January 24, 2007 Miller Road, Linden to I-75 Miller Road Project Linden Rd to I-75 INTRODUCTION John Daly, Manager-Director Genesee County Road Commission
January 24, 2007 Miller Road, Linden to I-75 Miller Road Program Lansing Highway – Ballenger Highway LLLLinden to I-75 IIII-75 to Ballenger LLLLansing Highway to Van Vleet CCCComputer sequencing of signals Linden - Ballenger Linden – I75
01/24/07 Year of Improvement Type of Improvement 1926 Hard Surface Concrete 1952 Widen to 4 Lanes 1972 Asphalt Resurf 1974 Asphalt Widening - 6 Lanes 1981 Asphalt Widening 1987 Asphalt Widening - 72' - 83' Year of Improvement Type of Improvement 1926 Hard Surface Concrete 1952 Widen to 4 Lanes 1972 Asphalt Resurf 1974 Asphalt Widening 1989 Asphalt Resurf 06 PASER: 5 06 Traffic Traffic Total project cost: $8,194,000 Linden – I75
January 24, 2007 Miller Road, Linden to I-75 FUNDING – Federal HPP Senator Debbie Stabenow and Representative Dale Kildee introduce congressional earmark funding into SAFETEA-LU Identified Miller Rd from Linden Rd to I-75 under HPP $2.4 million and $2.5 million in the bill Appropriation estimate of $4,263,000
January 24, 2007 Miller Road, Linden to I-75 FUNDING – Michigan Jobs Today Governor Jennifer Granholm announced Michigan Jobs Today Michigan Jobs Today funds cover required Local Agency (GCRC) match Allows immediate project initiation Miller Road approved for $1,065,750
January 24, 2007 Miller Road, Linden to I-75 Extra funding required STP/GCRC Federal Surface Transportation Program (STP) being applied for Needed funds: $2,375,250 –GCRC $475,050 –STP $1,900,200
January 24, 2007 Miller Road, Linden to I-75 FUNDING – Flint Township CBDA Flint Township Central Business Development Authority committed $490,000
January 24, 2007 Miller Road, Linden to I-75 Miller Road Funding Package Summary HPP, $4,263,000 MDOT (JT), $ 1,065,750 CBDA, $490,000 GCRC/STP, $2,375,250 Total Project Cost: $ 8,194,000
January 24, 2007 Miller Road, Linden to I-75 Design process approved December, MDOT approved using HPP and Jobs Today funds design project perform feasibility study Study will identify needs of the corridor Process will incorporate public input Choose best design
January 24, 2007 Miller Road, Linden to I-75 Purpose of this meeting Share information Obtain your input, ideas and concerns Identify significant needs of the corridor Help determine best design
January 24, 2007 Miller Road, Linden to I-75 Critical Dates August 24, Final plans submitted to MDOT November 2, 2007 – Bid letting Early Spring, 2008 – Start Construction October, 2008 – Project completion
January 24, 2007 Miller Road, Linden to I-75 Thank you for coming! John Daly, Manager-Director Genesee County Road Commission (810)