F Booster Long Straight Corrector Upgrade Technical Status and Schedule for Installation Craig Drennan DOE Tevatron Operations Review March 27, 2007.

Similar presentations


Presentation on theme: "F Booster Long Straight Corrector Upgrade Technical Status and Schedule for Installation Craig Drennan DOE Tevatron Operations Review March 27, 2007."— Presentation transcript:

1 f Booster Long Straight Corrector Upgrade Technical Status and Schedule for Installation Craig Drennan DOE Tevatron Operations Review March 27, 2007

2 f 2007 DOE Tevatron Operations Review – C. Drennan 2 Long Straight Corrector Upgrade STATUS AND INSTALLATION PLANS  Goal of the Corrector Upgrade  Corrector Magnet Status  Magnet Stands and Installation Plans  Power Supply Status and Schedule  Power Cables and Rack Installation  Corrector Control Status

3 f 2007 DOE Tevatron Operations Review – C. Drennan 3 Long Straight Corrector Upgrade  The Long Straight Corrector Upgrade will install 24 new corrector magnets for improved beam control in the vertical plane.  The 24 short straight correctors will be upgraded during the 2008 shutdown.

4 f 2007 DOE Tevatron Operations Review – C. Drennan 4 Corrector Goals  Specifications for new corrector system:  Position Control: Be able to produce 1 cm of beam motion at highest beam energy (8GeV). Be able to slew position 1 mm/ms up to the middle of the cycle.  Tune Control: Maintain tune arbitrarily close to upper integer resonance throughout cycle. Be able to switch from full field plus to full field minus in ~2 ms in order to rapidly switch tunes at transition time.  Sextupoles Total strength consistent with existing system. Increase slew rate to rapidly switch chromaticity at transition time.

5 f 2007 DOE Tevatron Operations Review – C. Drennan 5 Meeting the Goals

6 f 6 Long Straight Corrector Upgrade The first corrector package prototype in test stand at the Magnet Test Facility.

7 f 2007 DOE Tevatron Operations Review – C. Drennan 7 Long Straight Corrector Upgrade CORRECTOR MAGNET STATUS  Magnet Tests on First Prototype, BMA000  Thermal Tests (Passed), Beams-doc-2713-v1 Test performed at full supply current and maximum specified RMS current. Tested with full, half, and no water flow.  Electrical Parameters (Passed), Beams-doc-2700-v1 Simple measurement of magnet inductance and resistance  DC Field Strengths (Passed), Beams-doc-2711-v1 Meets booster specifications Field strengths measured along with hysteresis  DC Field Shapes (Passed), Beams-doc-2712-v1 Excellent to +/- 25 mm, Good to +/- 38 mm

8 f 2007 DOE Tevatron Operations Review – C. Drennan 8 Long Straight Corrector Upgrade CORRECTOR MAGNET STATUS  Magnet Tests on First Prototype, BMA000 --continued—  AC Slew Rate and Field Strength (Passed), Beams-doc-2714-v1  Field Harmonics Testing (Passed)  Other Corrector Documents  Coordinate System: Booster Corrector Magnet System Beams-doc-2632-v2  Specification For The Booster Corrector Magnets And Power Supplies, Beams-doc-1881-v5  Current Schedule  Core production well ahead of schedule.  First production coil set arrived 3/15/2007  First production corrector package complete 6/22/2007  24 th corrector package complete 8/27/2007 Detailed Schedule available upon request – cdrennan@fnal.gov

9 f 9 Long Straight Corrector Upgrade Status of BPM’s  New BPM's have been designed and will be available for installation. A late design revision was made in Feb. 2007 Reference Jim Crisp, “Proposed Booster BPM Geometry”, Beams-doc-2221-v1

10 f 2007 DOE Tevatron Operations Review – C. Drennan 10 Long Straight Corrector Upgrade MAGNET STANDS AND INSTALLATION PLANS  New Stands are being design for the Corrector installation.  22 Locations use the standard design.  2 Locations require their own design.

11 f 2007 DOE Tevatron Operations Review – C. Drennan 11 Long Straight Corrector Upgrade  Standard Installation

12 f 2007 DOE Tevatron Operations Review – C. Drennan 12 Long Straight Corrector Upgrade  New Corrector Support

13 f 2007 DOE Tevatron Operations Review – C. Drennan 13 Long Straight Corrector Upgrade Special Case 1: L3 Dogleg  The new corrector package will mount between the dogleg magnets and the BEX magnet will move to where the current corrector is now.

14 f 2007 DOE Tevatron Operations Review – C. Drennan 14 Long Straight Corrector Upgrade Special Case 2: Injection Girder

15 f 2007 DOE Tevatron Operations Review – C. Drennan 15 Long Straight Corrector Upgrade  Mechanical Design Schedule

16 f 2007 DOE Tevatron Operations Review – C. Drennan 16 Long Straight Corrector Upgrade  Mechanical Installation Schedule

17 f 2007 DOE Tevatron Operations Review – C. Drennan 17 Long Straight Corrector Upgrade POWER SUPPLY STATUS AND SCHEDULE  New 40 Amp and 65 Amp power supply designs are tested and ready for production assembly bidding.

18 f 2007 DOE Tevatron Operations Review – C. Drennan 18 Long Straight Corrector Upgrade POWER SUPPLY STATUS AND SCHEDULE  Power Supply Production Schedule  Bid construction 3/19/2007 to 4/9/2007  Award contract 4/16/2007  Receive first units 5/7/2007  Receive 15 units per week 5/14/2007 to 7/2/2007  Production unit testing 5/21/2007 to 7/23/2007  Installation into Booster racks 6/11/2007 to 7/30/2007

19 f 2007 DOE Tevatron Operations Review – C. Drennan 19 Long Straight Corrector Upgrade POWER CABLES AND RACK INSTALLATION  Power cables are expected to arrive 3/31/2007 and will be pulled during the shutdown.  Sample run of cables have been tested in a Booster penetration

20 f 2007 DOE Tevatron Operations Review – C. Drennan 20 Long Straight Corrector Upgrade POWER CABLES AND RACK INSTALLATION  Rack mock up is being built in the Transfer Gallery area  This will include full set of amplifiers, bulk supply, control and monitoring electronics, and cooling hardware.  Empty Racks have been install in all 6 locations in the Booster gallery.  Racks have been equipped with the basic hardware and the AC power installation has begun.

21 f 21 Long Straight Corrector Upgrade Corrector Control Status  New Power Supply Ramp Controllers Available 5/30/07  Will output ACNET programmable current reference curves for the power amplifiers and monitor amplifier tracking.  Controller specifications available, Beams-doc-1882-v3  CAMAC C473 Users Manual available, Beams-doc-2361-v2

22 f 22 Long Straight Corrector Upgrade  ACNET / Software to support the new CAMAC ramp controller is available and in use in test areas.  The path for making the significant number of database entries and implementing the device change over is being charted.