IS&T Project Reviews September 9, 2004. Project Review Overview Facilitative approach that actively engages a number of key project staff and senior IS&T.

Similar presentations


Presentation on theme: "IS&T Project Reviews September 9, 2004. Project Review Overview Facilitative approach that actively engages a number of key project staff and senior IS&T."— Presentation transcript:

1 IS&T Project Reviews September 9, 2004

2 Project Review Overview Facilitative approach that actively engages a number of key project staff and senior IS&T members in discussions of the success targets, dependencies, and issues of a project >Goal: Project Success There are no surprise issues in 3 months >Internal IS&T Review, but across IS&T >Proactively identify risks and generate potential mitigation strategies >Opportunity to surface issues with ‘no fear of repercussions’

3 Pre Planning Reviews should not require ‘new’ documentation Documentation should be distributed one week prior to the review Project should develop a time-boxed agenda >General reviews are 2 hours in length Attendance list is generated based on the key focus of the review

4 Target Audience Attendance list depends on: >the project’s current phase, >the timing of the review, and >the focus of the review technical, managerial, financial, business process, etc. All reviews should consist of >Key Project Staff Project Manager, Team Leader, Client Relationship Manager >Senior Members of IS&T VPs office Directors Technical Architects Financial Business Consultants Process experts Testing experts Key Managers

5 Scheduling Full scale project reviews add the greatest value when they are conducted at natural breakpoints in the project – between phases. By conducting reviews at the completion of a phase or release, the review provides the opportunity to review the project status and focus on what needs to be done to meet the next challenge

6 Project Review Information Project Overview – Description of Project Delivery Assessment >All of the delivery assessment sections should contain the following details: Overview / Status Risks and Associated Mitigation Strategy Quality analysis >Delivery Assessment Sections Customer Relationship Delivery Solution – Functional/Business Delivery Solution – Technical Project Management Processes Work Plan Staffing Partners/3 rd Parties Financial Summary Issue and Risk Management

7 Project Overview Description of project >Succinct Summary of Project Scope >Description of current phase >Why are we doing this project? What is the value of the project? Review of previous phases

8 Customer Relationship Overview / Status >Customer Expectations >Critical Success Factors >Communication Plans User training Roll out plan Risks and Associated Mitigation Strategy Quality Analysis

9 Delivery Solution – Functional/Business Overview / Status >Items to consider Business Readiness for Solution (e.g., change management, training) Risks and Associated Mitigation Strategy Quality Analysis

10 Delivery Solution - Technical Overview / Status >Items to consider Architecture considerations Production Support Plan/Training Risks and Associated Mitigation Strategy Quality Analysis

11 Project Management Processes Overview / Status >Items to consider Tools and Procedures Scope Management Risks and Associated Mitigation Strategy Quality Analysis

12 Work Plan Overview / Status >Updated Project / Task Plan Estimated vs Actual Focus on deliverables >Roadmap >Dependency Chart Risks and Associated Mitigation Strategy Quality Analysis

13 Sample Roadmap Availability of deployment box caused a major delay with a cascading effect on downstream sequential tasks 11/0312/031/042/043/044/045/046/048/0410/04 Project Kickoff Requirements Validation Deployment Box Ready Detailed Designs Code and Unit Test Today 4/19/04 Install Product Deployment Box Ready DEPLOYMENT Install Product Detailed Designs Code and Unit Test 1 Original Plan Actual = Delivery Will Move LEGEND Client Testing / UAT System Test Client Testing / UAT

14 Sample Dependency Chart Requirements Validation 11/10 Strategy Definition 11/11 Dev Server Build (box, 3 rd party, etc) 2/1912/10 Product Install 2/26 Technical Design 4/30 Design (SRM, AAB, etc) 4/12 Code and Unit Test End Date Code and Unit Test End Date 5/21 Test Server Build End Date 5/7 System Test End Date 6/18 System Test End Date 6/18 M&P, Org, Readiness End Date 7/31 End User Training End Date 10/25 Functional Training End Date 10/24 Integrated Testing (End to End, Volume, and UAT) End Date 10/22 Capacity Planning End Date 5/31 Implementation Plan End Date Target Production Support Plan End Date 9/30 Technical Training End Date 10/24 Production Server Build End Date 6/15 Dress Rehearsal End Date 10/24 DEPLOY End Date 10/31 Training Server Build End Date 7/2 6/1 IS&T Client IT Business Communication Plan End Date 7/31 Business Business Requirements 9/30 Business Strategy Design 4/16 4/20 Treatment Schedule Design 4/14 3/12 Business Client IT IS&T Consultant Business/Sponsor Target Date End Date Task Owner = DONE = ON TRACK = THREAT = JEOPARDY LEGEND IS&T

15 Staffing Overview / Status >Documented Roles and Responsibilities Includes staff and client assignments, allocations, and targeted roll off dates Risks and Associated Mitigation Strategy Quality Analysis

16 Partners / 3 rd Parties Overview / Status >Items to Consider Consultant relationships Contractual Perception/Issues Risks and Associated Mitigation Strategy Quality Analysis

17 Financials Summary Overview / Status >Project Specific Financials Project Budget IS&T Cost >Full Cost Analysis Cost of the program the project is associated with Total cost to MIT Risks and Associated Mitigation Strategy Quality Analysis

18 Issues and Risk Management Overview / Status >Issue Tracking Spreadsheet (or similar tool) Risks and Associated Mitigation Strategy >Identification and mitigation plans >Include opportunity cost (e.g., if the project extends 1 month, then that requires the staff to stay engaged on this project for 1 month) >Distribute issue summary to end users Quality Analysis

19 Sample Risk Slide Risk: Client makes resource and timing decisions without fully contemplating their downstream impacts Threat: Staffing decisions impact the work plan and the target implementation date Mitigation Strategies: Rigorously maintain the Project Plan and use it as a tool to communicate pros/cons/cause and effects of clients resource and timing decision. Maintain excellent relationship with client PM such that client adopts the good managerial practices being modeled by IS&T Previous Current

20 During Review Project Manager, or designee, should document all actions items/issues that surface during the review Action Items #Action ItemResponsible PersonDue DateStatus

21 Post Review Action items/issues should be distributed immediately upon conclusion of the review Updates should be distributed on a regular basis (e.g., weekly) until all of the action items/issues are resolved Project should provide feedback to the project review process (e.g., continuously evolving process)