MAORY Status of the project

Slides:



Advertisements
Similar presentations
Requirements Specification and Management
Advertisements

PLATO PLATO TOU KO MEETING ‎ H. Rauer (DLR PF) H. Kinter/A. Salado (Kayser-Threde)
NGAO Team Meeting Management Peter Wizinowich May 26, 2009.
Pertemuan Matakuliah: A0214/Audit Sistem Informasi Tahun: 2007.
LSU 07/07/2004Communication1 Communication & Documentation Project Management Unit – Lecture 8.
Rev. 0 CONFIDENTIAL Mod.19 02/00 Rev.2 Mobile Terminals S.p.A. Trieste Author: M.Fragiacomo, D.Protti, M.Torelli 31 Project Idea Feasibility.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
LEONARDO TRANSFER OF INNOVATION PROJECT “MEDIA TECH: The future of media industry using innovative technologies ” No. LLP-LdV-ToI-11-CY Kick-off.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
PROJECT LIFECYCLE.
Introducing Project Management Update December 2011.
Activities and news Last meeting: 2015 CERN budget allocations as expected, now distributed on accounts Annual report done, and MTP (Medium Term Plan)
1 Global Design Effort: Controls & LLRF Controls & LLRF Working Group: Tuesday Session (29 May 07) John Carwardine Kay Rehlich.
Paul Alexander 2 nd SKADS Workshop October 2007 SKA and SKADS Costing The Future Paul Alexander Andrew Faulkner, Rosie Bolton.
SRR and PDR Charter & Review Team Linda Pacini (GSFC) Review Chair.
BSBPMG501A Manage Project Integrative Processes Manage Project Integrative Processes Project Integration Processes – Part 2 Diploma of Project Management.
Instrument Control Systems Seminar, 20 October 2014 Instrument Development Process Hans Dekker.
IS&T Project Reviews September 9, Project Review Overview Facilitative approach that actively engages a number of key project staff and senior IS&T.
Rob Connatser NSS Instrument Work Packages and XLPM.
André Hoddevik, Project Director Enlargement of the PEPPOL-consortium 2009.
Prof. Shrikant M. Harle.  The Project Life Cycle refers to a logical sequence of activities to accomplish the project’s goals or objectives.  Regardless.
Collaborating for Quality through the Project Quality Plan Matthew Conlon ESS ACCSYS QA/QC Quality Learning & Planning.
1. WELCOME Project Management Cycle (P.M.C.) What is a project? : What is project management?: Project management life cycle : Phase 1 st : Phase 2 nd.
CBETA Project ALD’s Cost and Schedule Review February 6, 2017
Camera PDR/CD1 Planning 19 September 2008
AMICI WP1 – Management, coordination and dissemination
Telescope Assembly, Integration and Verification (AIV) WBS 04C. 14 J
Managing the Project Lifecycle
Status of the MICE Construction Project
ISA 201 Intermediate Information Systems Acquisition
Concluding remarks E. Migneco
CSP 25th November 2010 Technical agreement number 3: overview
Oct 22 Group Leaders Planning meeting
Chapter 6: Database Project Management
Project Management Lifecycle Phases
TechStambha PMP Certification Training
Development Projects / Analysis Projects / On-site Service Projects
PM view of SAFe SAFe Construction Planning Workshop A J Casson
Description of Revision
Chapter 4 Systems Planning and Selection
Software Project Management
Engineering Processes
SKADS Controller’s Meeting Timeline Annual Financial Report
JEFFERSON LAB LCLSII CRYOPLANT INSTALLATION PACKAGE DIRECTOR’S PROGRESS REVIEW Welcome and Introduction Stuart Henderson June 1, 2017.
Reporting 25 April 2018.
IS&T Project Reviews September 9, 2004.
FP7 SCIENTIFIC NEGOTIATIONS Astrid Kaemena European Commission
Lockheed Martin Canada’s SMB Mentoring Program
Click to add title Planning for LSST Verification George Angeli LSST All Hands Meeting Tucson August 15, 2016.
FP7 SCIENTIFIC NEGOTIATIONS
Information session SCIENTIFIC NEGOTIATIONS Call FP7-ENV-2013-two-stage "Environment (including climate change)" Brussels 22/05/2013 José M. Jiménez.
Information session SCIENTIFIC & TECHNICAL NEGOTIATIONS Call FP7-ENV-2013-WATER-INNO-DEMO "Environment (including climate change)" Brussels 24/06/2013.
Mark McKinnon EVLA Project Manager
TOP6 – WP4 Coordination and Management JPICH Coordination Office
DOD’S PHASED SYSTEM DEVELOPMENT PROCESS
MULTISPORTS CENTRE PRESENTATION
Overall Project RAG Status
Ctclink executive leadership committee May 31, 2018
PSS verification and validation
Review plan of the nature reporting – update 6
Water Directors meeting Spa, 2-3 December 2010
Test Beamline System Requirements and Charge to PDR Committee
TOP6 – WP4 Coordination and Management JPICH Coordination Office
(Project) SIGN OFF PROCESS MONTH DAY, YEAR
Schedule (Major Deliverables and Milestones)
Executive Project Kickoff
Project Kick-off <Customer Name> <Project Name>
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
{Project Name} Organizational Chart, Roles and Responsibilities
Presentation transcript:

MAORY Status of the project PAOLO CILIEGI

WELCOME TO NICHOLAS DEVANEY ALEXANDER GONCHAROV School of Physics at the National University of Ireland Galway

Short history from last November 21/12/2018 Roberto Tamai informed us that MAORY received a Red Flag due to possible consequences of the MAORY Managerial Team restructure. The decision has been taken with the goal of improving the situation and ESO will be happy to withdraw the Red Flag once the project is back on track 11/01/2019 Presentation of the new team to ESO and start of trade off and consolidation Phase. We propose 30 June 2019 to finish the trade off and consolidation phase. 6/03/2019 Progress meeting with ESO and MICADO to illustrate our acitivities 19/03/2019 Document received from ESO «Criteria for Evaluating the Level of Success of the MAORY Consolidation Phase»

Criteria for Evaluating the Level of Success of the MAORY Consolidation Phase ESO asked to use the following criteria : A feasible baseline instrument design compliant with the technical specifications and interface to the ELT, MICADO and 2 nd port instrument Design trade off report Draft risk analysis report A credible schedule for the design , development , construction, installation and commissioning of the MAORY instrument within the available budget Schedule for the complete project, fully detailed up to PDR and containing major milestones up to delivery of the instruments Cost estimate for selected baseline A functional consortium ready to take an agreed baseline to PDR and beyond Updated project management plan and work packages description Formal agreement on the instrument baseline by the MAORY steering committee

How we proceeded… A feasible baseline instrument design compliant with the technical specifications and interface to the ELT, MICADO and 2 nd port instrument Design trade off report Draft risk analysis report We introduced the System Engineering team in order to ensure that the System Overview is shared between an adequate number of people . The System Engineering Team was presented to ESO on January 2019. We improved the communication and interaction between Consortium Institutes. An example is the LGS Objective design done in collaboration between Magrin (Padova), Rabou (Grenoble) and Munari (Catania). We shared as much as possible the information also with ESO and MICADO. ESO experts (Madec for Optics, Frank for Mechanics, Kosmalski for Optica Design, Amico for System Engineerging) regularly participate in ours meetings. This was strongly appreciated by ESO Evaluation Matrix has been prepared by the MAORY team and discussed with ESO at System Engineer level (Riva – Amico) to compare the different solutions

How we proceeded… 5/4/2019 Progress Meeting with ESO (Progress Report) Section 5.4 The next key milestone in our current activity is the end of the trade off studies.  Initially scheduled at the end of June, we anticipated the delivery of the documents at the end of May, with a face to face meeting to be scheduled in the second half of June

Alternative Optical design investigated 4 parabolas based 3 spheres based Pro and Cons of all solutions have been investigsted and compared to the current baseline Collaboration with the MICADO team to evaluate the impact of alternative design on MAORY-MICADO interfaces The 4 parabolas based solution has an excellent quality but it not allow a proper optical correction due to the focal plane field curvature

How we proceeded…. A credible schedule for the design , development , construction, installation and commissioning of the MAORY instrument within the available budget Schedule for the complete project, fully detailed up to PDR and containing major milestones up to delivery of the instruments Cost estimate for selected baseline SHORT TERM SCHEDULE 7/6/2019 Delivery trade off documentation to ESO End July 2019 Consolidation Design Meeting (TBC) 31/01/2020 Delivery PDR documentation to ESO April 2020 PDR June 2020 Discussion of the MAORY Status at the ESO Council

LONG TERM SCHEDULE MAORY PROJECT 3099 02/02/2016 19/09/2028 Activity Duration (days) Start End MAORY PROJECT 3099 02/02/2016 19/09/2028 Phase B : Preliminary Design 1103 01/06/2020 Phase C : Final Design 445 02/06/2020 04/05/2022 Phase D : MAIT 1568 11/02/2021 24/08/2027 Preliminary Acceptance in Europe (PAE) 10 21/04/2027 04/05/2027 Phase E : Commissioning 275 25/08/2027 12/09/2028 FIRST LIGHT 1 21/12/2027 Provisional Acceptance in Cile (PAC)

Cost estimation OUR BUDGET Signed agreement ESO – INAF 18.500 M EUR (2015) of which 1.755 M EUR for ESO deliverable (AO WFS Cameras detector) as reported in the signed agreement 1.53970 M EUR cost incurred by INSU-IPAG (upper limit) excluding AO WFS cameras required for the production of the deliverables products of INSU-IPAS (MoU)

Component Baseline 2016 Baseline 2019 4 parabola based 2019 Post Focal relay optics including LGS Object 3559 3675 3900 Main Structure+ Opt Mounts+ICH+TCS 2000 1920 2070 Calibration Unit 200 550 550 LOR WFS (no camera) 800 800 800 LGS WFS (no camera) 1540 1400 1400 AO WFS camera (ESO deliverable) 1755 1755 1755 2 DM 6200 8820 8820 RTC 1800 3474 3474 AIV tools 200 1100 900 Shipment in Chile 200 300 300 TOTAL 18254 23794 23969 COST ESTIMATION K EUR

Actions to mitigate cost Major difference for DM , RTC and AIV tools Contact with a different providers to receive different ROM cost estimation for optics . Start a feasibility study for an alternative RTC design based on CPU (TMT-like) ( Jean Pierre Veran) Cost budget to be discussed with ESO as soon as possible

How we proceeded …. A functional consortium ready to take an agreed baseline to PDR and beyond Updated project management plan and work packages description Formal agreement on the instrument baseline by the MAORY steering committee Management Plan and WP description has been revised and delivered to ESO Also the MoU must be revised NUIG will be in charge for a WP called «Test and Wavefront Correction Verification» It will involve developing a strategy to test MAORY on Integration (possibly both in Italy and Chile). We need to determine exactly what can realistically be verified, and so, of course, the financial allocation for hardware is impossible at this point. New PM. Selected. Full time expected by September October

NEXT STEP Technical discussion with ESO

Conclusion Considerable effort has been done from the technical point of view to conclude the trade off analysis The documents nave been delivered to ESO first week of June The whole team is working well. The improved communication and collaboration between the team located in different Institutes helped to build a more compact and collaborative team The entry of NUIG as new consortium partener will consolidate the team both in technical and political terms. ESO is very positive in this regard. Some critical points remain The new PM must be involved in the project as soon as possible. Cost budget .