1 BROOKHAVEN SCIENCE ASSOCIATES LBT Diagnostics Installation Update Dan Padrazo Diagnostics & Instrumentation Group Feb 1, 2012.

Similar presentations


Presentation on theme: "1 BROOKHAVEN SCIENCE ASSOCIATES LBT Diagnostics Installation Update Dan Padrazo Diagnostics & Instrumentation Group Feb 1, 2012."— Presentation transcript:

1 1 BROOKHAVEN SCIENCE ASSOCIATES LBT Diagnostics Installation Update Dan Padrazo Diagnostics & Instrumentation Group Feb 1, 2012

2 2 BROOKHAVEN SCIENCE ASSOCIATES Acknowledgements Om SinghTimur Shaftan Igor PinayevKurt Vetter Bernie KosciukYong Hu Ray FlillerSergei Seletskiy Dick HseuhTony Caracappa Mike Johanson

3 3 BROOKHAVEN SCIENCE ASSOCIATES Overview  Diagnostics Technical Support for Installation  Diagnostics for Linac To Booster Transport Line  Integration Model of LBT.  Illustration of LBT Diagnostics Part 1 & 2.  Illustration of LINAC BPM / PUE.  Installation of LBT Diagnostics Part 1  Integration of LBT Diagnostics Part 1  Electronics, Racks, Controls Interface  Injector Diagnostics Installation Schedule  Summary / Status

4 4 BROOKHAVEN SCIENCE ASSOCIATES Diagnostics Technical Support for LBT Installation Group Leader – Om Singh Project Engineer – Dan Padrazo Project Engineer- Bernie Kosciuk Engineer – Bel Bacha Engineer – Tony Caracappa AP – Igor Pinayev AP - Sergei Seletskiy Technical Supervisor- Wayne Rambo Technical Support – Jack Tallent, Chris Danneil, Marshall Maggipinto, Artie Munoz, Al Borelli, Dennis Poshka,George Stenby(MOU), Dave Tupper(JS), Bill Brannigan(JS)

5 5 BROOKHAVEN SCIENCE ASSOCIATES Diagnostics Supported for (LBT / LINAC) Monitor TypeTotal QTY Part-1 QTY Part-2 QTY ResolutionMeasured Beam Parameter FCT211.6pC/bunchFill Pattern, Bunch Charge ICT211.6pC/trainInjected Bunch Charge, Efficiency BPM- (LA) 1130µBeam Position BPM- (SA) 52330µBeam Position Energy Slit11Beam Energy Spread Flag- LA- (40mm x 90mm) 22OTR-50µ YAG- 30µ Energy Spread, Beam Size, Position Flag-SA- (40mm) 752OTR-50µ YAG- 30µ Beam Size, Position Faraday Cup22.05-22nC Gross Charge per Train(0-150 Bunches) BPM – (LINAC)5Beam Position

6 6 BROOKHAVEN SCIENCE ASSOCIATES Integration Model LBT Part 1 & 2 LBTL-Part 1 LBTL-Part 2

7 7 BROOKHAVEN SCIENCE ASSOCIATES 2 Part 1 Diagnostics Monitor TypePart 1 QtyIdentification BPM-(SA)2LB-P1, LB-P3 BPM-(LA)1LB-P2, Flag-SA5LB-VF1, LB-VF1BD1, LB-VF2BD1, LB-VF3BD1, LB-VF3 Flag-LA2LB-VF2, LB-VF1BD2 FCT1LB-FT1 ICT1LB-IT1 Energy Slit1LB-SL1 Faraday Cup2LB-FC1BD1, LB-FC2BD2 Illustration LBT Diagnostics-Part 1

8 8 BROOKHAVEN SCIENCE ASSOCIATES Illustration LBT Diagnostics-Part 2 2 Part 2 Diagnostics Monitor TypePart 2 QtyIdentification BPM-(SA)3LB-P4, LB-P5, LB-P6 Flag-SA3LB-VF3, LB-VF4, LB-VF5 FCT1LB-FT2 ICT1LB-IT2

9 9 BROOKHAVEN SCIENCE ASSOCIATES BPM Supported in LINAC LIN-P1 LIN-P2 LIN-P3 LIN-P4 LIN-P5 LINAC BPM

10 10 BROOKHAVEN SCIENCE ASSOCIATES LA BPM Assembly 11-12-11 SA BPM Assembly 11-12-11 LA BPM Chamber- populated w/Button Feed-thru Assembly (11-12-11) TL Button/Feed-thru assembly 11-15-11 Pre-Installation Work (LBT-BPM Chamber/PUE) Fixture using single wire test 40mm x 90mm Elliptical

11 11 BROOKHAVEN SCIENCE ASSOCIATES Pre-Installation Work (Testing Energy Slit/ Flags) Test Rack used for Diagnostics Electronics and Controls. Test Stand using SP-1005 Girder top for SA Flag testing (11-23-11) Energy Slit & LA Flag mounted on Production Version SP-1006 Girder, captured in portable clean room (11-4-11)

12 12 BROOKHAVEN SCIENCE ASSOCIATES Pre-Installation Work (FCT/ICT) In-Flange Bergoz FCT- Cleaned and prepared for install. FCT-CF6”3/4-96.0-UHV-20:1-H FCT-Test Fixture for Pre test prior to install In-Flange Bergoz ICT – Cleaned and prepared for install. ICT-CF6”-60.4-UHV-070-20:1-H Beam Charge Monitor Chassis BCM-IHR Module

13 13 BROOKHAVEN SCIENCE ASSOCIATES Tunnel Installation Work (LBT Part 1 & 2) LBT Girder Install Part 1(11-7-11) LBT Component Install Part 1(1-4-12) LBT Part 2 Diagnostics Cables Pulled (12-6-11) LBT Part 2 (11-30-11)

14 14 BROOKHAVEN SCIENCE ASSOCIATES Cable Description / Specification  LMR-240FR – Low Loss Coax Cable (RF BPM / ICT)  Attenuation (db/ft).057db @500Mhz  Jacket Diameter.240”  Custom trim to relative timing specification of +/-25pS, with a delta phase specification of 4.5 degrees @ 500Mhz.  LMR-400FR – Low Loss Coax Cable (RF BPM / FC)  Attenuation (db/ft).028db @500Mhz  Jacket Diameter.400”  LMR-900FR – Low Loss Coax Cable (FCT)  Attenuation (db/ft).014db @500Mhz  Jacket Diameter.900”  SIO2 – Silicon Dioxide Low Loss Coax Cable (RF BPM)  Attenuation (db/ft).06db @500Mhz  Jacket Diameter.141”  Semi-Rigged, fired glass hermetically sealed assembly  Commercially fabricated as a straight length and a relative timing specification of +/- 25ps, with a delta phase specification of 4.5 degrees @ 500Mhz

15 15 BROOKHAVEN SCIENCE ASSOCIATES BPM Cable Work LMR-240FR Cable install (11-8-11) Pneumatic Crimp tool Mobile Cart for Cable Time / Terminate (1-10-12) SIO2 Cable Assembly (1Meter)

16 16 BROOKHAVEN SCIENCE ASSOCIATES BPM / PUE / PTC Module Installation LINAC PTC Module Install (11-8-11) Patch Panel Interface to PTC for LINAC LBT-P1 BPM SA Chamber Assembly at SP-1002 Girder w/SIO2 Cables Installed 1-20-12 LIN-P5 BPM PUE Assembly w/LMR-240FR Cables (1-15-12)

17 17 BROOKHAVEN SCIENCE ASSOCIATES LBT Flags Installation SA Flag Assembly at SP- 1005 Girder LA Flag Assembly at SP-1006 Girder Tunnel patch panels for flag Pneumatics / PLC / Controls Tunnel patch for Energy Slit / Flag at SP-1006

18 18 BROOKHAVEN SCIENCE ASSOCIATES LBT Beam Dump / Faraday Cup Install Dump 1 at SP-3000 Girder (1-20-12) Dump 2 at SP-4000 Girder (1-20-12)

19 19 BROOKHAVEN SCIENCE ASSOCIATES LBT Electronics Rack Layout cPCI CPU board cPCI Acqiris digitizer

20 20 BROOKHAVEN SCIENCE ASSOCIATES PLC Controls for Flags (Rear View) Cable Route into Rack Penetrations (Top View) BPM receiver LINAC (Front View) Diagnostics Electronics / Cable Management (RG-Q) Custom patch Panel /SR for LMR Cables (Top View)

21 21 BROOKHAVEN SCIENCE ASSOCIATES Injector Diagnostics Installation Schedule

22 22 BROOKHAVEN SCIENCE ASSOCIATES  Implemented Resources loaded Work Plan  Diagnostics Component Tunnel Installation - Complete  Diagnostics Cable pull, Time, Termination - Complete  Diagnostics Electronics Install in Rack RG-Q1,2,3,4 - Complete  Post installation Diagnostics Sub-System Functional testing - Complete  System testing in progress, expected to be complete 2-13-2012 Summary / Status