14 dBm BTS Transport 625 x 40 mm114.4 V-10 dBm Booster2425 x 40 mm114.4 V-10 dBm Resolution Requirement 1. High charge (15nC)  30 microns 2. Low charge (0.05 nC)  300 microns Simulation shows15 mm diameter buttons will meet resolution requirement BPM electronics - commercial or in-house * Multi-bunch mode with 0.1 nC per bunch;  = 15 ps; C b = 2.5 pF Pinayev Padrazo

4 BROOKHAVEN SCIENCE ASSOCIATES Injector RF BPM buttons - continued Pinayev Padrazo Kosciuk 40x90 mm LTB beampipe 40x40 mm LTB beampipe Sensitivity and power level calculations completed 15 mm dia RF buttons assembly design in progress Completion schedule – 1 st Article 6/2010; Production 6/2011

5 BROOKHAVEN SCIENCE ASSOCIATES RF BPM TypesQty 1.Multi-Pole Chamber RF BPMs (LA)6 per cell = Total Insertion Device Chamber RF BPMs (SA)2 or 3 per ID SR RF BPMs Location in a Cell

6 BROOKHAVEN SCIENCE ASSOCIATES RF Cable Junction Box – SR Tunnel Junction box – to interconnect and to house passive components SiO2 cables buttons LMR-240 used from box to rack DellaPenna Kosciuk

7 BROOKHAVEN SCIENCE ASSOCIATES SR RF BPM Button Design – Trapped Mode Optimization Bunch Gaussian BW (  =15psec) Freq of trapped mode (r=3.5mm) Relative voltage induced I. Pinayev, A. Blednykh, P. Cameron, B. Bacha NSLS-II button geometry  7 mm dia; 16mm hor sep

8 BROOKHAVEN SCIENCE ASSOCIATES SR RF BPM Button Design – Heating Optimization FEA Thermal Simulation Kosciuk Cameron 1 st Article Unit

9 BROOKHAVEN SCIENCE ASSOCIATES SR RF BPM Buttons Procurement Status Acquisition Status for large aperture (BLA) buttons (7mm dia) First articles received and acceptance tests completed  August 09 Contract for 460 pieces awarded  Sep 2009 Production schedule  Dec 2009 – June 2010 Acquisition Status for small aperture (BSA) buttons (4mm dia) Engineering drawing, Specification, and SOW complete – Mar 2010 Contract Awarded - Apr 2010; Receive first articles – Jul 2010 Acceptance testing, go-ahead to vendor for production – Sep 2010 Order complete – Dec 2010 P. Cameron

10 BROOKHAVEN SCIENCE ASSOCIATES Resonance Modes in Multipole Chamber (3.05m) Measurement Set-up Resonance modes can reside inside or too close to BPM pass band frequency – not good Resonance Modes could effect BPM performance and requires to be suppressed or moved out of BPM band BPM Frequency Pass Band 492 – 508 MHz Blednykh Hseuh Ferreira Bacha Blednykh Hseuh Ferreira Bacha Use RF shield installed with modified NEG carriers in the ante-chamber Shield located 147 mm from beam center – away from SR Shield 500 mm long with 300 mm spacing – shifts F o to > 530 MHz Working on robust installation scheme – Review committee - 9/25/ RF Shields

11 BROOKHAVEN SCIENCE ASSOCIATES RF BPM ELECTRONICS  2/2009 – Completed evaluation of Libera, Bergoz and APS BPM electronics. Libera meets NSLS-II baseline technical requirements  4/ Shifted to evaluate other requirements - exposed several issues i. Utilizes ~10 year old Virtex-2 FPGA technology - Virtex-6 is current ii. Insufficient capability for future application software – No room to grow iii. Cumbersome to manage future upgrades – FPGA source not given to NSLS-II iv. Limited Itech support for a quick response at Brookhaven – Located in Slovenia v. AFE Crossbar switching improves drift compensation, but adds complications for TBT and fast orbit feedback data. vi. Expensive - $13,500 each (NSLS-II qty – 250)  6/2009 – Attended Libera User Workshop at ESRF – mixed responses  7/2009 – Motivated to evaluate an in-house BPM development & production  10/2009 – Planning & design in advanced stage  12/2009 – Make or buy decision finalized

12 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II RF BPM In-house Design Plan – 7/2009 Objective  Design and build in-house RF BPM’s for the Injection system and Storage Ring Development Approach  Multi-phase development  Parallel development of AFE and DFE  System Integration Testing and Analysis  Beam Test  Iterate for performance optimization  Dedicated Lab Challenges  Aggressive schedule  SR Stability Requirements  SR Resolution Requirements BPM Development Team  K. Vetter – A. DellaPenna J. DeLong K. Ha Y. Hu B. Kosciuk J. Mead – BNL Instrumentation S. Orban I. Pinayev Y. Tian

13 BROOKHAVEN SCIENCE ASSOCIATES RF BPM Prototype - Physical Architecture (7/2009) ADC Calibration BPF Fixed Point DSP + Cal Control Interface Raw Data First Turn T-B-T (10KHz) Post Mortem Raw Data Slow Acquisition ADC Clock ADC Clock ADC BPF ADC BPF ADC BPF AFE Virtex-5 FOFB DFE A B C D Memory DDR2 SDRAM AFE - Under Sampling (initial proposed concept) - Factory Calibration (gain, temperature) - Dynamic Calibration DFE - Fixed Point Digital Signal Processing, Position calculation, PU Linearization - Embedded Eventlink - Digitally Assisted AFE Calibration Factory Calibration – Remove Systematic Errors Dynamic Calibration – Remove Drift - Communication Links InterLock High Speed, Impedance Controlled Differential Connector (LVDS) Slow Data & Control Timing InterLock

14 BROOKHAVEN SCIENCE ASSOCIATES Spectrum with Calibration Duplexer  Frequency multiplex RF Signal from pickup with continuous calibration tone.  Cal tone tracks RF Signal passband Insertion Loss by virtue of Monolithic Distributed design  Currently working with vendors to optimize filter response, cost, and complexity Bessel/Gaussian 5 th -order Transitional filter (e.g Gaussian to -3/-6dB, Chebychev) under investigation for RF Signal passband Bessel, Butterworth and Chebychev response under investigation for Pilot-Tone passband RF Duplexer Theoretical Response Target Rejection = 60dB RF Signal Passband Cal Tone Passband K. Vetter

15 BROOKHAVEN SCIENCE ASSOCIATES Calibration Concept #1 - (Out-of-Band Pilot Tone via RF Duplexer) Benefits Continuous Real-Time Calibration No perturbations to signal path Inherent Built-In Test dB Gain Balance Required for 200nm k=10mm K. Vetter In-Tunnel hardware

16 BROOKHAVEN SCIENCE ASSOCIATES RF BPM Prototype Development Plan (7/2009) AFE DFE Beam Test

17 BROOKHAVEN SCIENCE ASSOCIATES RF BPM Development Status – 10/2009 Started RF BPM development – July 2009 RF BPM architecture in mature stage (next slide) DFE Board Schematic 90% complete. Board layout to begin this month 1-month ahead of schedule Developing Requirements for custom RF Duplexer - Complete in November 2009 ADC Evaluation started. Evaluating performance of four Candidate ADCs RF BPM Thermal Analysis started Highly desirable to have passive cooling (no fans) Take advantage of the temperature control rack capable of ±0.1°C stability Establish convective heat transfer coefficient inside the rack via accurate FEA study. With accurate boundary conditions and preliminary board layout, predict operating temperatures of FPGA and other electronic components. Start AFE layout in December 2009 Preliminary chassis layout in advance stage – more later Power supply requirements 85% complete RF BPM Development space – Lab acquired; Test equipment procurement in progress K. Vetter

18 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II RF BPM Architecture – 10/2009 Bandpass Sampling 16b ADCs Sample Rate ~ 113MHz Xilinx Virtex-5 10KHz 10Hz Embedded PC with Linux OS Embedded Floating-Pt coprocessor Embedded EventLink 128Mbyte DDR2 Active Calibration for long- term drift Factory Calibration to remove systematic errors DFE platform adaptable to other NSLS-2 applications

19 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II BPM Mechanical Concept Same chassis as Power Supply Interface (PSI), PS Regulator Module, and Cell Controller Same chassis as Power Supply Interface (PSI), PS Regulator Module, and Cell Controller SFP Communication Ports RF SMA Connectors Triggers Modular Approach - separate AFE, DFE DFE AFE Kosciuk Orban Tian Kosciuk Orban Tian

20 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II RF BPM Electronics Schedule – 10/2009

21 BROOKHAVEN SCIENCE ASSOCIATES X-BPM Concept Invar based High stability stand Translation stages Photo Emission Type XBPM assembly B. Kosciuk P. Ilinski B. Kosciuk P. Ilinski

22 BROOKHAVEN SCIENCE ASSOCIATES 22 Typical Front End Configuration – XBPMs Shown Slow Gate Valve Photon Shutter XBPM 1 Fast Gate Valve Ratchet Wall Collimator Dual Safety Shutters Safety Shutter Collimator Collimator Fixed Aperture Mask XBPM 2 Bending Magnet photon shutter X-Y Slits Ion Pumps with TSPs Ion Pump with TSP Ion Pump Lead Shield Shrama Doom Shrama Doom

23 BROOKHAVEN SCIENCE ASSOCIATES SUMMARY Injector RF button design in progress. Button delivery on schedule SR RF buttons –  Design completed including heating optimization  1 st article accepted successfully; Production delivery starts 12/2009 Resonance modes solution in progress; SR shield review held; recommendations are being evaluated NSLS-II RF BPM Electronics –  Evaluated BPM electronics  Libera meets technical requirements, but falls short in several other areas  In-house design study in progress; prototype test with beam 4/2010  Installation schedule will be met with in-house BPM electronics

24 BROOKHAVEN SCIENCE ASSOCIATES Acknowledgment B. Bacha, A. Blednykh, A. Borrelli, P. Cameron, W. Cheng, L.B. Dalesio, J. De Long, P. Ilinski, A.J. Della Penna, L. Doom, M. Ferreira, G. Ganetis, W. Guo, H-C Hseuh, E.D. Johnson, B.N. Kosciuk, S.L. Kramer, S. Krinsky, F. Lincoln, C. Longo, W. Louie, J. Mead, S. Orban, D. Padrazo, I. Pinayev, J. Ricciardelli, G. Shen, S. Sharma, J. Skaritka, C. Spataro, T. Tanabe, Y. Tian, K. Vetter, W. Wilds, F.J. Willeke, L-H Yu

25 BROOKHAVEN SCIENCE ASSOCIATES Back up slides

26 BROOKHAVEN SCIENCE ASSOCIATES Rogue Mode Requirements - (From RF BPM Perspective) K. Vetter

27 BROOKHAVEN SCIENCE ASSOCIATES Acceptance Testing of the 5 First Article Buttons Dimensional verification and leak checking done at the vendor’s facility. The following acceptance testing completed at BNL 1.Vacuum Group - leak check, bake, leak check – <2* std.cc/sec 2.Central Shops - dimensions verified using CMM (coordinate measuring machine) 3.Diagnostics Group Capacitance – ~4pF, divided evenly between button and feedthru (one assembly shipped without buttons to permit this measurement) Contact insertion and withdrawal force Leakage resistance and voltage holdoff VSWR Trapped mode frequency (avoid the RF harmonics) and Q Thermal response to button heating In addition, Central Shops sectioned one assembly (wire EDM) to permit inspection of internal construction details.

28 BROOKHAVEN SCIENCE ASSOCIATES Button Assembly 001, and Test Fixtures trapped mode frequency measurementSMA contact insertion force measurement Bacha Cameron Kosciuk