Dogleg Review 2-1-131 Dogleg Upgrade Tommy Hiatt Magnet Modifications.

Slides:



Advertisements
Similar presentations
Smartphone Outlook Android Overview Youngmin Jung.
Advertisements

Robert P. Dick, Ganesh Lakshminarayana, Anand Raghunathan, and Niraj K. Jha Design Automation Conference, 2000 Reporter: Keng-Mao Cho Advisor: Prof. Chu-Sing.
Tagger and Vacuum Chamber Assembly Procedure. Outline. Assembly procedure for tagger and vacuum chamber. Support stands. Alignment.
Overview of the GlueX Tagger and Photon Beamline..
Real-time software Sommerville, Hfst. 13. Sommerville, Ch. 132 Real-time systems A real-time system is a software system where the correct functioning.
11 March 2012 Holger Witte Brookhaven National Laboratory Advanced Accelerator Group A Dipole (without) Grain Oriented Steel.
Existing Arcs and 4m Dipole Preliminary Design and Safety Review Beam Transport Interface Mike Bevins February 22, GeV Upgrade - Beam Transport.
The eXtensible Markup Language (XML) An Applied Tutorial Kevin Thomas.
12GeV Project CD-4 Leigh Harwood Associate Project Manager Accelerator Systems.
Creative Commons: A very quick introduction 10/12/ Mic Porter.
Comparison of Particle Production between MARS and FLUKA (Update) X. Ding, UCLA Target Studies Aug. 8, /8/13.
Planned FCC Power Outage July 11, ARRA Feynman ARRA construction project requires completion by September 30 th. This constraint.
Lecture 131 EEE 302 Electrical Networks II Dr. Keith E. Holbert Summer 2001.
Proton Source Workshop Booster Downtime Wednesday, December 8, 2010 T. Sullivan.
KICKOFF AS PRESENTED 6/17/11, SEE THIS WEEKS SCHEDULE FOP THE LATEST UPDATE Shutdown Shutdown ‘11.
David H. Dowell Injector RF Design November 3, LCLS Injector RF Gun: Design, Fabrication & Tuning Plans D. H. Dowell,
§5.2: Biot-Savart Law Christopher Crawford PHY
LINACs Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review.
Computer-Assisted Drug Design (1) i)Random Screening ii)Lead Development and Optimization using Multivariate Statistical Analyses. iii)Lead Generation.
UVA Polarized Target In Hall A Pictures and Cost Paul Brindza Dec 17, 2009.
Polarized 3 He Target for 12 GeV Experiments J. P. Chen, August 15, 2012, JLab  Experiments and requirements  Target performance from previous experiments.
Learning Lesson Plan: ____________________ Consistent with Theme 10 Objectives210 Time Schedule210 Supplies3210 Attention Grabber 210 Detailed Description.
Proton Plan Director's Review 8/15/06 – Booster Corrector UpgradeDrennan1 Proton Plan Booster Corrector Upgrade Directors Review August 2006 Presenter:
Injector/Re-injection Chicane Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design.
Facts about the sun Sun Cycle Layers of the sun Sun’s Energy Terms Magnetic field $ 200 $ 200$200 $ 200 $ 200 $400 $ 400$400 $ 400$400 $600 $ 600$600.
F Booster Long Straight Corrector Upgrade Technical Status and Schedule for Installation Craig Drennan DOE Tevatron Operations Review March 27, 2007.
LER Workshop, CERN, October 11-12, 2006Detector Safety with LER - Henryk Piekarz1 LHC Accelerator Research Program bnl-fnal-lbnl-slac Accelerator & Detector.
PEPII Magnet Feasibility in the MEIC ECR Tommy Hiatt – MEIC Collaboration 10/07/ of 15.
G2p/gep Beamline Project Overview Tim Michalski Project Lead.
1 Tim Michalski October 6, 2015 Engineering Issues in MEIC.
AHCAL Mechanics status report Karsten Gadow CALICE Collaboration Meeting Argonne,
BIA’s Director Review, September Accelerator Improvements FY11-16 Fulvia Pilat.
Accelerator Science and Technology Centre POST-LINAC BEAM TRANSPORT AND COLLIMATION FOR THE UK’S NEW LIGHT SOURCE PROJECT D. Angal-Kalinin,
Extraction Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review.
Accelerator Science and Technology Centre POST-LINAC BEAM TRANSPORT AND COLLIMATION FOR THE UK’S NEW LIGHT SOURCE PROJECT D. Angal-Kalinin,
Some Value Engineering Proposals For LBNE Beamline.
XFEL X-Ray Free-Electron Laser Bernward Krause MEA WP-12: Warm Magnets WPL: B. Krause.
Spreaders & Recombiners Beam Transport Michael Bevins May 30, GeV Upgrade - Beam Transport Spreader/Recombiner Dipoles and Layout, & Installation.
Dave Johnson July 12, 2010 NOvA/ANU Recycler Upgrades Review Optics, Apertures, and Operations Nova-doc 4930.
Hall A Installation Review John J. LeRose 2/25/2009.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
Dave Johnson July 12, 2010 NOvA/ANU Recycler Upgrades Review Optics, Apertures, and Operations Nova-doc 4930.
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
August 2007 Booster RF Upgrades J.Reid Booster RF Upgrades West Gallery LCW modifications: – Headers in select locations to be upgraded by.
PAC Meeting, December 12, Prebys 1 The Problem.
F James T Volk Arpil Permanent Magnets for Linear Colliders James T Volk Fermilab.
P1, P2 and AP-1 Aperture Improvements February 5, 2015 J. Morgan 1.
MI/RR Shutdown 2012 Dec Gev Lines/Injection region: Staging equipment, cleaning and prepping new part to start vacuum work. Preparing to modify the.
St. George Infrastructure
7. Quantum-Mechanical View of Atoms
SBS- Counterweight Support and Magnet Assembly - Status
Joseph Meyers Magnet Measurement Facility
Hall A Infrastructure and the Moller Parity Experiment “AMPEX”
Exchange Rate Determination
MDL0L02 Dipole Hysteresis Loop Study
III. Correction Dipoles MDG Accessories for all Magnets V. Summary
Performance Recovery at CEBAF
ILC Main Linac Superconducting Splittable Quadrupole
Hall C Beamline Upgrade
IR Upgrade Possibilities for PEP-II
Study on Emittance Reduction with a Robinson Wiggler in HEPS
7. Quantum-Mechanical View of Atoms
Extraction Michael Bevins May 17, 2007
Similarities Differences
RHIC Magnets for JLEIC Yuhong Zhang May 11, 2018.
Electron Collider Ring Magnets Preliminary Summary
Bunch Compressor Beam Line Optics
Feasibility of Recuperation of Magnets in Decommissioned Storage Rings
The Feasibility of Using RHIC Magnets for MEIC and Cost Impact
ESR2 Process Cycle Design
Presentation transcript:

Dogleg Review Dogleg Upgrade Tommy Hiatt Magnet Modifications

Dogleg Review Outline Requirements Design Approach Mechanical Design Modeling Performance Schedule Summary

Dogleg Review Modification Requirements Design modifications to dipoles so that the dogleg dipoles meet the specified BL requirements Constraints –Use same type of power supply for each string –Modifications compatible with existing stands –Magnet deinstallation-modification-measurement- reinstallation must fit within UIM down (summer 2014) Dipoles affected –Dog3 – 1 BX dipole –Dog4 – 1 BX dipole and 2 BW dipoles

Dogleg Review Design Approach Use similar approach as the 12 GeV dipoles –Minimize Cost –Reuse existing magnet cores –Limit temperature rise in LCW to be consistent with 12 GeV Upgrade (<40C dT) –Use lengthening shims or field shaping shims if needed on modified magnets Repurpose or procure steel to increase core length Minimize additional LCW consumption Remove / touch as few magnets as possible

Dogleg Review Mechanical Design Dogleg dipoles have published field maps on a 300 A loop –Dog1 will operate within that range at 167 A All other dipoles will be pushed to higher currents –Some will meet the BL requirements by just pushing the current Dog2 – 318 A Dog5 – 365 A Dog6 – 389 A Dog7 – 414 A Dog8 – 396 A Dog9 – 413 A –Others will need mechanical modification to achieve BL Dog3 BX – new coils Dog4 – new coils and more steel

Dogleg Review Mechanical Design Modify Dog3 BX –Use larger cross section coil (BZ conductor) –No coil pocket mods necessary –No lengthening steel added Modify Dog4 BWs –Use larger cross section coil (BZ conductor) –Modify coil pocket (remove steel) –Add face shim to make up for part of the coil pocket mod. –Add ~30 cm of lengthening steel Modify Dog4 BX –Use larger cross section coil (BZ conductor) –No coil pocket mods necessary –Add ~60 cm of additional steel

Dogleg Review Mechanical Design BX Modifications (1 in Dog3 and 1 in Dog4) –Use larger cross section coils –Dog3 – no lengthening steel –Dog4 – ~60cm of additional steel Dog 4 BX Modifications

Dogleg Review Mechanical Design BW Modification (2 in Dog4) –Use larger cross section coils –Modify coil pocket –Use face shim to make up for part of the coil pocket modification Dog 3 BW Modifications

Dogleg Review Mechanical Design Mechanical changes result in –3 modified coil designs 2 for BX (with and without steel addition) 1 for BW –31 ft 3 of additional steel required Lengthen 3 dipoles –Decision point on steel acquisition options Option 1 – Obtain permission to use excess 12 GeV spare steel –Billets were purchased as back up steel for catastrophic machining or handling of S/R and arc dipoles. 2 – 3m steel billets on hand Dogleg upgrade will consume 2 billets 6 – 1m steel billets on hand Dogleg upgrade will consume 2 billets Option 2 – Purchase the steel billets that we need (similar to 12 GeV) and machine (~$65k) Option 3 – Design for 1 plate laminates (something readily procure-able) and purchase plate

Dogleg Review Modeling Linear extrapolations were done to calculate preliminary BL Tosca models were used to –confirm saturation effects for Dog3 and Dog4 –dial in exact lengths of additional steel for Dog4

Dogleg Review Modeling Use TOSCA to confirm B 0 at high currents Dog3 BX at A, B 0 = 8421G (1/4 symmetry, vert. and hor.) Dog 4 BW at A, B 0 = 7390 G (1/2 symmetry, horizontal only) Scale is ,000 GScale is 10, ,000 G Scale is ,000 GScale is 10, ,000 G

Dogleg Review Performance DogCurrent B 0 (linear) Total Voltage Total Flow LCW Max dT (A)(G)(V)(gpm)(C) – BY 7189 – BZ – BY 7656 – BZ – BY 8148 – BZ – BY 7794 – BZ – BY 8127 – BZ 58621

Dogleg Review Performance BL without modifications DogDipoleCurrent Tosca B 0 dLBL Required BL - -(A)(G)(cm)(G-cm) 3 BX ,098837,196 4 BW ,145588,806 4 BX ,8991,177,612

Dogleg Review Performance BL with modifications DogDipoleCurrent Tosca B 0 dLBL Required BL - -(A)(G)(cm)(G-cm) 3 BX ,098837,196 4 BW ,849588,806 4 BX ,177,6911,177,612

Dogleg Review Schedule Coils –~12 month lead time –Complete detailed design and drawings by March 2013 (drop dead) –PO finalized by end of April 2013 (drop dead) –Ready for magnet assembly by May 2014 Steel –Decision of option path by Feb. 22, 2013 (drop dead) –Complete detailed design drawings in next 12 months –Ready for magnet assembly by May 2014

Dogleg Review Summary Most dogleg dipoles meet BL requirements with current increase only Some dipoles will require lengthening steel and new coils Will need to purchase 3 families of coils Will need 30.6 ft 3 of steel This work is understood and similar to recent work done for 12 GeV

Dogleg Review Questions?

Dogleg Review backup

Dogleg Review backup

Dogleg Review backup Machine Shop work –2 machinist at 1 week per dipole half 2 BW, 1 BX = 6 dipole halves 2 x 6 = 12 man-weeks (12*40*$55 = $26.4k) Refurb work –2 MT at 1 week per dipole 2 BW, 2 BX = 4 dipoles (4 * 2 * 1 * $1.3k = $10.4k) Installation –Tooling Design 1 MD for 5 weeks = (1 * 5 * $1.3k = $6.5k) –Tooling cost - $5k –Ripout – 6 MT at 2 weeks each side (6 * 2 * 2 * $1.3 = $31.2k) –Install – 6 MT at 4 weeks each side (6 * 4 * 2 * $1.3 = $62.4k) –Vacuum – half of Install estimate = $31.2k –Alignment – 2 MT for 2 week (2 * 2 * $1.3 = $5.2k) –My estimate (above = $141k) Neils estimate 209 man days = $95k