What is an Operation and Misoperation

Slides:



Advertisements
Similar presentations
1 MSRATF Update to TSS (Modeling SPS and RAS Ad Hoc Task Force) Scope of Work Approval January 25, 2013 Joe Seabrook Puget Sound Energy.
Advertisements

The Western Electricity Coordinating Council Doug Tucker of WECC & Brian Keel of SRP November 16, TRD/TADS Webinar.
The Western Electricity Coordinating Council Doug Tucker Associate Engineer September 22, TRD/TADS Webinar.
Doug Tucker Associate Staff Engineer TRD/TADS update and Future reporting.
1. Four LLs were published in February Transmission Relaying – Undesired Blocking 2.Lack of Separation for Critical Control Power Supply Leads.
Transmission Operator Protection System Misoperations 2014 ERCOT Transmission Protections System Misoperations Data – 138kV and 345kV Combined (Not including.
Goshen Area Bus Reconfiguration
2014 System Operator Conference 1 Protection System Misoperations: Why Should a System Operator Give a Hoot? April 17 & May 1, 2014 – Charlotte, NC September.
SPS Mis-operation – DRAFT Proposal for ERCOT procedures.
Distribution Planning Use of SMART Distribution Automation Control System (DACS) Presented by: Ed Briggs, P.E. Created by: Ed Briggs & Greg Wickliffe
SPS policy – Information Presentation Presentation to ROS June 16, 2004.
© Property of ERCOT /06/20041 Overview of SPS in ERCOT February 5, 2004.
Summary Rich Bauer, Senior Reliability Engineer Event Analysis Subcommittee – LL Update March 04, 2014.
NERC Project S ystem Protection Coordination - PRC-027​ Presentation to the NSRS Conference Call August 17, 2015 Sam Francis Oncor Electric Delivery.
NERC Lessons Learned Summary LLs Published in September 2015.
N-1-1 Contingency Analysis & Relay Protection 4 th BTA Presentation Bob Smith Manager Transmission Planning June 6, 2006.
Loop-Sectionalizing Automation Scheme Colin Hawthorne 4/26/2016.
April 7, 2015 Washington, D.C. Area Low-Voltage Event Operations Training Seminar 2016 Erik Johnson System Operations Training (ERCOT)
Protection of Power Systems
Misoperations Reduction Strategy
NERC Published Lessons Learned Summary
Protection Relay Modeling for Transient Stability Simulation 10/26/2016 CJ Jing, David Franklin, Kevin Moran.
NERC Lessons Learned Summary
Steve Rueckert – Director of Standards
Phase Angle Limitations
Misoperation Workshop
Summary Rich Bauer, Senior Reliability Engineer
Overhead Distribution Systems
Kenneth Silver Los Angeles Department of Water & Power
EAS Lessons Learned Summary
NERC Published Lessons Learned Summary
Reducing “Unknown” Misoperation Causes
Kirha Quick Communications Specialist
Practices Short Circuit Model
NERC Published Lessons Learned Summary
PRC Implementation Plan and Summary of Devices
Western Electricity Coordinating Council
What is an Operation and Misoperation
Kenneth Silver Los Angeles Department of Water & Power
Kenneth Silver Los Angeles Department of Water & Power
Removal of Fraser RAS from RAS Databse
Workshop Session 2: Forms
Chapter 7 System Protection
Misoperations in the West: Lay of the Land
Specifications Updates and Approval
Protection Relay Modeling for Transient Stability Simulation 10/26/2016 CJ Jing, David Franklin, Kevin Moran.
Human Performance Work Group
Commissioning: Best Practices and Possible Traps
Western Electricity Coordinating Council
WECC Short Circuit Analysis
Power System Protective Relaying-Part One
$ $
WECC Performance Analysis
WECC Short Circuit Analysis
2018 State of the Interconnection Overview
How to Build a Successful Corrective Action Plan
Misoperations Reduction Strategy
Reliability Assurance Initiative (RAI) 101
Randy Spacek AvistaCorp, RWG chair
Human Performance Work Group
Commissioning: Best Practices and Possible Traps
Misoperations in the West: Lay of the Land
Kirha Quick Communications Specialist
Heather Rasmussen Communications Specialist
Removal of Fraser RAS from RAS Databse
Western Electricity Coordinating Council
TPL Voltage Guideline Presented to TSS Baj Agrawal Arizona Public Service Co. 8/21/2017.
Reducing “Unknown” Misoperation Causes
Kenneth Silver Los Angeles Department of Water & Power
Practices Short Circuit Model
Presentation transcript:

What is an Operation and Misoperation James Hanson, WECC Rich Quest, MRO Rich Bauer, NERC Western Electricity Coordinating Council

Western Electricity Coordinating Council Example 1 A permanent fault occurs on Line A. Both ends trip and reclose (two attempts) to lockout. How many operations and misoperations should be reported? Western Electricity Coordinating Council

Example 1 – Survey Results Western Electricity Coordinating Council

Western Electricity Coordinating Council Example 1 - Reason When reclosing is applied (automatic or manual), a sequence of reclosing and tripping associated with isolating a faulted system Element is counted as a single operation. Multiple unintended operations of an Element due to this sequence of reclosing and tripping would also be counted as a single operation. Reference: MIDAS Reporting Template – Definition of Protection System Operation Western Electricity Coordinating Council

Western Electricity Coordinating Council Example 2 A permanent fault occurs on Line D. The Line D breakers trips, but a breaker on Line E overreaches and trips incorrectly. How many operations and misoperations should be reported? Line A Line B Line C Line D Line E Western Electricity Coordinating Council

Western Electricity Coordinating Council Example 2 - Poll Two operations, one misoperation No operation, one misoperation One operation, one misoperation None of the above Western Electricity Coordinating Council

Example 2 - Answer Two operations, one misoperation Correct Answer: Western Electricity Coordinating Council

Western Electricity Coordinating Council Example 3 A breaker on Line D trips due to a failed relay with no fault. How many operations and misoperations should be reported? Line D Line E Western Electricity Coordinating Council

Western Electricity Coordinating Council Example 3 - Poll No operation, one misoperation One operation, no misoperation One operation, one misoperation None of the above Western Electricity Coordinating Council

Example 3 - Answer One operation, one misoperation Correct Answer: Reason: No misOPERATION without an OPERATION Western Electricity Coordinating Council

Western Electricity Coordinating Council Example 4 A fault occurs on Line A. The left terminal breaker fails to trip. The remote ends of Line D and E trip. In this case, the left terminal breaker does not have breaker failure protection. How many operations and misoperations should be reported? Western Electricity Coordinating Council

Western Electricity Coordinating Council Example 4 - Poll Three operations, one misoperation Two operations, one misoperation Three operations, no misoperation None of the above Western Electricity Coordinating Council

Western Electricity Coordinating Council Example 4 - Answer Correct Answer: Three operations Western Electricity Coordinating Council

Western Electricity Coordinating Council Example 5 During scheduled maintenance a relay operates. How many operations and misoperations should be reported? Western Electricity Coordinating Council

Western Electricity Coordinating Council Example 5 - Poll No operation, no misoperation One operation, one misoperation One operation, no misoperation None of the above Western Electricity Coordinating Council

Example 5 - Answer No operation, no misoperation Correct Answer: Western Electricity Coordinating Council

Western Electricity Coordinating Council Example 6 A fault occurs on Line A. The left terminal breaker fails to trip. The remote ends of Line D and E trip. In this case, the left terminal breaker has breaker failure protection. How many operations and misoperations should be reported? Western Electricity Coordinating Council

Western Electricity Coordinating Council Example 6 - Poll Three operations, one misoperation Two operations, one misoperation Three operations, no misoperation None of the above Western Electricity Coordinating Council

Example 6 - Answer Three operations, one misoperation Correct Answer: Western Electricity Coordinating Council

Western Electricity Coordinating Council Example 7 XYZ end of ABC - XYZ 345kV line tripped and reclosed. The misoperation occurred again at 12:27, 13:08, and 13:44. Tripping was due to a misoperating transfer trip receiver. How many operations and misoperations should be reported. Western Electricity Coordinating Council

Western Electricity Coordinating Council Example 7 - Poll Three operations, three misoperations One operation, one misoperations No operation, one misoperation Three operations, one misoperation Western Electricity Coordinating Council

Example 7 - Answer One operation, one misoperation Correct Answer: Western Electricity Coordinating Council

Western Electricity Coordinating Council Example 8 Entity 1 and Entity 2 jointly own Line A. A permanent fault occurs on Line A. Both ends trip and reclose (two attempts) to lockout. One operation and no misoperation should be reported. Who should report? Western Electricity Coordinating Council

Western Electricity Coordinating Council Example 8 - Poll Both entities report. The report includes no notes about joint ownership. The entities communicate and both entities report. The reports include notes that Line A is jointly owned and that both entities are reporting. The entities communicate and decide only one entity will report. Western Electricity Coordinating Council

Western Electricity Coordinating Council Example 8 - Answer Correct Answer: The entities communicate and decide only one entity will report. Western Electricity Coordinating Council