Presentation is loading. Please wait.

Presentation is loading. Please wait.

The Oakton Condominium Association September 12, 2017

Similar presentations


Presentation on theme: "The Oakton Condominium Association September 12, 2017"— Presentation transcript:

1 The Oakton Condominium Association September 12, 2017
Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation

2 Update on Project Design Timeline and Process Going Forward Q&A
Tonight’s Agenda Project Overview Update on Project Design Timeline and Process Going Forward Q&A 2

3 Project Overview Multimodal improvements to 22.5 miles of I-66
Median space reserved for future transit 2 express lanes in each direction from I-495 (Capital Beltway) to Gainesville (University Boulevard) Improved park and ride options with access to express lanes Shared use bike and pedestrian trails – integrated with existing trails 3 general purpose lanes in each direction HOV and transit access to express lanes 3

4 Where We Are in Design Process
July 2016 VDOT Design Concepts and RFP Summer 2017 Concept Adjustments Late 2017 Construction Start-up Activities May/June 2015 Design Public Hearings* November 2016 Partner Selected (I-66 Express Mobility Partners) TODAY October 2015 Public Information Meetings October 2016 Technical Proposals Submitted from Two Teams Including Alternative Technical Concepts (ATC’s) November 2017 Design Public Hearings June 2017 Public Information Meetings Summer Winter 2018 Environmental and Traffic Analyses of Concepts * Bike Trail Plans First Introduced

5 Right of Way ACTIVITY To Date and Beyond 2018 Outreach and letters to impacted landowners – January through June 2018 Appraisals and interviews with property owners Estimated days between appraisals and offers for properties Acquisition negotiations Key objective to minimize right of way impact on communities 200 property owners (commercial and residential) notified of access needs and surveys – March 2017 Initiated one-on-one contact with residential relocation owners – spring 2017 Survey work -- April through September 2017 Design Public Hearing – late fall 2017 5

6 NEPA and Preliminary Design
Noise Analysis Process Identify noise receptors Perform noise measurements at representative receptors along the corridor Perform noise modeling Identify impacts (is noise mitigation warranted?) Design and assess mitigation (typically noise walls) Is the wall feasible? Is the wall reasonable? Noise walls were shown in preliminary concept plans in 2015 Show preliminary noise wall locations on updated 2017 design plans Perform final noise analyses based upon design plans and updated traffic Publish final noise study results and noise wall locations in 2018 Solicit public input from benefited property owners and renters (voting process) Incorporate approved noise walls into the final road design construction plans NEPA and Preliminary Design FINAL DESIGN 6

7 Noise Walls in Your Community
If your community has a noise wall today, you will have one in the future Replacement walls will be at same height or higher than existing walls and when a wall is removed work must be continuous until replacement (240 day goal) Benefitted property owners (or tenants) will be consulted prior to any new walls being installed (voting process) 7

8 Noise Walls Sample Noise Barriers Under Construction
Sample Completed Noise Barriers 8

9 Bicycle and Pedestrian Trails
Shared use trails along I-66 that integrate with County and Park trails Near homes, the path will be on the I-66 side of the noise wall Along I-66, concrete barrier with fence will separate the trail from the roadway 9

10 Addressing Visual Aesthetics
Comprehensive Agreement calls for a sensitive approach to address aesthetic considerations and address construction impacts FAM and I-66 EMP will engage with localities and key stakeholders for input in the corridor aesthetic plan. 10

11 What to Expect During Construction
Construction start-up late 2017 within existing right of way Construction ramp-up spring 2018 Construction to take place throughout the 22.5 mile corridor for duration of project No lane closures on I-66 during peak periods Public will be kept informed through Transform66.org, social media, TV, radio, print media, roadway signage Provide advance construction information to adjacent communities and address issues of concern – Good Neighbor policy 11

12 I-66 Inside the Beltway Program
Tolling during weekdays, peak hours, peak directions beginning December 2017 Eastbound: 5:30 – 9:30 a.m. and Westbound: 3:00 – 7:00 p.m. E-ZPass required for all users; E-ZPass Flex if HOV HOV2 toll-free in 2017, HOV3 toll-free when express lanes open outside Beltway in 2022 Multimodal projects benefitting I-66 users funded by toll revenue Widening I-66 eastbound between Dulles Connector Road and Fairfax Drive-Exit 71 (approximately 4 miles) – construction begins in 2018 and open in Mid-2020 Clean Special Fuel License Plate drivers traveling alone will need to pay toll unless meeting HOV requirements 12

13 Current Concept Plans DR BUSHMAN 13 13

14


Download ppt "The Oakton Condominium Association September 12, 2017"

Similar presentations


Ads by Google